| 1 | Earth work excavation of foundation trench in hard soil within 1.50m initial lift and depositing the excavated materials with 50m.initial lead including all cost of labour and materials required for the work etc. complete and as directed by Engineer-in-charge. |
| 2 | Filling in foundation and plinth with sand well watered and rammed including all cost of labour and material required for the work etc. complete and as directed by Engineer-in-charge. |
| 3 | Cement Concrete (1:4:8) with 4 cm. size hard granite metal in foundation with all cost of labour and material required for the work etc. complete and as directed by the Engineer-in-charge. |
| 4 | Brick work with Fly ash Brick in foundation & Plinth in cement mortar (1:6)including cost of all material and labour required for the work etc. complete and as directed by Engineer-in-charge. |
| 5 | Cement Concrete (1:5:10) with 4 cm. size hard granite metal(CB) in foundation with all cost of labour and material required for the work etc. complete and as directed by the Engineer-in-charge. |
| 6 | RCC of M-20 grade with 20mm and down grade sizeblack hard granite crusher broken chips for R.C.C work with all cost of labour and material required for the work etc. complete and as directed by the Engineer-in-charge. |
| 7 | Supplying and Labour charges for cutting, bending, binding& tying the grills of HYSD rod and placing the grills in proper position including cost of ms rod(SAIL) with all taxes, royalty and labour required for the work etc. complete and as directed by Engineer-in-charge. |
| 8 | Rigid and smooth centering & shuttering for R.C.C work including false work and dismantling then after curing period of casting with all cost of labour and material required for the work etc. complete and as directed by Engineer-in-charge. ( i )Column Base & Plinth Band |
| 9 | Rigid and smooth centering & shuttering for R.C.C work including false work and dismantling then after curing period of casting with all cost of labour and material required for the work etc. complete and as directed by Engineer-in-charge. (ii) Lintel and wall beam |
| 10 | Rigid and smooth centering & shuttering for R.C.C work including false work and dismantling then after curing period of casting with all cost of labour and material required for the work etc. complete and as directed by Engineer-in-charge. (iii) Column and beam |
| 11 | Rigid and smooth centering & shuttering for R.C.C work including false work and dismantling then after curing period of casting with all cost of labour and material required for the work etc. complete and as directed by Engineer-in-charge. (iv) Slab, chhaja and landing |
| 12 | Brick work with Fly ash Brick in superstructurein cement mortar (1:6)including cost of all material and labour required for the work etc. complete and as directed by Engineer-in-charge. |
| 13 | 16mm. thickplastering in cement mortar (1:6)including cost of all material and labour required for the work etc. complete and as directed by Engineer-in-charge |
| 14 | 12mm. thickplastering in cement mortar (1:6)including cost of all material and labour required for the work etc. complete and as directed by Engineer-in-charge |
| 15 | 20mm. thickplastering in cement mortar (1:4)including cost of all material and labour required for the work etc. complete and as directed by Engineer-in-charge |
| 16 | Fixing of Kota Tile in floors, treads steps and landing on 25 mm thick bed of cement mortar (1:1) joint with neat cement slury atc. and as per direction of Engineer in charge. |
| 17 | Fixing of Kota Tile in Dado, Riser on cement mortar (1:3) joint with neat cement slury etc. and as per direction of Engineer in charge. |
| 18 | Fixing of chequered Tile in floors, treads steps and landing on 25 mm thick bed of cement mortar (1:1) joint with neat cement slury atc. and as per direction of Engineer in charge. |
| 19 | Supplying, fitting & fixing of M.S Doors, Windows & Grills in proper position including cost of all material and labour required for the work etc. complete and as directed by Engineer-in-charge. |
| 20 | Painting 2 coats with approved enamel paint over 1 coat of red oxide primer on new works comp. with all cost of materials & labours |
| 21 | Wall putty 2 coats with Acrylic wall putty on new works complete including cost of all material and labour required for the work etc. complete and as directed by Engineer-in-charge. |
| 22 | Wall painting two coats with approved shed of plastic emulsion paint over 1 coat of wall primer including cost of materials and labours etc. and as per direction of Engineer in charge |
| 23 | Finishing wall two coats with approved weather coat over 1 coat of wall primer including cost of materials and labours etc. and as per direction of Engineer in charge. |
| 24 | Supplying, fitting and fixing of Stainless Steel of 304 grade in hand railing using 50mm dia of 2mm thick circular pipes with Balustrade of size 32mm x32mmx 2mm @ 0.90m c/c and stainless square pipe bracing of 32mm x 32mmx 2mm in three rowa in stair case as per approved design and specifications buffing, polishingincluding cost, carriage,royalty etc complete. ( Data for 3.26 Rmt )Revised A/ R(Building) -2012, Item no - 11. |
| 25 | Recessed wiring to light point/fan point/exhaust fan point/callbell point with 1.5 sqmm FR PVC insulated single core multistarand copper conductor of ISI marked with 20mm dia non metallic PVC flexble conduit with 5AMP 250V paino Group (A) Finolex/L&T/Anchor/Havell/Vguard |
| 26 | Recessed wiring to light point/fan point/exhaust fan point/callbell point with 1.5 sqmm FR PVC insulated single core multistarand copper conductor of ISI marked with 20mm dia non metallic PVC flexble conduit with 5AMP 250V paino Group (B) Finolex/L&T/Anchor/Havell/Vguard |
| 27 | Recessed wiring to light point/fan point/exhaust fan point/callbell point with 1.5 sqmm FR PVC insulated single core multistarand copper conductor of ISI marked with 20mm dia non metallic PVC flexble conduit with 5AMP 250V paino Group (C) Finolex/L&T/Anchor/Havell/Vguard |
| 28 | S/F of5A Switch/Socket on the existing switch box& cover |
| 29 | Circuit submain wiring in PVC conduit(Finolex/Anchor) 2x1.5 sqmm+1 |
| 30 | Circuit submain wiring in PVC conduit(Finolex/Anchor) 2x2.5 sqmm+1 |
| 31 | Circuit submain wiring in PVC conduit(Finolex/Anchor) 2x4 sqmm+1 |
| 32 | S/F Fiiting of BK ANGLE HOLDER ISI MARK |
| 33 | S/F CEILING FAN 48\" AC FAN(Bajaj /Usha) |
| 34 | S/F CEILING FAN 9\" AC FAN(Bajaj /Usha) |
| 35 | S/F of 9 Watt LED Bulb |
| 36 | S/F of 20 Watt LED Bulb |
| 37 | S/F of4 way MCB DB single door |
| 38 | S/F ofB series SP MCB(Havells/HPL/Anchor) |
| 39 | S/F of 32Amp DP Main switch (HPL/Anchor) |
| 40 | S/F of standard earthing |
| 41 | S/F No.8 SWG copper wire |