Tender For Construction Of New Oht 30000 Lit At Annanagar In Navalpattu Panchayat In Thiruverumbur Block Under Nabard-Ridf-Xxix 2024-2025
Tender Value
18.42 Lakhs
Estimated cost
Bid Submission
06 Aug 2024
0 days left
EMD
19000
Bank guarantee accepted
Document Fee
Ref. Documents
Non-refundable
Tender Type
Online
Tender Overview
Organization
Tender ID
Competition Type
NCB
Bidding Type
Tender
Location / State
thiruverumbur → Tamil Nadu
EMD Exemption
Not Available
Quantity
Not Available
Website
Contact Person
Address
Project Description
Construction Of New Oht 30000 Lit At Annanagar In Navalpattu Panchayat In Thiruverumbur Block Under Nabard-Ridf-Xxix 2024-2025
BOQ
| Sl. No. | Item Description |
| 1 | Construction of New OHT 30000 Litres atAnna Nagar in Navalpattu Panchayat inThiruverumbur Block Earthworkexcavation and depositing on bank with an initial lead of 10m and lift of 2m in the following classification of soils as directed by TWAD Board officers. Hard stiff clay, block cotton, hard red earth shales, murram, ordinary gravel, stoney earth and earth mixedwith smallsize boulders for foundation SS 20B First depth 0.00 - 2m |
| 2 | Seconddepth2.00 m -Below For Column Foundation |
| 3 | Sand filling for foundation with clear river sand including cost of sand watering, ramming and consolidationetc complete. |
| 4 | Cementconcrete1:4:8 (one cement four sand and eight aggregates) using 40mm HBGS for levelling course for foundation including the cost of mixing concrete, ramming, curing etc., complete. |
| 5 | Supplying and erecting steel centering for sides and soffits I including necessary supports\" and shuttering to the required height for RCC items using MS sheets of suitable size of BG.10 stiffeneq with welded MS angles of size 25mm x 25mm x3mm of boarding, laid over silver oak joints of size 10cm x 6.5cm spaceqat 90cm centre to centre and supported by casuarina props of 10cm to 13cm dia spaced at 75cm centre to centre complying with standard specifications etc., complete and as directed by TWAD Board officers. PLANE SURFACESBelow GL |
| 6 | Supplying, fabricating and placing in position of HSD steel rods for Reinforcement including the cost of steel and binding wire etc., complete. |
| 7 | RCC in M30 GRADE using graded aggregtes of HBGs excluding cost of reinforcement, centering, shuttering strutting, but including cost of mixing concrete, placing, vibrating withmechanical vibrator, finishing, curing etc., complete MAT Concrete |
| 8 | Supplying and erecting steel centering for sides and soffits I including necessary supports\" and shuttering to the required height for RCC items using MS sheets of suitable size of BG.10 stiffeneq with welded MS angles of size 25mm x 25mm x3mm of boarding, laid over silver oak joints of size 10cm x 6.5cm spaceqat 90cm centre to centre and supported by casuarina props of 10cm to 13cm dia spaced at 75cm centre to centre complying with standard specifications etc., complete. Square column Cen. Rate |
| 9 | RCC in M30 GRADE using graded aggregtes of HBGs excluding cost of reinforcement, centering, shuttering strutting, but including cost of mixing concrete, placing, vibrating withmechanical vibrator, finishing, curing etc., complete.RCC Rate Below GL |
| 10 | Earthworkexcavation and depositing on bank with an initial lead of 10m and lift of 2m in the following classification of soils as directed by TWAD Board officers. Hard stiff clay, block cotton, hard red earth shales, murram, ordinary gravel, stoney earth and earth mixedwith smallsize boulders for foundation SS 20B |
| 11 | Cementconcrete1:4:8 (one cement four sand and eight aggregates) using 40mm HBGS for levelling course for foundation including the cost of mixing concrete, ramming, curing etc., complete as directed by TWAD Board officers. |
| 12 | Supplying and erecting steel centering for sides and soffits I including necessary supports\" and shuttering to the required height for RCC items using MS sheets of suitable size of BG.10 stiffeneq with welded MS angles of size 25mm x 25mm x3mm of boarding, laid over silver oak joints of size 10cm x 6.5cm spaceqat 90cm centre to centre and supported by casuarina props of 10cm to 13cm dia spaced at 75cm centre to centre complying with standard specifications etc., complete. |
| 13 | Supplying, fabricating and placing in position of HSD steel rods for Reinforcement including the cost of steel and binding wire etc., complete As per Sl. No. 2 of Steel Schedule |
| 14 | RCC in M30 GRADE using graded aggregtes of HBGs excluding cost of reinforcement, centering, shuttering strutting, but including cost of mixing concrete, placing, vibrating withmechanical vibrator, finishing, curing etc., complete. |
| 15 | Refilling the foundation with excavated earth including watering and consolidation etc., complete. |
| 16 | Supplying and erecting steel centering for sides and soffits I including necessary supports\" and shuttering to the required height for RCC items using MS sheets of suitable size of BG.10 stiffeneq with welded MS angles of size 25mm x 25mm x3mm of boarding, laid over silver oak joints of size 10cm x 6.5cm spaceqat 90cm centre to centre and supported by casuarina props of 10cm to 13cm dia spaced at 75cm centre to centre complying with standard specifications etc., complete.Centering Rate Square column (0.00 to 2.65) |
| 17 | RCC in M30 GRADE using graded aggregtes of HBGs excluding cost of reinforcement, centering, shuttering strutting, but including cost of mixing concrete, placing, vibrating withmechanical vibrator, finishing, curing etc., complete.RCC Rate (0.00 to 2.65) |
| 18 | Supplying and erecting steel centering for sides and soffits I including necessary supports\" and shuttering to the required height for RCC items using MS sheets of suitable size of BG.10 stiffeneq with welded MS angles of size 25mm x 25mm x3mm of boarding, laid over silver oak joints of size 10cm x 6.5cm spaceqat 90cm centre to centre and supported by casuarina props of 10cm to 13cm dia spaced at 75cm centre to centre complying with standard specifications etc., complete.FIRST BRACE BEAM - (2.65 - 3.10) |
| 19 | Supplying, fabricating and placing in position of HSD steel rods for Reinforcement including the cost of steel and binding wire etc., complete As per Sl. No. 3 of Steel Schedule |
| 20 | RCC in M30 GRADE using graded aggregtes of HBGs excluding cost of reinforcement, centering, shuttering strutting, but including cost of mixing concrete, placing, vibrating withmechanical vibrator, finishing, curing etc., complete.RCC Rate (2.65 - 3.10) |
| 21 | First Brace Beam Laid Supplying and erecting steel centering for sides and soffits I including necessary supports\" and shuttering to the required height for RCC items using MS sheets of suitable size of BG.10 stiffeneq with welded MS angles of size 25mm x 25mm x3mm of boarding, laid over silver oak joints of size 10cm x 6.5cm spaceqat 90cm centre to centre and supported by casuarina props of 10cm to 13cm dia spaced at 75cm centre to centre complying with standard specifications etc., complete.First brace beam Top to Second beam bottom (3.10-5.75) |
| 22 | Sq.Col.Cent. Rate (3.30 - 4.30) |
| 23 | Sq.Col.Cent. Rate(4.30 - 5.30) |
| 24 | Sq.Col.Cent. Rate(5.30 - 5.75) |
| 25 | RCC in M30 GRADE using graded aggregtes of HBGs excluding cost of reinforcement, centering, shuttering strutting, but including cost of mixing concrete, placing, vibrating withmechanical vibrator, finishing, curing etc., complete.First brace beam Top to Second beam bottom (3.10-5.75) |
| 26 | Square Column(3.10 - 4.50) |
| 27 | Supplying and erecting steel centering for sides and soffits I including necessary supports\" and shuttering to the required height for RCC items using MS sheets of suitable size of BG.10 stiffeneq with welded MS angles of size 25mm x 25mm x3mm of boarding, laid over silver oak joints of size 10cm x 6.5cm spaceqat 90cm centre to centre and supported by casuarina props of 10cm to 13cm dia spaced at 75cm centre to centre complying with standard specifications etc., complete.Second Brace beam(5.75 - 6.20) |
| 28 | Supplying, fabricating and placing in position of HSD steel rods for Reinforcement including the cost of steel and binding wire etc., complete |
| 29 | RCC in M30 GRADE using graded aggregtes of HBGs excluding cost of reinforcement, centering, shuttering strutting, but including cost of mixing concrete, placing, vibrating withmechanical vibrator, finishing, curing etc., complete. |
| 30 | Supplying and erecting steel centering for sides and soffits I including necessary supports\" and shuttering to the required height for RCC items using MS sheets of suitable size of BG.10 stiffeneq with welded MS angles of size 25mm x 25mm x3mm of boarding, laid over silver oak joints of size 10cm x 6.5cm spaceqat 90cm centre to centre and supported by casuarina props of 10cm to 13cm dia spaced at 75cm centre to centre complying with standard specifications etc., complete.Second Brace beam Top to Third Brace Beam Bottom(6.20 - 8.85) |
