Construction Of P.C.C Road At Barhait Santhalisouth From Rajkumar Pandit To Old Tankiin Barhait Santhali South G.P.And Construction Of P.C.C Road At Chhuchi Momin Tolafrom Daud House To Jalamuddinhouse In Chhuchi G.P. In Barhait Block , Dist - Sbg
Tender Overview
Project Description
CONSTRUCTION OF P.C.C ROAD AT BARHAIT SANTHALISOUTH FROM RAJKUMAR PANDIT TO OLD TANKIIN BARHAIT SANTHALI SOUTH G.P.AND CONSTRUCTION OF P.C.C ROAD AT CHHUCHI MOMIN TOLAFROM DAUD HOUSE TO JALAMUDDINHOUSE IN CHHUCHI G.P. IN BARHAIT BLOCK , DIST - SBG
BOQ
| Sl. No. | Item Description |
| 1 | Lobour for site clearance do…….do….E/I |
| 2 | Earth work in excavation in foundation trenches in ordinary soil ( vide classification of soil item A) and disposal of excavated earth as obtained to a distance upto 50M including all lifts leveling ramming the foundation treanches, removing roots of trees, and shrubs all complete as per approved design, building specification and direction of E/I. |
| 3 | Providing stone dust filling in road do……do…..E/I |
| 4 | Supplying and laying (properly as per design and drawing)rip-rap with \"good quality of boulders duly packed including the cost of materials, royalty all taxes etc. but excluding the cost of carriage all cornplete as per specification and direction of E/|. |
| 5 | Providing P.C.C.M 200 in nominal mix of (1:1.5:3) in foundation withapproved quality of stone chips 20 mm to 6 mm size graded andclean coarse sancl of F M.2 5 to 3 including screening shutteringmixing cement concrete in mixer and placrng in positionlvibrating, strrking, curing, taxes and royalty all complete as per specification and direction of Engineer-in-charge |
| 6 | Filling in foundation trenches and plinth in layers notexceeding 150 mm thick wellwatered, rammed, fully compacted and finedressed with earth obtained after cutting withtn a lead of50 ltl and liftof 1.5 M all complete as per buildingspecification and direction of E/l |
| 7 | Centring and shuttering including strutting proping etc removal of form for all complete as per buiding specification and direction of E/I |
| 8 | Add Carrige cost of materials from source to W/S , Boulder20 Km |
| 9 | sand25 Km |
| 10 | Stone Chips18 Km |
| 11 | Stone Dust18 Km |
| 12 | Cement12 Km |
| 13 | Lobour for site clearance do…….do….E/I |
| 14 | Earth work in excavation in foundation trenches in ordinary soil ( vide classification of soil item A) and disposal of excavated earth as obtained to a distance upto 50M including all lifts leveling ramming the foundation treanches, removing roots of trees, and shrubs all complete as per approved design, building specification and direction of E/I. |
| 15 | Providing stone dust filling in road do……do…..E/I |
| 16 | Supplying and laying (properly as per design and drawing)rip-rap with \"good quality of boulders duly packed including the cost of materials, royalty all taxes etc. but excluding the cost of carriage all cornplete as per specification and direction of E/|. |
| 17 | Providing P.C.C.M 200 in nominal mix of (1:1.5:3) in foundation withapproved quality of stone chips 20 mm to 6 mm size graded andclean coarse sancl of F M.2 5 to 3 including screening shutteringmixing cement concrete in mixer and placrng in positionlvibrating, strrking, curing, taxes and royalty all complete as per specification and direction of Engineer-in-charge |
| 18 | Filling in foundation trenches and plinth in layers notexceeding 150 mm thick wellwatered, rammed, fully compacted and finedressed with earth obtained after cutting withtn a lead of50 ltl and liftof 1.5 M all complete as per buildingspecification and direction of E/l |
| 19 | Centring and shuttering including strutting proping etc removal of form for all complete as per buiding specification and direction of E/I |
| 20 | Add Carrige cost of materials from source to W/S , Boulder20 Km |
| 21 | sand25 Km |
| 22 | Stone Chips18 Km |
| 23 | Stone Dust18 Km |
| 24 | Cement12 Km |
| 25 | add S/B & PHOTOGRAPHY |
| 26 | Add . 18 % GST |
| 27 | add 1 % labour cess |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
CompletedBid Opening Date
Technical bids will be opened and evaluated.
CompletedTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender