| 1 | Supply of following decentralised materials as per RESSPO/PuVVNL norms at the work site. |
| 2 | 33 KV TOP CHANNEL CLAMP FOR ST POLE 11 MTR WITH NUT BOLT |
| 3 | 33 KV BRACING ANGLE CALMP FOR STP/ TOP / BOTTOM POLE WITH NUT BOLT |
| 4 | PG CLAMP |
| 5 | 33 KV CABLE JOINTING KIT 3X300 MM ² O/D |
| 6 | 33 KV CABLE JOINTING KIT 3X300 MM ² S/T |
| 7 | DANGER BOARD WITH CLAMP WITH NUT & BOLT |
| 8 | NUT & BOLT DIFFERENT SIZES |
| 9 | GI BARBED WIRE |
| 10 | 33 KV TOP CHANNEL |
| 11 | 33 KV BUSBAR GANTRY WITH TWO NOS STRUCTURE |
| 12 | 33 KV LA STRUCTURE |
| 13 | 33 KV ISOLATOR STRUCTURE |
| 14 | 33 KV POST STRUCTURE |
| 15 | 33 KV FUSE SET STRUCTURE |
| 16 | 90 IBS RAIL 2.5 MTR LONG FOR TWO NOS PLINTH |
| 17 | 33 KV FUSE SET COMPLETE |
| 18 | 33 KV BUS ISOLATOR |
| 19 | 33 KV LINE ISOLATOR |
| 20 | MS ANGLE 65X65X6 MM |
| 21 | 24 BOLT BATTERY WITH CHARGER WITH CABINET |
| 22 | CONTROL CABLE 2X2.5 MM ² |
| 23 | CONTROL CABLE 4X2.5 MM ² |
| 24 | AL LUG 300 Sqmm FOR LT CABLE LONG SIZE |
| 25 | RUBBER MAT |
| 26 | FIRE FIGHTING STAND WITH BUCKET |
| 27 | HAND GLOVES |
| 28 | S/S NAME BOARD AND ARROW BOARD |
| 29 | 33 KV VCB CONNECTER |
| 30 | 33 KV CT CONNECTER |
| 31 | 33 KV LA CONNECTER |
| 32 | 33 KV TOP CHANNEL FOR CABLE STAND |
| 33 | Shifting,loading ,carriage& unloadingof following materials on private truck at store centre Ballia & Un-loading of the same with proper stacking at work site . |
| 34 | S.T. Pole 11 M long. |
| 35 | ACSR ‘Dog’ Conductor |
| 36 | 33 KV ‘XLPE’ Cable 3x300mm² (900x2) mtr |
| 37 | OTHER MATERIALS ( X ARM, STAY EARTHING, DISC INSULATOR etc.) |
| 38 | 33 KV VCB WITH CONTROL PANNEL OFR SINGLE T/F CONTROL PANNEL & CT 200/100/1A WITH STRUCTURE & PT O/D 33/110 V WITH STRUCTURE. |
| 39 | 33 KV PPMC |
| 40 | 33 KV CT/PT POLE MOUNTED UNIT |
| 41 | 33 KV PT 33/110 WITH STRUCTURE |
| 42 | Work of following materials as per RESSPO/PuVVNL norms at the work site. |
| 43 | Erection of Single pole structure on 11 mtr ST. (SP-55) Pole including all works of evocation of pit, pole erection, & fitting of all accessories( \"V\" type cross arm 100 x 50 x 6 mm,/side arm with clamps with bolt and nut, composite polymer pin, insulator. complete as per RESSPO Norms) andErection of Double pole structure on 11 Mtr ST Pole including all works of evocation of pit, pole erection & fitting of all accessoriestop channel 125 x 65 x 3200 mm with clamps complete,disc insulater with fitting,etc as per RESSPO Norms) as per site requarment. |
| 44 | Instalation of VCB with Control Pannel, C.T. 200/100/1A including all works & fitting of all accessories etc as per RESSPO Norms) . |
| 45 | Instalation of 33 KV PT O/D 33/110 V WITH STRUCTURE including all works & fitting of all accessories etc as per RESSPO Norms) . |
| 46 | Instalation of 33 KV PPMC including all works & fitting of all accessories etc as per RESSPO Norms) . |
| 47 | Instalation of 33 CT/PT POLE MOUNTED UNITincluding all works & fitting of all accessories etc as per RESSPO Norms) . |
| 48 | Laying, spreading, lifting and final sagging of 3 phases of ACSR Dog conductorin accordance with profile and sag chart including binding, Jumpering and fixing of P.G. Clamp as per requirement in 03 Nos. conductor in parallel. |
| 49 | Grouting of stay rods (20 x 1800) mm including all work of excavation, cement concrete in size (0.60 x 0.60 x 0.30) m in ratio 1:4:8 cement, sand, 40mm brick ballast) as per drg including back filling, proper ramming etc. Fixing tightening & nozzling of stay wire with stay rod with the poles of required tension as per RESSPO Norms |
| 50 | Guarding between two poles like single poles, double poles, four poles, etc. to guard LT, 11 KV Line telephone and river crossing, road crossing etc. with G.I. wire no. 6 SWG and G.I. wire no. 8 SWG, cutting, fabrication and fixing of guarding channel 75 x 40 x 3010 mm with clamps nut & bolts etc. as per RESSPO Norms |
| 51 | Jointingcharges of 33 KV ‘XLPE’ C/J Kit 3x300mm² Outdoor |
| 52 | Jointingcharges of 33 KV ‘XLPE’ C/J Kit 3x300mm² S/T |
| 53 | Laying of 33 KV 3x300 mm² ‘XLPE’ cable(D/C) of Double cable by digging pit & making trench in Proper size(1.2M depth x1M wide) below ground level by fixing bricks(4½˝)on both side of trench wall and 9˝ brick work at the centre of the trench along the cable.Fixing brick slab on top after filling sand around both the cable including cost of bricks/ HDD Method as per site required. |
| 54 | Laying of 33KV ‘XLPE’ cable in air after providing 6” dia. M.S pipe 3.5 m long Complete work. |
| 55 | Earthing of Outdoor Structure and Equipments |
| 56 | Earthing of I/D Equipments |
| 57 | Separate Earthing of T/Fs with 400 mm dia GI pipe 30 feet long. |
| 58 | Switch yard lighting and aproach road |
| 59 | Painting of all structure & Equipments. |
| 60 | Earthing of poles by MS earthing rod 20x2500 mm with GI Wireas per RESSPO Norms |
| 61 | Concriting of poles as per RESSPO Norms |
| 62 | Making plinth forPoles as per RESSPO Norms |
| 63 | Fixing of danger boards on poles as per RESSPO Norms |
| 64 | Fixing of Barbed wire on poles as per RESSPO Norms |
| 65 | Fixing of PG Clamps |