Tender For Work To Be Done In Anticipation Of Receiving Financial Approval For Construction And Bifurcation Of 11 Kv Line ( Including Semi-Turnkey Decentralized Material ) Under Business Plan 2024-25 ( Summer Plan ) In The Jurisdiction Of Elect, lakhimpur-Uttar Pradesh

Madhyanchal Vidut Vitran Nigam Limited has published Tender For Work To Be Done In Anticipation Of Receiving Financial Approval For Construction And Bifurcation Of 11 Kv Line ( Including Semi-Turnkey Decentralized Material ) Under Business Plan 2024-25 ( Summer Plan ) In The Jurisdiction Of Elect. Submission Date for this Tender is 07-05-2024. Electrification Work Tenders in lakhimpur Uttar Pradesh. Bidders can get complete Tender details and download the document.




Tender Notice

43277146
Tender For Work To Be Done In Anticipation Of Receiving Financial Approval For Construction And Bifurcation Of 11 Kv Line ( Including Semi-Turnkey Decentralized Material ) Under Business Plan 2024-25 ( Summer Plan ) In The Jurisdiction Of Elect
Open Tender
Indian
Uttar Pradesh
lakhimpur
07-05-2024

Tender Details

Tender For Work To Be Done In Anticipation Of Receiving Financial Approval For Construction And Bifurcation Of 11 Kv Line ( Including Semi-Turnkey Decentralized Material ) Under Business Plan 2024-25 ( Summer Plan ) In The Jurisdiction Of Electricity Distribution Division-I, Lakhimpur. -1 Estimate For Installation Of Mid Span Poles For Strengthening Of 11 Kv Line Feeders Town No. 01, 03 And 04 Under 33 / 11 Kv Substation Chhauchh Lakhimpur 2 Supply And Fixing Of Clamp With Bolts And Nuts 3 Grouting Of Stay 4 Digging Of Pits Then Erection Of Pole By Stp Pole, Grouting Of Stp Pole With Groutng Materials Including Fitting Of Required All Accessories As Per Respo Norms. 5 Supply And Fixing Of Cross Arm Holding Clamps 6 Ordinary Earthing By Ms Earth Rod 2500Mm Long As Per Respo Schedule. Only Gi Wire. 7 Carriage & Errection Of 24 No. Disc Insulator, 10 No. Stay Complete , 2 No. 11 Kv Top Channel, 25 No. Stp Poles, 2 No. Dropper Channel , 25 No. 11 Kv Cross Arms , 11 Kv F-Clamp, 4 No. Tee Off Channel And 24 No. Earthing Completefrom Store To Working Site Feeder No. 01, 03 And 04 With Labour For Installation Of Poles At Site Feeder No. 01, 03 And 04 Under 33 / 11 Kv Substation Chhauchh Lakhimpur Providing All Suitable Decentralised Materials And T&P Shall Be Provided By The Contractor 8 11 Kv Feeder Trifurcation Of Town No. 01 At Kheri Town 9 Carriage And Errection Of Stp Pole 11 Meter 77 Nos., X-Arm M.S. Angle 65*65*6Mm V Type 66 Nos., 11Kv Composite Pin Insulator 198 Nos., Acsr Weasel Conductor 11.55 Km., Stay Complete 20 Nos., Earthing Complete 74 Nos., Top Channel Ms. 100*50*2240Mm 05 Nos., 11Kv Comp. Polymer Disc Insulator B & S Type 54 Nos., 11 Kv Ms Angle 65X65x6 48 Kg., 11 Kv F Clamp 66 No.S, Tee-Off Channel 18 Nos., Dropper Channel 6 Nos., G.I. Wire 10 Swg 30 Kg From Store To Site 11 Kv Town No. 01 For Feeder Seperation Under 33 / 11 Substation Kheri Town With Labour For Erection Of 77 Nos. Stp Pole Including Dragging With Fitting Of All Accessories As Per Respo Norms Providing All Suitable Decentralised Materials And T&P Shall Be Provided By The Contractor. 10 Digging Of Pits Then Erection Of Pole By Stp Pole, Grouting Of Stp Pole With Groutng Materials Including Fitting Of Required All Accessories As Per Respo Norms. 11 Digging Of Pits, Fixing Nozzling & Grouting Of Stay Rod Including Fitting Of All Accessories With Grouting Materials As Per Respo Norms. 12 Ordinary Earthing By Ms Earth Rod 2500Mm Long As Per Respo Schedule. Only Gi Wire. 13 Supply And Fixing Of Stone Pads 14 Supply And Fixing Of Clamp With Nuts And Bolts. 15 Estimate For Construction Of New Lt Line Near C.B. Singh School Under Substation Lakhimpur Town 16 Carriage And Errection Of 3 Nos. Pcc Poles, 110 Mtr. Ab Cable ( 3X50 Sq.Mm ) , 2 No. 3-Ph Distribution Box And 1 No. Stay Complete From Store To Site Near C.B. Singh School With Labour For Construction Of New Lt Line At Near C.B. Singh School Under 33 / 11 Kv Substation Lakhimpur Town Providing All Suitable Decentralizes Material For Completion Of Work And T&P Shall Be Provided By The Contractor 17 Grouting Of Stay 18 Grouting Of Poles 19 Supply And Fixing Of Clamps For Distribution Box With Nuts And Bolts 20 Supply And Fixing Of Lt Shackle Insulator 21 Supply And Fixing Of Clamp For Lt Shackle Insulator With Nuts And Bolts 22 Estimate For Construction Of Three Phase Lt Line At Lahauri Nagar Under Substation Kheri Town 23 Carriage And Errection Of, 1110 Mtr. Ab Cable ( 3X95 Sq.Mm ) , 10 Nos. 3-Ph Distribution Box And 5 Nos. Stay Complete From Store To Site Near C.B. Singh School With Labour For Construction Of New Lt Line At Near C.B. Singh School Under 33 / 11 Kv Substation Lakhimpur Town Providing All Suitable Decentralizes Material For Completion Of Work And T&P Shall Be Provided By The Contractor 24 Grouting Of Stay 25 Supply And Fixing Of Clamps For Distribution Box With Nuts And Bolts 26 Supply And Fixing Of Clamps With Nuts And Bolts 27 Supply And Fixing Of Lt Shackle Insulator

Key Value

Document Fees
INR 3540 /-
EMD
INR 12150.0 /-
Tender Value
INR 12.15 Lakhs /-

BOQ Items

Name of Work: fo|qr forj.k [k.M&izFke] y[kheiqj ds dk;Z{ks= esa fctusl Iyku 2024&25 ¼lej Iyku½ ds vUrxZr ,y0Vh0] 11 ds0oh0 ykbu dk fuekZ.k ,oa ckbQjds’ku gsrq foRrh; vuqeksnu izkIr gksus dh izR;k’kk esa fd;k tkus okyk dk;Z ¼lseh VuZdh fodsUnzh;d`r lkexzh lfgr½A
Sl. No. Item Description
1Estimate for installation of mid span poles for strengthening of 11 KV line feeders Town no. 01, 03 and 04 under 33/11 KV Substation Chhauchh Lakhimpur
2Supply and fixing of Clamp with bolts and nuts
3Grouting of Stay
4Digging of pits then erection of pole by STP pole, grouting of STP pole with groutng materials including fitting of required all accessories as per RESPO Norms.
5Supply and fixing of Cross arm holding clamps
6Ordinary earthing by MS earth Rod 2500mm long as per RESPO Schedule. Only GI wire.
7Carriage & errection of 24 no. disc insulator, 10 no. stay complete , 2 no. 11 kv top channel, 25 no. STP poles, 2 no. Dropper Channel ,25 no. 11 Kv Cross arms , 11 KV F-clamp, 4 no. Tee off channel and 24 no. earthing completefrom store to working site feeder no. 01, 03 and 04 with Labour for installation of poles at site feeder no. 01, 03 and 04 under 33/11 KV Substation Chhauchh Lakhimpur providing all suitable decentralised materials and T&P shall be provided by the contractor
811 KV feeder trifurcation of town no. 01 at Kheri Town
9Carriage and errection of STP Pole 11 Meter 77 Nos., X-arm M.S. Angle 65*65*6mm V type 66 Nos., 11KV composite Pin insulator 198 Nos., ACSR Weasel Conductor 11.55 km., Stay complete 20 Nos., Earthing Complete 74 Nos., Top channel MS. 100*50*2240mm 05 Nos., 11kV comp. polymer disc insulator B & S type 54 Nos., 11 Kv MS angle 65X65X6 48 Kg., 11 KV F clamp 66 no.s, Tee-off channel 18 Nos., Dropper Channel 6 Nos., G.I. wire 10 swg 30 Kg from store to site 11 KV town no. 01 for feeder seperation under 33/11 Substation Kheri town with Labour for Erection of 77 Nos. STP Pole including dragging with fitting of all accessories as per RESPO Norms providing all suitable decentralised materials and T&P shall be provided by the contractor.
10Digging of pits then erection of pole by STP pole, grouting of STP pole with groutng materials including fitting of required all accessories as per RESPO Norms.
11Digging of pits, fixing nozzling & grouting of stay rod including fitting of all accessories with grouting materials as per RESPO Norms.
12Ordinary earthing by MS earth Rod 2500mm long as per RESPO Schedule. Only GI wire.
13Supply and Fixing of Stone pads
14Supply and Fixing of Clamp with nuts and bolts.
15Estimate for construction of new LT line near C.B. Singh School under Substation Lakhimpur Town
16Carriage and errection of 3 Nos. PCC poles, 110 mtr. AB Cable (3X50 sq.mm), 2 No. 3-Ph Distribution box and 1 No. Stay Complete from store to site near C.B. Singh School with Labour for construction of new LT line at near C.B. Singh School under 33/11 KV Substation Lakhimpur Town providing all suitable decentralizes material for completion of work and T&P shall be provided by the contractor
17Grouting of Stay
18Grouting of Poles
19Supply and fixing of Clamps for distribution box with nuts and bolts
20Supply and fixing of LT Shackle insulator
21Supply and fixing of clamp for LT Shackle insulator with nuts and bolts
22Estimate for construction of three phase LT line at Lahauri nagar under Substation Kheri Town
23Carriage and errection of, 1110 mtr. AB Cable (3X95 sq.mm), 10 Nos. 3-Ph Distribution box and 5 Nos. Stay Complete from store to site near C.B. Singh School with Labour for construction of new LT line at near C.B. Singh School under 33/11 KV Substation Lakhimpur Town providing all suitable decentralizes material for completion of work and T&P shall be provided by the contractor
24Grouting of Stay
25Supply and fixing of Clamps for distribution box with nuts and bolts
26Supply and fixing of Clamps with nuts and bolts
27Supply and fixing of LT Shackle insulator
Disclaimer :
We takes all possible care for accurate & authentic tender information, however Users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender.
Tell us about your Product / Services,
We will Find Tenders for you

Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy

For Tender Information Services Visit : TenderDetail