| 1 | Carriage of following material from store center Meerut to site of work including loading & unloading at both ends maximum distance up to 40 Km. :- |
| 2 | PCC Pole 8.5 Mtr Long/STP Pole 11 Mtr. Long. |
| 3 | Line material such as 11 KV Cross arms 11 KV pin, 11 KV pin insulator, 11 KV Disc, Stay rod, Stay wire ACSR weasel conductor, GI Wire, MS angle iron & MS Channel, TPMO, Fuse set etc. |
| 4 | 10 KVA to 100 KVA T/F including complete related material required for transformer. |
| 5 | LT Lead |
| 6 | Metering cubical |
| 7 | CT/PT Unit |
| 8 | XLPE Cable of size 3x70/3x120 sq.mm |
| 9 | Erection of PCC pole 8.5 Mtr long/STP Pole 11 mtr long after digging a pit of size 1.6 mtr deep in all type of Soil including grouting ratio (1:4:8) & back filling of the pole with proper ramming after completion of work. |
| 10 | Fabrication and fixing of all 11 KV HT/LT line accessories. |
| 11 | Erection of Double pole on PCC pole 8.5 mtr after digging a pit of size1.6 mtr deep in all type of Soil for each pole including grouting & back filling of the pole with proper ramming after completion of work. |
| 12 | Fabrication and fixing of MS angle and MS channel, fixing all 11 KV accessories TPMO, Fuse set 11 KV pin insulators on D/P Pole. |
| 13 | Mounting of 10to 100 KVA T/F with proper jumpering of HT side and fixing of cable on LT side of T/F. |
| 14 | Making a section pole to exist pole after fabrication & fixing of T-channel fixing of all 11 KV accessories. |
| 15 | Erection of stay rod complete after digging a pit of size 1.6 mtr deep and grouting the same in block of size 0.60 x 0.60 x 0.30 mtr and nuzzling at the both ends and filling the pit with excavated earth soil with proper ramming. |
| 16 | Laying lifting stringing & proper sagging of ACSR weasel conductor for 3 phase, 3 wire 11 KV line including binding & jumpering properly. |
| 17 | Laying of LT ABC Cable of various size including fixing of all LT ABC accessories on support |
| 18 | Fixing of Distribution box including fixing the cable from transformar and consumer service cable |
| 19 | Earthing of each 11 KV line pole & T/F properly after drive of electrodes if size 20mm x 250 mm and connection the earthing point with GL wire. |
| 20 | Guarding of line with G.I. wire having 2 no. horizontal wire & 3 Mtr distance of SWG G.I. wire after fabrication of guard cross arms of & fixing the same in supports. |
| 21 | Filling of 11 KV Jointing Kit Indoor/Outdoor of size 3x70/3x120 sq.mm |
| 22 | Laying of XLPE Cable of size 3x70/3x120 sq.mm pit of the size 1.5 in the trench and road crossing in the air |
| 23 | Mounting and installation of CT/PT Unit. |
| 24 | Mounting of fixing of metering cubical |
| 25 | Providing and fixing of Holding clamp. |
| 26 | Providing and fixing of LT Clamp. |
| 27 | Providing and fixing of J Hook. |
| 28 | Providing and fixing of Piercing Clamp. |
| 29 | Providing and fixing of Dead and clamp. |
| 30 | Providing and fixing of MS Nut and bolts |
| 31 | Providing and fixing of LT Insulator. |
| 32 | Cutting & chopping tree branches near side of line for making the clearance between line and tree. |