| 1 | Earthwork in excavation of foundation of structure as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and otherdeleterious matter, dressing of sides and bottom, backfilling the excavation earth to the extent required and utilising the remaining earth locally for road work - by mechanical means - depth upto 3m Ordinary soil) |
| 2 | Construction of granular sub-base by providing close graded material, mixing in a mechanical mix plant at OMC, carriage of mixed material to work site, spreading in uniform layer with motorgrader on prepared surface and compacting with vibratory power roller to achieve the desireddensity, complete as per clause 401of MoRTH specification, 4th Revision - by plant mix method for grading I material. |
| 3 | Providing , laying , spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the material with water at OMC in mechanical mix plant carriage of mixed material by tipper to site , laying in uniform layer by manual means in sub-base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density - Using vibratory roller |
| 4 | Providing and applying primer coat with bitumen emulsion on prepared surface of granular base including clearing of road surface and spraying primer at the rate of 0.60 kg/sqm using mechanical means. (As per MoRTH specification, 4th Revision) |
| 5 | Providing and applying tack coat with bitumen emulsion using emulsion pressure distributor at the rate of 0.20 kg. per sqm. on the prepared bituminous / granular surface cleaned with mechanical broom. (As per MoRTH specification, 4th Revision) |
| 6 | Providing and laying bituminous macadam with hot mix plant of capacity not less than 40 -60 TPH using crushed aggregates of specified grading premixed with bituminous binder, transported to site, laid over a previously prepared surface with paver finisher to the required grade, level and alignment and rolled as per clauses 501.6 and 507.7 of MoRTH specification, 4th Revision, to achieve the desired compaction. - using grade II metal and bitumen 60/70 grade. |
| 7 | Providing and laying bituminous concrete with HMP of capacity not less than 40 to 60 TPH using crushed aggregates of specified grading, premixed with bituminous binder @ 5.4 to 5.6 percent of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per clause 509 of MoRTH specification, 4th Revision, complete in all respects - Using grade-II material.-Bitumen 60/70 |
| 8 | Providing and laying of hot applied thermoplastic compound 2.5mm thick including reflectorising glass beads @ 250 gms per sqm area, thickness of 2.5mm is exclusive of surface applied glass beads as per IRC:35. The finished surface to be level, uniform and free from streaks and holes. |
| 9 | Supplying and filling with gravel (excluding rock) in layers not exceeding 20cm in depth , breaking clods , watering , rolling each layer with 1/2 tonne roller , or wooden or steel rammers and rolling every 3rd and top-most layer with power roller of minimum 8 tonnes capacity including all leads and lift (Payment will be made based on level measurement) |