| 31 | Sq. Col. Cent. Rate (6.30 - 7.30) |
| 32 | Sq. Col. Cent. Rate(7.30 - 8.30) |
| 33 | Sq. Col. Cent. Rate(8.30 - 8.85) |
| 34 | RCC in M30 GRADE using graded aggregtes of HBGs excluding cost of reinforcement, centering, shuttering strutting, but including cost of mixing concrete, placing, vibrating withmechanical vibrator, finishing, curing etc., complete.Column From Second Brace beam Top to Third Brace Beam Bottom(6.20 - 8.85) |
| 35 | Supplying and erecting steel centering for sides and soffits I including necessary supports\" and shuttering to the required height for RCC items using MS sheets of suitable size of BG.10 stiffeneq with welded MS angles of size 25mm x 25mm x3mm of boarding, laid over silver oak joints of size 10cm x 6.5cm spaceqat 90cm centre to centre and supported by casuarina props of 10cm to 13cm dia spaced at 75cm centre to centre complying with standard specifications etc., complete.THIRD BRACE BEAM - (8.85-9.30) |
| 36 | Supplying, fabricating and placing in position of HSD steel rods for Reinforcement including the cost of steel and binding wire etc., complete |
| 37 | RCC in M30 GRADE using graded aggregtes of HBGs excluding cost of reinforcement, centering, shuttering strutting, but including cost of mixing concrete, placing, vibrating withmechanical vibrator, finishing, curing etc., complete. Third Brace beam (8.76-9.00) |
| 38 | Third Brace beam (8.76-9.00) |
| 39 | Third Brace beam (8.76-9.00) |
| 40 | Third Brace beam (8.76-9.00) |
| 41 | LANDING BEAM THIRD BRACE BEAM LAIDSupplying and erecting steel centering for sides and soffits I including necessary supports\" and shuttering to the required height for RCC items using MS sheets of suitable size of BG.10 stiffeneq with welded MS angles of size 25mm x 25mm x3mm of boarding, laid over silver oak joints of size 10cm x 6.5cm spaceqat 90cm centre to centre and supported by casuarina props of 10cm to 13cm dia spaced at 75cm centre to centre complying with standard specifications etc., complete.Third Brace Beam Top to Floor (Grid) Beam Bottom (9.30 - 11.14) |
| 42 | Square Column(9.30 - 10.30) |
| 43 | Square Column(10.30 - 11.14) |
| 44 | Square Column(10.30 - 11.14) |
| 45 | RCC in M30 GRADE using graded aggregtes of HBGs excluding cost of reinforcement, centering, shuttering strutting, but including cost of mixing concrete, placing, vibrating withmechanical vibrator, finishing, curing etc., complete.Column From Third Brace beam Top to Floor (Grid) Beam Bottom(9.30 - 11.14) |
| 46 | Supplying and erecting steel centering for sides and soffits I including necessary supports\" and shuttering to the required height for RCC items using MS sheets of suitable size of BG.10 stiffeneq with welded MS angles of size 25mm x 25mm x3mm of boarding, laid over silver oak joints of size 10cm x 6.5cm spaceqat 90cm centre to centre and supported by casuarina props of 10cm to 13cm dia spaced at 75cm centre to centre complying with standard specifications etc., complete.Centering Rate plain surface (11.14 - 11.30) |
| 47 | Floor Slab Side (Curved Surface)Floor Slab side(0.00 - 0.26) Chainage Height (11.59-11.85) |
| 48 | Floor Slab Side (Curved Surface)Floor Slab side(0.00 - 0.26) Chainage Height (11.59-11.85) |
| 49 | Supplying, fabricating and placing in position of HSD steel rods for Reinforcement including the cost of steel and binding wire etc., complete |
| 50 | RCC in M30 GRADE using graded aggregtes of HBGs excluding cost of reinforcement, centering, shuttering strutting, but including cost of mixing concrete, placing, vibrating withmechanical vibrator, finishing, curing etc., complete.Grid (Floor) Beam(11.14 - 11.59) |
| 51 | Supplying and erecting steel centering for sides and soffits I including necessary supports\" and shuttering to the required height for RCC items using MS sheets of suitable size of BG.10 stiffeneq with welded MS angles of size 25mm x 25mm x3mm of boarding, laid over silver oak joints of size 10cm x 6.5cm spaceqat 90cm centre to centre and supported by casuarina props of 10cm to 13cm dia spaced at 75cm centre to centre complying with standard specifications etc., complete.Centering Rate plain surface (11.14 - 11.30) |
| 52 | Floor Slab Side (Curved Surface)Floor Slab side(0.00 - 0.26) Chainage Height (11.59-11.85) |
| 53 | Floor Slab Side (Curved Surface)Floor Slab side(0.00 - 0.26) Chainage Height (11.59-11.85) |
| 54 | Floor Slab Side (Curved Surface)Floor Slab side(0.00 - 0.26) Chainage Height (11.59-11.85) |
| 55 | RCC in M30 GRADE using graded aggregtes of HBGs excluding cost of reinforcement, centering, shuttering strutting, but including cost of mixing concrete, placing, vibrating withmechanical vibrator, finishing, curing etc., complete. Third Brace beam |
| 56 | Third Brace beam (8.76-9.00) |
| 57 | Supplying and erecting steel centering for sides and soffits I including necessary supports\" and shuttering to the required height for RCC items using MS sheets of suitable size of BG.10 stiffeneq with welded MS angles of size 25mm x 25mm x3mm of boarding, laid over silver oak joints of size 10cm x 6.5cm spaceqat 90cm centre to centre and supported by casuarina props of 10cm to 13cm dia spaced at 75cm centre to centre complying with standard specifications etc., complete.Centering Rate plain surface (11.14 - 11.30) |
| 58 | Floor Slab Side (Curved Surface)Floor Slab side(0.00 - 0.26) Chainage Height (11.59-11.85) |
| 59 | Supplying, fabricating and placing in position of HSD steel rods for Reinforcement including the cost of steel and binding wire etc., complete |
| 60 | RCC in M30 GRADE using graded aggregtes of HBGs excluding cost of reinforcement, centering, shuttering strutting, but including cost of mixing concrete, placing, vibrating withmechanical vibrator, finishing, curing etc., complete.Grid (Floor) Beam(11.14 - 11.59) |
| 61 | Providing PVC ventilating arrangements mosquito proof nylon net with 110 mm PVC pipes and cowl etc., complete., |
| 62 | Providing manhole cover of size 0.60 m X 0.60 m in RCC 1: 1.5:3 with suitable reinforcement and 5O x 5O x 6mm MS angle fixed along edges etc., complete., |
| 63 | Providing and fixing of RCC inner access ladder in RCC 1:1.5:3 (one cement, one and half sane! and three aggregates) using 20mm HBG stone for OHT including cost of reinforcement, placing grill in position, centering shuttering charges, mixing concrete curing etc., to required height and clear width of 4Scm consisting of two Nos. of ve~ical post of 10cm x lScm and step slab of 25mm x 25mm etc., complete. |
| 64 | Fabrication, supply, delivery and fixing of outside MS Ladder of 45cm clear wide made out of 50 mm x 50 mm x 60 mm MS angle for both sides and for steps at 30 cm C/C welded jointed etc., for I staging from GL to Fst level brace (weight 4.5kg/m) Iind and IIIrd staging upto floor slab and IVth staging from floor slab to roof top.Supply, delivery and fixing of 32 mm GI pipes medium for hand rails from I stage to IVth stage.RCC M30 Grade mix for Landing slab 5 nos. at Ground Level - 1 No. and abouve Ground Level - 4 Nos.Supply and fixing of 32 mm GI pipe medium for hand rails for the Landing slab.Supplying and fixing of MS base plate of 100 mm x 100mm x 6 mm thick for fixing Anchore fastener bolt for fixing of hand rails at Landing Slab and MS Ladder providing locking arrangements with two coats of approved enamel paint over one coat of red oxide paint as per approved Type Design and as directed by TWAD board officers. |
| 65 | Providing cut stone slab in CM 1:3 etc., complete.,(.45x.45x.15) |
| 66 | Towards cost and supply of plumbing materials for tank inlet, outlet, scour and over flow etc.,65mm dia GI pipes for inlet connection |
| 67 | 65mm dia GI pipes for over flow and RWH |
| 68 | 65mm dia GI pipes for delivery pipe.1 |
| 69 | 65mm dia GI pipes for delivery pipe.2 |
| 70 | 65mm dia GI pipes for scour pipe. |
| 71 | 90mm dia PVC FTA |
| 72 | 63mm dia PVC FTA |
| 73 | 65mm dia GI Tee |
| 74 | 65mm dia GI Coupler |
| 75 | 65mm dia GI flange |
| 76 | 65mm dia GI Elbow |
| 77 | 75 X 63mm dia PVC Reducer |
| 78 | 75 X 90 mm dia PVC Reducer |
| 79 | 65mm dia GM Gate Valve |
| 80 | 75mm PVC FTA |
| 81 | 63mm PVC Pipe 4KSC |
| 82 | 90mm PVC Pipe 4KSC |
| 83 | GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column \"BB\" for all works in this package} |
AI Tender Summary
Tender Timeline
Jul 31, 2024
11:30 IST
Tender Published
Tender notice published.
CompletedAug 06, 2024
17:00 IST
Bid Submission Deadline
Online submission via eProcurement portal.
CompletedAug 07, 2024
Bid Opening Date
Technical bids will be opened and evaluated.
CompletedTender Documents
Download All (ZIP) ↓
Disclaimer
We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender