| 1 | Pumping out water from ponds or tanks(Payment if permitted will be made on the quantity of water calculated on the basis of initial water level and final level on consideration being made for any water that may have been added through percolation or otherwise) |
| 2 | Cleaning of floating materials / garbage / any other foul materials from incoming sewer of drainage pumping station / adjoining penstock gate / open Nikashi / Lock Gate at Canal etc. by mathor labour after removing concrete slab / manhole cover etc. without damaging the same and refixing the same properly after cleaning as necessary and removing the sludge etc. by using iron pans, buckets including all labour, tools & plants including expulsion of impure / inflammable / asphyxiating gases from the drains etc. and removing the spoils in dry condition and disposing the same by truck beyond the area of Municipal Corporation / Municipality / Notified Area Authority / Industrial Township Authority etc. for such disposal including the cost of loading, unloading, transportation and making arrangement of necessary land for disposal, spreading and leveling as necessary etc. and cleaning the road side in all respects, complete as per direction of the Engineer- in-Charge. (Land for disposal to be arranged by the contractor). (Payment will be made on the basis of actual stack measurment of spoils in dry condition at roadside) |
| 3 | M.S. structural works in columns, beams etc. with simple rolled structural members (e.g. joists, angle, channel sections conforming to IS: 226, IS: 808 & SP (6)- 1964 connected to one another with bracket, gussets, cleats as per design, direction of Engineer-incharge complete including cutting to requisite shape and length, fabrication with necessary bolting, metal arc welding conforming to IS: 816- 1969 & IS: 1995 using electrodes of approved make and brand conforming to IS:814- 2004, haulage, hoisting and erection all complete. The rate includes the cost of rolled steel section, consumables such as electrodes, gas and hire charge of all tools and plants and labour required for the work including all incidental chages such as electricity charges, labour insurance charges etc. I) For structural members of specified sections weighing less than 22.5 Kg./m(Payment to be made on the basis of calculated weight of structural members only in finished work as per IS specified weight. Payment for gusset, bracket, cleat, rivets, bolts and nuts may be make by adding the actual weight of such items with the weight of finished structural members or 7% of weight for finished structural members weighing not less than 22.5 Kg. / m. or 15 % of weight for finished structal members weighing less than 22.5 Kg. / m. may be increased allow for bracket, cleat, rivet, bolts and nuts etc. and no seperate payment being made for these items, as per direction of Engineer In Charge. The rates are considered for a height of erection 8m. / 2nd floor level from the ground. Add 1.5% extra over the rate for each additional floor or 4m. beyond initiial 8m. or part thereof.) |
| 4 | Lifting and dismantling of the 15 HP pumping set part by part of all accessories and keeping at pump floor at suitable place after proper cleaning as per direction ofEIC. |
| 5 | Supply , delivery & fitting of the following spares as per samplefor Lifting stations pumps |
| 6 | i) Head Bush |
| 7 | ii) Impeller Ring |
| 8 | iii)Renewable Ring |
| 9 | iv)Locking bolt for impeller |
| 10 | v)Grub srew for loking bolt |
| 11 | vi)Impeller key |
| 12 | vii)Guide ring |
| 13 | viii)Shaft Sleeve |
| 14 | ix)Bush for L.B.H |
| 15 | x)Oil seal forL.B.H |
| 16 | xi)Oil seal cover forL.B.H |
| 17 | xii) Intermediate bearing holder |
| 18 | xiii)Intermediate bearing holder bush |
| 19 | xiv)Oil sealfor Intermediate bearing holder |
| 20 | xv)Shaft cuopling(screwed) |
| 21 | xvi)CT housing |
| 22 | xvii)Distance piece |
| 23 | xviii) Pump half coupling |
| 24 | xix) Coupling pin & bush |
| 25 | xx) Grease pot for ball bearing |
| 26 | xxi) Impeller shaft |
| 27 | xxii) Stuffing box & bush |
| 28 | xxiii) Thrust bearing |
| 29 | xxiv)Intermediate bush |
| 30 | xxv) Shaft nut( bronze) |
| 31 | Supply and delivery of Neoprene Rubber Sheet- 5mm thick |
| 32 | Supply and delivery of Cotton Impregnated with lubricant-Hydraulic Gland Packing (Style-376), Thickness- 13 to 25mm,Make- Champion |
| 33 | Supply, delivery at site and storage of 1.1 KV grade 12 core PVC insulated armounred 2.5 sq.mm control cable . |
| 34 | Laying of 1.1 KV grade 12 core PVC insulated armounred 2.5 sq.mm control cable including termination complete by supplying of neccearry glands & sockets as per direction of EIC. |
| 35 | Re-assembling of the pump(15HP) with all spares with proper alignment. |
| 36 | Commissioning and trail run(15HP) |
| 37 | Add GST @ 18% |
| 38 | Add LWC @ 1% |
| 39 | Less: Old/unserviceable materials sl no. (5.I to 5.viii and 5.xii, 5.xiii, 5.xv to 5.xix and 5.xxi to 5.xxv) ) @5% |