| 1 | Innitial RehabilationClearing and grubbing road land including uprooting wild vegetation, grass, bushes, shrubs, saplings and trees of grith upto 300mm removal of stumps of such trees cut earlier and disposal of unserviceable materials by manual means andstacking of serviceab |
| 2 | Innitial RehabilationProviding 37.5mm thick Built up spray grouting after scrapping, cleaning the road surface applying tack coat using 3.00kg of bitumen for 10sqm and laying of one layer of 37.5mm thick by using 0.45cum of 25mm to 40mm grade bitumin for 10 sqm in each layer with 0.12 cum of 12mm size B.H.G. C.B chips as key stone for 10 sqm.spreading over and laying induding heating pouring, spreading bitumirl metal and chips and compacting with P.R.R including cost ,conveyance royalty taxes of all required metterials,hire and running chsrges of mechinaries T&P etc complete as per direction of the Engineer-in-charge |
| 3 | Innitial RehabilationPainting two coats including primer coat after filling the surface with synthetic enamel paint in all shades on new plastered /concrete surfaces as per drawing and technical specificationunder section 1700 of MORD. |
| 4 | Innitial RehabilationProviding Rainforced Cement Concrete of (1:2.5:5) with 20mm to 40mm size stone aggregate in foundations upto a depth of 1.5m below ground level and upto a height of 1.5m above ground level / bed level including cost and conveyance of all materials to site, and all labour charges complete as per direction of E.I.C. |
| 5 | Innitial RehabilationProviding and fixing of Retro reflective cautionary, mandatory and informatory sign board as per IRC:67 made ofhigh intensity grade sheetingas per clause no 801.30 fixed over aluminium sheeting 1.5mm thick Supported on a mild steel angle iron post 75x75x6 mm etc complete and as per direction of Engineer-in-Charge. |
| 6 | 1200x900 mm Informatory board |
| 7 | 600 mm dia Circular cautinary signage |
| 8 | 900 mm equilateral triangle cautinary signage |
| 9 | 600x600 mm place Identification board |
| 10 | Innitial RehabilationProviding & laying good laterite moorum for filling road flanks including cost and conveyance of all materials to site, and all labour charges complete as per direction of E.I.C. |
| 11 | Innitial RehabilationEarth work in excavation of foundation in hard soil with all leads and lift including rough dressing breaking clods and leveling bed and depositing the excavated materials away from the working area etc. complete as directed E.I.C. |
| 12 | Innitial RehabilationFilling in foundation and plinth with sandwatered and rammed with cost, conveyance, royality, taxes of all materials and all labour, T&P, etc. complete |
| 13 | Innitial RehabilationCement concrete of proportion (1:3:6) in foundation using 4cm sizeblack broken granite stone aggregates of approved quality and from approved quarry including hoisting, lowering and laying concrete in layers not exceeding 15cm(6\") thick to the require |
| 14 | Innitial RehabilationProviding Rainforced Cement Concrete of (1:2.5:5) with 20mm to 40mm size stone aggregate in foundations upto a depth of 1.5m below ground level and upto a height of 1.5m above ground level / bed level including cost and conveyance of all materials to site |
| 15 | Innitial RehabilationProviding weep holes in Brick masonary / Plain / Reinforced concrete abutment, wing wall / returning wall with 100mm dia AC pipe, extending through the full width of the structure with slope of IV : 20H towards drawing foce, complete as per the direction of the E.I.C. |
| 16 | Periodic RenewalProviding and apppying tack coat with bitumen Emulsion using emulsion pressure distributer at the rate of 0.30kg per sqm on the prepared bituminous/granular surface etc complete |
| 17 | Periodic RenewalProviding and laying semi dense bituminous concrete with batch type hot mix plant using crushed aggregates of specified grading, premixed with bituminous binder of 60/70 penetration grade of bitumen, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheelede, vibratory and tandem rollers to achieve the desired compaction as per Clause 508 of MoSRT&H Specifications for Road & Bridge works (4th Revision) |
| 18 | Routine Maintenance |
| 19 | BT Work |
| 20 | For 1st Year |
| 21 | For 2nd Year |
| 22 | For 3rd Year |
| 23 | For 4thYear |
| 24 | For 5thYear |
| 25 | CC Road |
| 26 | For 1st Year |
| 27 | For 2nd Year |
| 28 | For 3rd Year |
| 29 | For 4thYear |
| 30 | For 5thYear |
| 31 | Emergency works(Work to be taken up as per the reqirement & separate work order to be issued by PIU) |