| 1 | Supply of Material |
| 2 | Prov.RCC muff 2mtr long with conc. Filling. |
| 3 | Prov. Cross Arm: [Channel Iron (100x50x6 mm), Length (1500) mm for single pole |
| 4 | Prov. Angle Iron (50x50x6 mm), Length (2x750) mm for single pole |
| 5 | Prov. 11 kV Pin Insulators (Porcelain, 12 kV, 10 KN, CD-320): 3 No. per single pole structure |
| 6 | CI X-Arm 2400mm (100x50xx6mm) |
| 7 | Prov Discs insulator sets on Dead End str.(comprising 1 No. Disc (Procelain, BS,12 KV , 90 KN ) including Dead end clamps etc.) |
| 8 | Prov. Stay set complete in all respect( Stay clamp, egg etc.) |
| 9 | Prov.Stay Wire (7/3.15 mm) (10.0 kg Per Stay Set) |
| 10 | Prov. Nuts and Bolts of Various Sizes |
| 11 | Prov. Half Clamp |
| 12 | Prov. Full Clamp |
| 13 | Erection of Single Pole New |
| 14 | Digging of pit |
| 15 | Erection of poles |
| 16 | Filling of pit-ramming |
| 17 | Drilling Of Holes In Pole X-Arm |
| 18 | Erec. Of X-Arm, Insulator, knee bracing top clamps etc. |
| 19 | Concreting of Muff |
| 20 | Erection of Double Pole New |
| 21 | Digging of pit |
| 22 | Drilling Of Holes In Pole X-Arm |
| 23 | Erection of poles |
| 24 | Erec. Of X-Arm, Insulator, knee bracing top clamps etc. |
| 25 | Filling of pit-ramming |
| 26 | Concreting of Muff |
| 27 | Re-erection of straightening/displaced / tilted D/P Str. |
| 28 | Re-erection of straightening/displaced / tilted pole Single |
| 29 | Erection of stay sets HT |
| 30 | Digging of Pit, Fixing of stay rod, filling of pit & nozzeling & Tightening |
| 31 | Re-Sagging of ACSR Conductor 6/1/3.35 mm2 (old) |
| 32 | Stringing and sagging |
| 33 | Binding with insulator |
| 34 | Manual Carriage of pole , conductor & associate material ( from road head to site @ avg. lead 1 km) |
| 35 | Pole along with muffs. |
| 36 | Stay sets complete with stay wire. |
| 37 | Other matirial viz. disc insulator, pin insulator, nut and bolts, clamps etc. |