Tender For Supply And Renovation Of Otis Make Boiler Unit - 6 Lift At Stps, Suratgarh. , Supply , Microprocessor Based V3f Drive Main Controller Suitable For18kw Motor , All Track Rollers, Door Sleepers, Gate Contactor, Pulley Of Landing Door , Door
Tender Overview
Project Description
Supply And Renovation Of Otis Make Boiler Unit - 6 Lift At Stps, Suratgarh. , Supply , Microprocessor Based V3f Drive Main Controller Suitable For18kw Motor , All Track Rollers, Door Sleepers, Gate Contactor, Pulley Of Landing Door , Door Drive Power Supply Unit, Track Roller Of Car Door , Infrared Door Sensor , Cop (G+5) , Lop With Direction And Position Indicator , Wiring Material Of Machine Room, Shaft Limit Switches And Gate Lock With Trailing Cable , Main Suspension Steel Wire Rope 13 Mm Dia. (Lift Duty) , Sub Total(From 1.02 To 1.05) , Total Packing & Forwarding Charges(On 1.06) , Sub Total Of Suppy+P&F (Including Gst) , Total Freight , Total Insurance Charges , Other Taxes/ Charges(If Any) , Total Supply Amount (1.08 To 1.10) , Etc ( As Per Scope Of Work) , Erection, Testing &Commissioning Of Lift After Replacement Of Item 1 To 8 , Any Other Charges , Total Etc Amount (2.01+2.02)
Corrigendum
| Sr No | Corrigendum Date | Corrigendum | Type | New Submission Date |
|---|---|---|---|---|
| 1 | 08-Jul-2024 | Extension-I | Date | 22-Jul-2024 |
| 2 | 22-Jul-2024 | EXT-II | Date | 05-Aug-2024 |
| 3 | 05-Aug-2024 | Extension-III-1948 | Date | 21-Aug-2024 |
BOQ
| Sl. No. | Item Description |
| 1 | Supply |
| 2 | Microprocessor based V3F drive main controller suitable for18KW motor |
| 3 | All track rollers, Door sleepers, Gate Contactor, Pulley of Landing Door |
| 4 | Door drive power supply Unit, Track roller of Car door |
| 5 | Infrared Door Sensor |
| 6 | COP (G+5) |
| 7 | LOP with direction and position indicator |
| 8 | Wiring material of machine room, shaft limit switches and gate lock with trailing cable |
| 9 | Main Suspension steel wire rope 13 mm Dia. (Lift Duty) |
| 10 | Sub Total(From 1.02 to 1.05) |
| 11 | Total Packing & Forwarding Charges(on 1.06) |
| 12 | Sub Total of Suppy+P&F (Including GST) |
| 13 | Total Freight |
| 14 | Total Insurance Charges |
| 15 | Other taxes/ charges(If any) |
| 16 | Total Supply amount (1.08 to 1.10) |
| 17 | ETC ( As per scope of work) |
| 18 | Erection, Testing &Commissioning of lift after replacement of item 1 to 8 |
| 19 | Any other charges |
| 20 | TOTAL ETC AMOUNT (2.01+2.02) |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedCorrigendum-1 Issued
Clarifications on tender conditions and amendments issued.
CompletedCorrigendum-2 Issued
Clarifications on tender conditions and amendments issued.
CompletedCorrigendum-3 Issued
Clarifications on tender conditions and amendments issued.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
CompletedBid Opening Date
Technical bids will be opened and evaluated.
CompletedTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender