| 1 | Clearing shrub jungles uprooting stumps and small bushes and trees below 1 m girth on pre- measurement, deposing the debries away from the work site with all leads,lifts and delifts with cost of all labour T & P, hire and running charges of all machineries, labour welfarecess etc.Complete as per the direction of the Engineer-in-Charge. |
| 2 | Earth work in excavation of foundation in all kinds of soil including dressing and leveling the bed and depositing the excavated soil clear of work site with all leads, lifts, delifts and dewatering including removing bushes, stumps and any other foreign materials from the working area as well as from the foundation trenches with cost of all labour, T&P, hire and running charges of all machineries, labour welfare cess etc. complete in all respects as per specification and direction of the Engineer-In-Charge. |
| 3 | Filling foundation and plinth with sand in layers not exceeding 22.50cm in thickness, well watered and rammed including cost, conveyance, royalty and all other taxes of all materials with all leads, lifts and delifts, cost of all labour, T&P, labour welfare cess etc. complete in all respects and as per specification and the direction of the Engineer-In-Charge. |
| 4 | Supplying and spreading sand of approved specification satisfying filter criteria in filter drains zones and filter blanketsincluding levelling etc complete with cost, carriage, royalty labour welfare cess and taxes of all materials etc. complete as per specification and direction of Engineer-In- Charge. |
| 5 | Supplying and spreading 20mm size granite metal filter in horizontal filter zones and filter including levelling etc complete with cost, carriage, royalty labour welfare cess and taxes of all materials etc. complete as per specification and direction of Engineer-In- Charge. |
| 6 | Supplying and spreading 20mm size granite metal filter in rock toe riprap and filter drains in earth dam or dyke to proper slope including levelling etc complete with cost, carriage, royalty labour welfare cess and taxes of all materials etc. complete as per specification and direction of Engineer-In- Charge. |
| 7 | Supplying and spreading 40mm to 20mm size granite metal filter in rock toe riprap and filter drains in earth dam or dyke to proper slope including levelling etc complete with cost, carriage, royalty labour welfare cess and taxes of all materials etc. complete as per specification and direction of Engineer-In- Charge. |
| 8 | Quarrying, collecting & supplying good quality moorum and sand from approved quarry and stacking the same at work site or at approved stack yard for premeasurement in regular box heaps of 1.50m x 1.50m x 0.50m to be measured as one cum and conveying from premeasured stacks and mixing the sand and moorum in required proportion (30:70) to form the admixture and spreading the admixture over the prepared surface not exceeding 100mm in layers to required thickness including watering and compacting to required density with P.R.R including cost, conveyance, royalty and all other taxes of all materials and cost of labour, T&P required for the work including hire & running charges of machineries with all leads, lifts and delifts and labour welfare cess etc. complete in all respects and as per specification and direction of the Engineer-In-Charge. |
| 9 | Supplying , prov iding and laying 150mm dia perforated PVC pipe of 5mm thick and labour for drilling hole of 12mm dia(100 minimum 100 perforation per meter length of pipe) in horizontal filter drains with all cost, conveyance,labour and taxes , royalitiesetc. complete as per specification and direction of Engineer-In- Charge. |
| 10 | Supplying,providing & fixing 90mm dia pressure relief valve PVC Housing pipe 160mm OD having length of 430mm (working pressure 0.6 N/mm2 ) with all cost ,carriage,labour,royalty etc. complete as per specification and direction of Engineer-In- Charge. |
| 11 | Cement concrete M15 with 40 mm downgraded crusher broken hard granite chips including mixing with concrete mixer, hoisting and laying manually, compacting by vibrator including cost, conveyance,.royalty of all materials complete including watering etc. as directed by the Engineer-in-Charge. |
| 12 | Providing and laying cement concrete of grade M-15 with 20mm downgraded granite coarse aggregate for concrete lining to the bed & slope of canal with sleeper beam,keys etc. in pannels including supply of all material labour & machinery, compacting with space vibrator or manually & finishing the concrete surface including trimming & dressing of canal bed & slope including cutting trenches for sleeper beam, keys & drainages etc.including watering & compaction of slopes & bed with hand rammer to proper profile & supplying & laying polythine film of 100 micron complete as directed by the EIC. |
