| 1 | Loading, Carriage of RMU |
| 2 | Installation of RMU |
| 3 | Making plinth and Grouting ofRMU |
| 4 | 3 Ft chemical Earthing with material |
| 5 | Energisation of RMU |
| 6 | Taking out 11 KV cable from drum/complete drum of cable from store its loading carriage and safe unloading by truck/bullock cart at site of work or vice-versa. |
| 7 | Digging of Trench for laying of 11 KV and 33 KV cable in normal soil in size of 30 cm. wide and 1 to 1.5 meter deep. |
| 8 | Digging of Trench for laying of 11 KV and 33 KV cable in kharanja soil in size of 30 cm. wide and 1 to 1.5 meter deep. |
| 9 | Digging of Trench for laying of 11 KV and 33 KV cable in metallic road in size of 30 cm. wide and 1 to 1.5 meter deep. |
| 10 | Laying of Cable by HDD Method |
| 11 | Laying of 11 KV and 33 KVXLPE cable in above digged trench covering with bricks and back filling and proper ramming. |
| 12 | Laying of cable pole to pole |
| 13 | Making indoor/outdoor joints of 11 KV and 33 KV XLPE Cable where the cable is being laid. |
| 14 | Mounting of all types of cable box on pole as well as on H.T.P.B./Outdoor Metering Cubical/H.T.M.C. the work includes proper clamping of cable box on both ends with pipe provided by KESCo |
| 15 | Loading, Carriage and unloading of ST poles including old & used S.T. Pole from store to work site or vice-versa. |
| 16 | Erection of Double pole structure as per standard specifications |
| 17 | Conversion of existing Single pole to Double Polestructure as per standard specification |
| 18 | Grouting of pole with cement brick ballast and coarse sand as per standard specification. |
| 19 | Making of pole plinth of 400 mm dia, 600 mm height (200mm underground) with C.C. in ratio 1:4:8 of cements, stone ballast and coarse sand including cost of materials. |
| 20 | Painting of Steel Tubular Pole with one coat of red oxide and two coats of first enamel Alm. Paint upto fuse set including cost of all materials. |
| 21 | Earthing of supports as per standard specifications. |
| 22 | Fixing of stay rod and its erection and grouting by fitting of stay clamp. Stay wire and its proper binding and tightening etc. |
| 23 | Fabrication/modifications of M.S. Items as per requirement of site conditions. |
| 24 | Opening of H.T. Jumpers from the existing 3 Phase 3 Wire H.T. O.H. line for erection work. |
| 25 | Making of H.T. Jumpers with3 Phase 3 Wire H.T. O.H. line after erection of work. |
| 26 | Loading, Carriage and unloading of ACSR/ Panther /Weasel Conductor from store to work site or vice-versa. |
| 27 | Laying, stringing, tensioning and binding of Weasel/Dog conductor for H.T./L.T. O.H. |
| 28 | Loading and Carriage of Sectionalizer from store to site or site to store vise versa |
| 29 | Mounting and Installation of Sectionalizer on Double Pole using hydra |
| 30 | Testing and Commissioning of Sectionalizer |
| 31 | Provding and fixing of copper L-connection for T/F Bushing for connection |
| 32 | Mounting11 kv pin and Disc Insulator |
| 33 | Making jumper of sectionlizer with cable after removing carbon layer from cable with proper luging on the bushing point |
| 34 | Making jumpers from cable box to line, cable support switchgear panels, section poles of each phase. |