| 1 | Charges for fixing and removing the scaffolding arrangements for Shifting of Ceiling Suspended Air Handling Units - 3 Nos at turbine pocket store rooms, south & north side of site & newly contructed AHUroom (Scaffolding Materials are under contractor scope) |
| 2 | Charges for dismantling the Ceiling Suspended Air Handling Units - 3 Nos and its connected Ducts, Bellows, Valves, Gauges, MS water pipe lines at TG building 17 Mtr Turbine pocket store including the cost of consumables, T&P, lead, lift etc., |
| 3 | Welding Charges for erection of MS ERW pipe lines of 80NB & 50 NB and patch works during shifting of Ceiling Suspended Air Washer unit - 3 Nos at TG building 17 Mtr Turbine pocket store to newly constructed room above the Turbine pocket store including the cost of consumables, T&P, lead, lift etc., |
| 4 | Charges for Assembling the Ceiling Suspended Air Handling Units - 3 Nos and its connected Ducts, Bellows, Valves, Gauges and erection of new MS water pipe lines at newly constructed room above the TG building 17 Mtr Turbine pocket store including the cost of consumables, T&P, lead, lift etc., |
| 5 | Charges for cleaning, painting of EPOXY zinc chromate primer one coat and EPOXY green paint two coats for newly erected MS ERW pipelines, supports etc., at newly constructed room above the TG building 17 Mtr Turbine pocket store including the cost of consumables, T&P, lead, lift etc., |
| 6 | Charges for checking the alignment and commissioning the Ceiling Suspended Air Handling Units - 3 Nos at newly constructed room above the TG building 17 Mtr Turbine pocket store including the cost of consumables, T&P, lead, lift etc., |
| 7 | Charges for removal of insulation by breaking the cement plaster in chill water pipelines at Ceiling Suspended Air Handling Units at TG building 17 Mtr Turbine pocket store room including the cost of consumables, T&P, lead, lift etc., |
| 8 | Charges for providing of new insulation for chill water pipelines at newly constructed room above the TG building 17 Mtr Turbine pocket store including the cost of consumables, T&P, lead, lift etc., |
| 9 | Charges for plastering (over the insulation) the chill water pipelines at Ceiling Suspended Air Handling Units at newly constructed room above the TG building 17 Mtr Turbine pocket store including the cost of consumables, T&P, lead, lift etc., |
| 10 | Material charges for 80 NB MS ERW pipe including the cost of transporting, consumables, lead, lift etc., |
| 11 | Material charges for 50 NB MS ERW pipe including the cost of transporting, consumables, lead, lift etc., |
| 12 | Material charges for 80 NB MS ERW 90 deg bend including the cost of transporting, consumables, lead, lift etc., |
| 13 | Material charges for 50 NB MS ERW 90 deg bend including the cost of transporting, consumables, lead, lift etc., |
| 14 | Material charges for 80 NB CI gate valve including the cost of transporting, consumables, lead, lift etc., |
| 15 | Material charges for 10mm MS Rod including the cost of transporting, consumables, lead, lift etc., |
| 16 | Material charges for insulation and plastering for chill water pipelines including the cost of transporting, consumables, lead, lift etc., |