| 1 | Earth work excavation for foundation in all soils and sub soils and to full depth as may be directed except in rock requiring blasting but inclusive of shoring and strutting and balling out water wherever necessary refilling the sides of foundation with excavated earth in layers of not morecomplete complying with standard specification |
| 2 | Plain Cement concrete 1:4:8 mix(one cement ,four M.sand and eight aggregate) using 40mm ISS HBG metal including cost andconveyance of all materials to site and all labour charges for mixing, laying, consolidatingand curing etc., complete as per standard specification. |
| 3 | Supply and errection of steel centering for RCC works using MS sheets and angles and strutting upto 3.00M in height including cost and conveyance of all materials to site and all labour charges etc completeFooting & Grade beam |
| 4 | Column |
| 5 | Roof Beam & Slab |
| 6 | Reinforced cement concrete 1:1 1/2 :3mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying, finishing and curing etc complete. |
| 7 | Supply and fabrication of steel for R.C.C work using R.T.S & M.S rod includingcost and conveyance of all materials to site all labour charges etc complete as per standard specification. |
| 8 | Re-filling the excavation earth filing including cost and conveyance of all materials to site and all labour charges etc complete as per standard specification. |
| 9 | Filling with 40 mm BSS HBG metal from approved quarry and including cost and conveyance of all materials to site and all labour charges etc complete as per standard specification. |
| 10 | Brick work in cement mortar 1:5 mix (one Cement, Five Sand) using best quality of country bricks including curing cost and conveyance of all materials to site and all labour charges etc., complete as per standard specification. |
| 11 | Honeycomb brick work in cement mortar 1:5 mix (one Cement, Five Sand) using best quality of country bricks including curing cost and conveyance of all materials to site and all labour charges etc., complete as per standard specification. |
| 12 | Plastering with cement mortar 1:3 mix (One cement and three sand) to 12mm thick includingcuring cost and conveyance of all materials to site and all labour chargesetc., complete as per standard specification |
| 13 | Plastering with cement mortar 1:3 mix (One cement and three sand) to 10mm thick includingcuring cost and conveyance of all materials to site and all labour chargesetc., complete as per standard specification |
| 14 | Plastering with cement mortar 1:5 mix (One cement and five sand) to 12mm thick includingcuring cost and conveyance of all materials to site and all labour chargesetc., complete as per standard specification |
| 15 | Paving the floor with design coloured scratch proof ceromic tiles of size 305 x 305 x 6mm of best quality and approved variety complying / confirming ISI specification land over cement mortar 1:3 (one cement and three sand) 20mm thick and pomted with same coloured cement neatly etc., complete. |
| 16 | Dadooing the walls with glazed tiles of 15 c.m x 15c.m 6mm size laid in cement mortor 1:2 mix 10mm thick and pointing with 0.40 kg white cement and including cost and conveyance of materials and all labour charges and all etc.,complete complying with standard specifications. |
| 17 | Weathering course withCM 1:3 mix over brick jelly concrete in lime mortor over the RCC roof slab, in the proportion of 32:12.50,80mm thick.includingcost and conveyance and labour charges etc.complete |
| 18 | Finishing the top with one course of machine pressed tiles on 200x200x20mm. Thick of approved quality laid in cement mortar 1:3 (1 of cement and three of sand) mixed with water proff compounds 2% by weightof cement used and the top pointed with the same mortar etc., complete - 10m2 |
| 19 | Painting two coats with Emulsion Paint over plastered wall surface including cost and conveyance of all materials to site and all labour charges etc complete. |
| 20 | Painting twocoats with ready mixed paint for new iron work including cost of all materials to site and all labour charges etc complete. |
| 21 | Supplying and fixing of Oriyapan indian type water closet and including cost and conveyanceof all materials to siteand all labour charges etc |
| 22 | Supplying and fixing of Urinal ladies and including cost and conveyanceof all materials to siteand all labour charges etc |
| 23 | Supplying and fabrication of the following steel doorof Size 1.00x1.80mworks including cost and conveyanceof all materials to siteand all labour charges etc |
| 24 | Supplying and fabrication of the following Bison door of Size 0.80x1.80mworks including cost and conveyanceof all materials to siteand all labour charges etc |
| 25 | Towards the supply and fixing of jali of size 0.45x0.30m-6 Nos including all cost and conveyance cost of all materials and labour charges etc complete |
| 26 | Supplying and fixing of RCC precost slab 75 mm thick and including cost and conveyanceof all materials to siteand all labour charges etc |
| 27 | Supplying and fixing ofCuddappah slab 50 mm thick and including cost and conveyanceof all materials to siteand all labour charges etc |
| 28 | Wiring with 2 x 1.5 sq.mm. PVC insulated SC unsheathed FRLS copper conductor of 1100V grade in suitable PVC rigid pipe on wall and ceiling with PVC accessories and with TW switch box and 5A FT switch with painting of suitable colour for open PVC light point / fan point (for electronic regulator)(SD No. 20) |
| 29 | Supply and fixing of single box type 4\"40W fluorescent fitting complete with copper choke and condensor with TW round blocks on wall or ceiling with flu tube with PVC unsheathed FRLS copper leads from terminals to the fitting [SD88] |
| 30 | Supply and fixing of WT bulk head fitting with guard suitable with 7W / 9W LED bulb . [SI 84] |
| 31 | Provision fortowards the suppling and fixing of rainwater downfall4\" PVC pipe including all cost and conveyance etc complete. |
| 32 | Supply and fixing of2000 lit HDPE Tank ISI make with all accessories such as Tank Nipple, Washer etc., including cost and conveyance of all materials to site etc., complete as per standard specifications. |