| 1 | Earthwork in excavation in foundation trenches in Hard soil (vide classification of soil item-A) and disposal of excavated earth as obtained to a distance upto 50 M. including all lifts, levelling, ramming the foudation trenches, removing roots of trees, shrubs all complete as per approved design, building specification and direction of E/l. |
| 2 | Providing coarse clean sand in filling in foundation trenches or in plinth including ramming and watering in layers not exceeding 150mm thick with all leads and lifts including\" cost of all materials, labour, royalty and taxes all complete as per building specification and direction of E/l (Mode of measurement complacted volume). |
| 3 | Providing designation 75 B one brick flat soling joints filled with local sand including cost of watering taxes royalty all complete as per building specification and direction of E/l. |
| 4 | Providing designation 75 B one brick edge soling joints filled with local sand including cost of watering taxes royalty all complete as per building specification and direction of E/l. |
| 5 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - all work upto plinth level :1:2:4 . |
| 6 | Providing designation 75 B brick work in C.M. (1:6) in foundation and plinth with approved quality of clean coarse sand of F.M. 2 to 2.5 including providing 10mm thick mortar joints, cost of screening materials, raking out joints to 15mm depth, curing, taxes and royalty all complete as per building specification and direction of E/l. |
| 7 | Providing 12mm cement plaster (1:4) with 1.5 mm punning clean coarse sand of F.M. 1.5 including screening, curingwithall leadsand liftsof water, scaffolding taxes and royalty all complete as per building specification and direction of E/l. |
| 8 | Carriage of material SAND |
| 9 | STONE CHIPS |
| 10 | BRICKS |
| 11 | CEMENT |
| 12 | Earthwork in excavation in foundation trenches in Hard soil (vide classification of soil item-A) and disposal of excavated earth as obtained to a distance upto 50 M. including all lifts, levelling, ramming the foudation trenches, removing roots of trees, shrubs all complete as per approved design, building specification and direction of E/l. |
| 13 | Providing coarse clean sand in filling in foundation trenches or in plinth including ramming and watering in layers not exceeding 150mm thick with all leads and lifts including\" cost of all materials, labour, royalty and taxes all complete as per building specification and direction of E/l (Mode of measurement complacted volume). |
| 14 | Providing designation 75 B one brick flat soling joints filled with local sand including cost of watering taxes royalty all complete as per building specification and direction of E/l. |
| 15 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - all work upto plinth level :1:2:4 . |
| 16 | R.C.C. work in walls (any thickness) including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, postsand struts etc. above plinth level upto floor five level excluding cost of centering, shuttering, finishing and reinforcement :1;1.5:3 . |
| 17 | R.C.C. work in beams ,suspended floors ,roofs having slope upto 15\", landings ,balconies ,shelves ,chajjas ,lintels ,bands , plain window sill ,staircase and spiral stairs cases above plinth level upto floor five level excluding the cost of centering ,shuttering , finishing and reinforcement with 1:1.5:3. |
| 18 | Providing Tor steel reinforcement of 10mm. ,12mm & 16mm dia. bars as per approved design and drawing excluding carriage of M.S. bars to work site , cutting, bending and binding with annealed wire with cost of wire, removal of rust placing the rods in position all complete as per building specification and direction of E/l. |
| 19 | Centering and shuttering including strutting , propping etc. and removal of form for-Foundation Base |
| 20 | Centering and shuttering including strutting , propping etc. and removal of form for-wall |
| 21 | Centering and shuttering including strutting , propping etc. and removal of form for-slab |
| 22 | Carriage of material CEMENT |
| 23 | SAND |
| 24 | STONE CHIPS |
| 25 | BRICKS |
| 26 | STEEL |
| 27 | Earthwork in excavation in foundation trenches in Hard soil (vide classification of soil item-A) and disposal of excavated earth as obtained to a distance upto 50 M. including all lifts, levelling, ramming the foudation trenches, removing roots of trees, shrubs all complete as per approved design, building specification and direction of E/l. |
| 28 | Providing coarse clean sand in filling in foundation trenches or in plinth including ramming and watering in layers not exceeding 150mm thick with all leads and lifts including\" cost of all materials, labour, royalty and taxes all complete as per building specification and direction of E/l (Mode of measurement complacted volume). |
| 29 | Providing designation 75 B one brick flat soling joints filled with local sand including cost of watering taxes royalty all complete as per building specification and direction of E/l. |
| 30 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - all work upto plinth level :1:2:4 . |
| 31 | R.C.C. work in walls (any thickness) including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, postsand struts etc. above plinth level upto floor five level excluding cost of centering, shuttering, finishing and reinforcement :1;1.5:3 . |
| 32 | R.C.C. work in beams ,suspended floors ,roofs having slope upto 15\", landings ,balconies ,shelves ,chajjas ,lintels ,bands , plain window sill ,staircase and spiral stairs cases above plinth level upto floor five level excluding the cost of centering ,shuttering , finishing and reinforcement with 1:1.5:3. |
| 33 | Providing Tor steel reinforcement of 10mm. ,12mm & 16mm dia. bars as per approved design and drawing excluding carriage of M.S. bars to work site , cutting, bending and binding with annealed wire with cost of wire, removal of rust placing the rods in position all complete as per building specification and direction of E/l. |
| 34 | Centering and shuttering including strutting , propping etc. and removal of form for-Foundation Base |
| 35 | Centering and shuttering including strutting , propping etc. and removal of form for-wall |
| 36 | Centering and shuttering including strutting , propping etc. and removal of form for-slab |
| 37 | Carriage of material CEMENT |
| 38 | SAND |
| 39 | STONE CHIPS |
| 40 | BRICKS |
| 41 | STEEL |
| 42 | Earthwork in excavation in foundation trenches in Hard soil (vide classification of soil item-A) and disposal of excavated earth as obtained to a distance upto 50 M. including all lifts, levelling, ramming the foudation trenches, removing roots of trees, shrubs all complete as per approved design, building specification and direction of E/l. |
| 43 | Providing coarse clean sand in filling in foundation trenches or in plinth including ramming and watering in layers not exceeding 150mm thick with all leads and lifts including\" cost of all materials, labour, royalty and taxes all complete as per building specification and direction of E/l (Mode of measurement complacted volume). |
| 44 | Providing designation 75 B one brick flat soling joints filled with local sand including cost of watering taxes royalty all complete as per building specification and direction of E/l. |
| 45 | Providing designation 75 B one brick edge soling joints filled with local sand including cost of watering taxes royalty all complete as per building specification and direction of E/l. |
| 46 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - all work upto plinth level :1:2:4 . |
| 47 | Providing designation 75 B brick work in C.M. (1:6) in foundation and plinth with approved quality of clean coarse sand of F.M. 2 to 2.5 including providing 10mm thick mortar joints, cost of screening materials, raking out joints to 15mm depth, curing, taxes and royalty all complete as per building specification and direction of E/l. |
| 48 | Providing 12mm cement plaster (1:4) with 1.5 mm punning clean coarse sand of F.M. 1.5 including screening, curingwithall leadsand liftsof water, scaffolding taxes and royalty all complete as per building specification and direction of E/l. |
| 49 | Carriage of material SAND |
| 50 | STONE CHIPS |
| 51 | BRICKS |
| 52 | CEMENT |
| 53 | Less 2300.00 per thousand for kiln burn bricks |
| 54 | GST @ 18% |
| 55 | Labour cess @ 1% |