| 13 | Providing and laying cement concrete of grade M-15 with 20mm downgraded granite coarse aggregate for concrete lining to the bed & slope of canal with sleeper beam,keys etc. in pannels including supply of all material labour & machinery, compacting with space vibrator or manually & finishing the concrete surface including trimming & dressing of canal bed & slope including cutting trenches for sleeper beam, keys & drainages etc.including watering & compaction of slopes & bed with hand rammer to proper profile & supplying & laying polythine film of 100 micron complete as directed by the EIC. |
| 14 | Providing Primming 1 coat with coaltar or equivalent any approved sealing compound at jointany approved primer etc. with all leads, lifts and delifts and labour welfare cess etc. complete in all respects and as per specification and direction of the Engineer-In-Charge. |
| 15 | Filling bitumen and cement and jute fibre in expansion joints inclusive of cost of materials, bitumen and cement proportion (3:1) including cleaning before pouring 12mm to 25mm and 15cm depth with hire &running charges of all machineries with all labour &T & P required for the work etc.complete in all respect as per specification and direction of the Engineer-in-Charge |
| 16 | Rigid and smooth centering and shuttering for R.C.C works including false works and dismantling them after casting including cost of materials, labours etc. complete as per direction of Engineer-in-charge. |
| 17 | Earth work in suitable type of soil in borrow area, loading into transport vehicle manually or mechanically and transportation of earth by mechamical means unloading the same over the approved surface of embankment in proper profiles with 5.0km leads, including rough dressing and breaking the clods to maximum 5cm. to 7cm. size including removal of roots, bushes, other deleterious materials from transported earth with all cost,carriage, roralty, labour welfarecess & laying in layers not exceeding 22.5cm in depth including compasition by Vibrator roller in OMC condition with hire &running charges of all machineries with all labour &T & P required for the work etc.complete in all respect as per specification and direction of the Engineer-in-Charge. |
| 18 | Fine dressing of earth works in slopes including filling of raincuts and slopes with suitable earth duly compacted and trimmed to the required profile and turfing the surface area with dub grass sods 8cm. To 10cm thick with 4 extra lead and 1 extra lift with initial lead and liftsetc. icluding laying and trimming to form a level and compact surface in the line with the slopes and grade of embakment section including watering until the luxuriant green growth of grass complete with labour welfarecess and as per direction of the Engineer-in-Charge. |
| 19 | Collecting & supplying approved quality of moorum from approved quarry and stacking at work site in regular stacks of 1.50 x 1.50 x 0.50m to be measured as 1.00 cum for premeasurment including cost, carriage royalty of materials and conveying from stacks and spreading on road surface and consolidation with P.R.R. including hire & running charges of PRR and taxes of all materials complete as peri direction of the Engineer-in-charge. |
| 20 | Providing weep holes in concrete works in abutments/wing walls /return walls with 100mm dia AC pipe extending through the full width of the structure with slope of 1V:20H towards drawing face with cost of all the materials, all labours ,all taxes, T&P, etc. complete including labour welfarecess as per specification and direction of Engineer-in-Charge. |
| 21 | Supplying ,providing & laying in position of Hume pipe Np3 150 dia with all cost,carriage,labour,royalty etc. complete as per direction of Engineer-in-Charge. |
| 22 | Dismantling and removing cement concrete including stacking the useful material for reuse and removing the debris within 50m lead as per direction of Engineer-in-Charge. |
| 23 | 20mm thick cement plaster (1:4) in for stone work including cost of all materials ,Labour ,T&P, etc . Complete in all respect and as per specifictaion and direction of the Engineer-In-charge. |
| 24 | The item rates indicated aove work inclusive of cost of all labour, materials,conveyence,taxes and royality(with EMF,DMF and additional charges) of materials,labour cess,here and running charges of all machineries and equipments and other incidental charges so as to complete the item in all respect as per specification and direction of Engineer-In-Charge.Accordingly the bidder has to quote the rates.The rate are exclusive of GST as applicable. |