| 1 | Excavation ofPole pit for 7.5m / 8m Poles |
| 2 | Erection of 7.5m/8m Poles |
| 3 | Excavation ofPole pit for 9m Poles |
| 4 | Erection 9m Poles |
| 5 | Transporting of 7.5m/8m Poles from Road side to Pole Pit |
| 6 | Transporting of 9m Poles from Road side to Pole Pit |
| 7 | Loading and Unloading of 7.5m/8m Poles |
| 8 | Loading and Unloading of 9m Poles |
| 9 | Earthing of poles with GI Wires 4 or 6SWG by coil earthing |
| 10 | Excavation ofstay pit(1.00m X 0.5m X 1.5m) |
| 11 | Erection of Stay set |
| 12 | Fixing of V Cross arm/Channel cross arm 3.5\" |
| 13 | Fixing of LT.3 Phase cross arm |
| 14 | Fixing of LT Single Phase cross arm |
| 15 | Fixing of HT/LT. TI Fitting |
| 16 | Fixing of HT Pin Insulators with pin for 11KV, 22KV & 33KV |
| 17 | Fixing of HT Strain Disc with metal parts for11KV, 22KV & 33KV |
| 18 | Fixing of LT PIN Insulator/Shackles |
| 19 | Stringing, sagging binding of 7/2.59 ACSR or 7/2.50AAAC conductor including transporting of materials from road side to site. |
| 20 | Stringing, sagging binding of 7/3.35 ACSR or 7/3.15AAAC conductor including transporting of materials from road side to site. |
| 21 | Erection of Flat Guarding (2wires) /Split neutral guarding |
| 22 | Fixing of earthing device with Stud |
| 23 | Erection of 11 KV Single pole Structure of DT complete with centre Support. |
| 24 | Erectionof Upto 25 KVA Distribution transformer including Loading and Unloading at Stores/Office and Location |
| 25 | Alteration of Clamp |
| 26 | Slotted holes |
| 27 | Dismantling and Reerection of Single Phase Service connection |
| 28 | Dismantling and Reerection of Three Phase Service Connection |
| 29 | Grill seperation from deteriorated poles including transport to section(without concrete) |
| 30 | Dismantling of 7.5m /8m pole with out damage |
| 31 | Dismantling of 9.14m pole/ RSJ with out damage |
| 32 | Dismantling/ Reerection of stay complete |
| 33 | Replacement of detoriated stay rod |
| 34 | Tree clearance |
| 35 | Rectification of leaning of 7.5/8Mts. RCC,PSC Poles |
| 36 | Rectification of leaning 9.14mts RCC/RSJ & Tubular pole |
| 37 | Fixing of Phase Seperator 4Wire and 5Wire |
| 38 | Fixing of Phase Seperator 2Wire |
| 39 | Fixing of meter Box with meter on LV side of DT |
| 40 | Dismantling of 7.5m /8m pole with damage |
| 41 | Dismantling of 9.14m pole/ RSJ with damage |
| 42 | Dismantling and Re-erection of 7/2.59ACSR /2.50 AAAC Conductors |
| 43 | Dismantling and Re-erection of 7/3.35 ACSR /3.15 AAAC Conductors |
| 44 | G.S.T. @18% should be Entered by the Bidder |