| 1 | Excavation in trenchesn.exc 1.5m wide and n.exc1.5 min depthfor foundation, or shafts,wells, cess pits manholes, pier holes etcn.exc 10 Sqmonplanandn.exc1.5 min depthandgettingoutin any type ofsoil / rock (soft / hard / dense soil /rock)complete allasspecifiedanddirectedbyEngr-in-charge. |
| 2 | Allasperitem No.1 here in beforebutdepth exc 1.5 mandn.exc 3.00 mcomplete allasspecified anddirected by Engr-in-Charge. |
| 3 | Demolition and breaking updrain pipes internal dia / boreofpipe 150mm (Salt glazed ware, AC or Reinforced concrete) set in cement mortar including haunching in any discription and disposed from MOD land. complete allasspecified anddirected by the Engineer-in-Charge. |
| 4 | Allas per item No. 3 here in before but internal dia / bore of pipe 200 mm. |
| 5 | Allas per item No. 3 here in before but internal dia / bore of pipe 300 mm. |
| 6 | S&F 150mm bore (inner dia) double wall corrugated HDPE pipes (SN8)in any length including all fittings and jointing with elastomeric rubber rings and couplers /other jointing materials as per manufacturers instructins,complete all as specified and directed. |
| 7 | All as per srl item No. 6 here in before but for 200mm bore (inner dia). |
| 8 | All as per Srl item No. 6 here in before but for 300mm bore (inner dia). |
| 9 | M & L for concrete bed PCC 1:4:8 Type D2 (Using 40mm graded stone aggregate) to drain pipes 150 mm dia including packing under and haunching against the sides of pipes after they are laid and tested all as specified and as directed by Engr-in-Charge. |
| 10 | Allasperitem No. 09 here in before but200 mmdia /bore complete. |
| 11 | Allasperitem No. 09 here in beforebut300 mmdia /bore complete. |
| 12 | M & LforReturning & filling in including spreading, levelling, watering & well ramming in layers n.exc 25mm thick in soft/hard/ dense soil complete all as specified and directed by Engineer-in-charge. |
| 13 | Removing surplus excavated material outside MOD land completeallas specified and directed by Engr-in-Charge. |
| 14 | Demolition of brick work built in cement mortar including all quains, arches, pillers etc andremoving debriesout site MOD landcomplete allasspeifiedand directedbyEngr-in-charge. |
| 15 | M&L forbrick work with sub classBbricks ofoldsizebuiltincement mortar 1:4 straight or curved on plan exceeding 6m mean radius complete all as specified and directed by Engr-in-Charge. |
| 16 | Taking down cementplaster of any description on brick or concrete surfaces of walls or ceilingetc incl. Raking out joints ,haking for key and scrubbing down with waterincluding removing debries out site MOD land complete all as specified and as directed by Engr-in-Charge. |
| 17 | M&L for 15 mm thick cement plaster in cement mortar 1:4 on concrete or brick surface and finished surafaceseven and smooth without using extra cement complete all as specified and as directed by Engr-in-Charge. |
| 18 | Demolition for reinforced cement Concrete of any description and in any position not otherwise specifically provided for cement concretecomplete all as specified and directed. |
| 19 | M&L for Reinforced cement concrete Type B0 1:2:4 (12.5mm graded aggregate) (nominal mix) in Chullah hoods; manhole covers stairways (except spiral staircases) including steps (square orspandril), string pieces, carriages, etc., complete, any section straight or winding, but excluding landings; RCC water tanks upto 1500 litres complete all as specified and directed. |
| 20 | M&L for TMT MS bars 10 mm dia over, cut to length, bent to shape required including cranckingbending spirally for hoping for col hooking ends and binding with and including mile steel wire non less than 0.9 mm dia securing with clips in qualitycomplete all as specified and directed. |
| 21 | All as per item No 20 here in before but 6mm to 8mm dia quality confirming |
| 22 | S& F inrepair Vitreous chinasquatting \"Orissa\"patternofsize580 x 440 mmwhitewithintegralfootrest (excludingflushingcisternandflushpipe)butincludingP orStrapetccompleteall asspecified anddirectedbyEnginee-in-charge. |
| 23 | S & FVitreous China, squatting pan ,semi-pedestal pattern (Anglo-Indian Type) including pors trap etc complete all as specified and directed. |
| 24 | Cleaning of all blockage of water closet ,gully/Nahani traps ,floor traps , compltete soil,waste and vent pipes etc in any situationgetting out sludge or any other materials and make complete line functional including cleaning offirst manholes ofany size / depthby flushing with water includingloadingand removingsludge /organic material in covered transport and disposing the same out side MODland complete all as specified as and directed by Engr-in-charge.Note : If the same blockage again occured with in 7 days the contractor will be cleaned the same and complaint will not be measured again. |
| 25 | Cleaning of all blockage of manholes by any mean (mechenically)in any situationgetting out sludge or any other materials from manholes of any sizeand depthn.exc 1.5 m, cleaning the manhole by flushing with water includingloadingand removing the taken out sludge /organic material in covered transport and disposing the same out side MODland complete all as specified as and directed by Engr-in-charge. Note : If the same blockage again occured with in 7 days the contractor will be cleaned the same and complaint will not be measured again. |
| 26 | All as per itemNo 25 here in beforebut depth of manhole exceeding 1.50 m and not exc 2.50m complete all as spfd and directed by Engr-in-charge. |
| 27 | Cleaning and removal of under ground blocked sewer line at any depth, any type and size upto any dia bore of sewer line in between manholes and making the line in working condition by Mechanically used water fitting Hydraulic pressure sewer sucker machine/ capacity min 5000lit, removingall sludge and solid, semi-solid, sludge and water or any shape from sewer line and manholes by blocking the line from one manhole to other manholes and cleaning the line by flushing with water includindloading and removing the taken out sludge/organic material in covered transort and disposing the same out side MOD land complete all as specified and directedNote - (1)After receivingcomplaint from MES Rep byContractor\"s supervisor / Site Engineer, jobto completed within 12 working hours. (Rate include all mobilisation of machine ,labour, Operator, helper reqd to clean the machine, T &P and other minor charges for 08 working Hrs).(2) If the same blockage again occured with in 7 days the contractor will be cleaned the same and complaint will not be measured again. |
| 28 | S& Finrepair75 mmborePVC (SWR ) pipesinglesocketedinany lengthwithrubber ringjoints, laidintrenches/floors/wall (using GI half round Clamp) etcincludingremovingfromsite completeallasspecifiedanddirectedbyEngr - in- charge. |
| 29 | S& Finrepair110 mmborePVC (SWR ) pipesinglesocketedinany lengthwithrubber ringjoints, laidintrenches/floors/wall (using GI half round Clampetcincludingremovingfromsite completeallasspecifiedanddirectedbyEngr - in- charge. |
| 30 | S& Finrepair200 mmborePVC (SWR ) pipesinglesocketedinany lengthwithrubber ringjoints, laidin trenches/floors/wall (using GI half round Clampetcincludingremovingfromsite completeallasspecifiedanddirectedbyEngr - in- charge. |
| 31 | S&F 75mm bore PVC (SWR) bends any radiuscomplete all as specified and directed by Engineer-in-Charge |
| 32 | S&F 110mm bore pipe PVC (SWR) bends any radius with oval acess door complete all as specified and directed by Engineer-in-Charge |
| 33 | Cleaning and removing all scale and dirt, etc. from tanks and form mouths of circulating pipes, etc. capacity exc 250 but n exc 500 ltrs complete all as specified and directed. |
| 34 | All as per Srl item No. 33 here in before but exc 500 but n exc 1000 ltr |
| 35 | Cleaning of all blockage of Covered drain atany situationgetting out sludge or any other materials (debries/ brocked drain cover/ vegitation / soil,) and make complete line functional incluing cleaning ofdrains ofany size / depthand removingsludge /organic material in covered transport and disposing the same out side MODland complete all as specified as and directed by Engr-in-charge.Note : Rate including removing cover of drains and refixing also. |
| 36 | M & Lforcutting in to existing manhole for connecting new drains, making good to pipe and rendrering, cutting out existing benching for and forming branch channel ( 1/2round or 3/4 section) in cement concrete1:2:4 type B-1 smooth finished, and reforming benching as required of 150 mm/200mm/300mm dia of pipe completeallasspeifiedand directedbyEngr-in-charge. |
| 37 | Demolition of concrete of any description and in any position not otherwise specifically provided for.complete all as specified and directed by Engr-In-Charge. |
| 38 | M & L for 75mm thick PCC 1:3:6 type C-2 (40mm graded stone aggregate) as in plinth protection complete as directed by Engr-in-Charge. |
| 39 | Excavation in trenches n.exc 1.5m wide and n.exc 1.5m in depth for foundation, or shafts, wells, cess pits manholes, pier holes etc n.exc 10 Sqm on plan and n.exc 1.5m in depth and getting out in any type of Hard rock complete all as specified and directed |
| 40 | Supply only drain expert drain cleaning powder for cleaning of nahani trap, under ground PVC pipe, blockage traps complete all as specified and directed. |