Dakshinanchal Vidyut Vitran Nigam Limited-DVVNL has published Tender For The Work Of Energizing A Total Of 11 Connections And Other Connections Applied On The Jhatpat/Nivesh Mitra Portal Under The Deposit Scheme Under Electric Distribution Division-I/Ii, Orai By Constructing Lines.. Submission Date for this Tender is 21-05-2024. Electrification Work Tenders in orai Uttar Pradesh. Bidders can get complete Tender details and download the document.
FileName | File Description | File Size |
0e5e0994-2258-4d6e-84c5-68d5c7e4b6fc.html | Tender Notice | 0 KB |
BOQ_1596397.xls | Tender Document | 0 KB |
Tendernotice_1.pdf | Tender Document | 0 KB |
TF02.pdf | Tender Document | 0 KB |
Sl. No. | Item Description |
1 | PART-A |
2 | Carriage offollowing line Items from Store Center Orai to the Pit Site of work including measuring weiging loading unloading at both ends and proper stacking at safe site. |
3 | PCC Pole 8.5 Mtr Long |
4 | STP Pole 11 Mtr Long |
5 | 16 KVA 11/0.25 Kv T/F New |
6 | T/F 11/0.4 Kv 25 KVA |
7 | T/F 11/0.4 Kv 63 KVA |
8 | ACSR Weasel Conductor |
9 | ACSR Dog Conductor |
10 | Cable 11 KV(E) XLPE 3x120 sqmm/3 Core Alluminum Conductor (EC Grade) |
11 | 3x70 Sqmm XLPE Cable |
12 | Cable Jointing Kit Indoor/outdoor 3x120 sqmm |
13 | ID & O/D Cable Jointing Kit Suitable for 3x70 mm XLPE Cable |
14 | G.I. Wire 6/8/10 Swg |
15 | Barbed wire |
16 | Stay wire 7/10 Swg |
17 | D.O. Fuse Set 3 Phase |
18 | Stay Complete |
19 | Earthing Complete |
20 | Other Line Item as 11 Kv Pin Insulator with fitting, 11 Kv Disc Insulator with fitting, 11 Kv Top Channel, 11 Kv Dropper Channel, Base Angle of T/F, Stone Pad, Alluminum Paint, Red Oxide Paint, Danger Board with clamp, Number Plate, STP Pole Clamp etc as per estimate |
21 | PART-B |
22 | Supply of the following line Item By Contractor as per RESSPO drawing & dimension:- |
23 | G.I. Pipe 6" Dia |
24 | PART-C |
25 | Erection of the following supports after making of pits as per RESSPO norms & filling of pits by concrete of ratio 1:4:8 (cement brick balast & sand). Fitting of all accessories as 11 Kv Pin Insulator with fitting, 11 Kv Disc Insulator with fitting, 11 Kv Top Channel, 11 Kv Dropper Channel, Base Angle of T/F, Stone Pad, Alluminum Paint, Red Oxide Paint, Danger Board with clamp, Number Plate, STP Pole Clamp etc as per estimate Plinthing of support above 300mm ground level by concrete of ratio 1:4:8(cement brick balast & sand)will be done at the time of erection of pole. Painting of ST Pole structure as per RESSPO norms also (all type of paints, red oxide primer, nut, bolts & grouting material etc. will be provided by contractor). |
26 | PCC 8.5 meter long with grouting, earthing concreting of support & stay including all fitting as per resspo norms. |
27 | STP 11 meter long with grouting, earthing concreting of support & stay including all fitting as per resspo norms. |
28 | Energization of 16 KVA 11/0.25 Kv T/F New with all fitting including earthing as per resspo norms |
29 | Energization of T/F 11/0.4 Kv 25 KVA with all fitting including earthing as per resspo norms |
30 | Energization of T/F 11/0.4 Kv 63 KVA with all fitting including earthing as per resspo norms |
31 | ACSR Weasel Conductor as per resspo norms |
32 | ACSR Dog Conductor as per resspo norms |
33 | Cable 11 KV(E) XLPE 3x120 sqmm/3 Core Alluminum Conductor (EC Grade) as per resspo norms |
34 | 3x70 Sqmm XLPE Cable as per resspo norms |
35 | Cable Jointing Kit Indoor/outdoor 3x120 sqmm as per resspo norms |
36 | ID & O/D Cable Jointing Kit Suitable for 3x70 mm XLPE Cable as per resspo norms |
37 | G.I. Wire 6/8/10 Swg as per resspo norms |
38 | Barbed wire as per resspo norms |
39 | Stay wire 7/10 Swg as per resspo norms |
40 | D.O. Fuse Set 3 Phase as per resspo norms |
41 | Stay Complete as per resspo norms |
42 | Earthing Complete as per resspo norms |
43 | G.I. Pipe 6" Dia as per resspo norms |
Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy