Dakshinanchal Vidyut Vitran Nigam Limited-DVVNL has published Tender For For The Work Of 33/11 Kv Protection Work At Various Sub-Stations On Semi-Turn-Key Basis In The Business Plan 2024-25 Under The Area Of Electricity Urban Distribution Circle, Firozabad. Submission Date for this Tender is 08-05-2024. Flood Protection Tenders in firozabad Uttar Pradesh. Bidders can get complete Tender details and download the document.
Sr No | CorrigendumDate | Corrignedum | CorrigendumType | NewSubmissionDate |
1 | 01-May-2024 | Date Extension_1 | Date | 08-05-2024 |
FileName | File Description | File Size |
4c5b7791-b5c0-4ae8-a861-11701d724e52.html | Tender Notice | 0 KB |
BOQ_1593710.xls | Tender Document | 0 KB |
T-50.rar | Tender Document | 0 KB |
Tendernotice_1.pdf | Tender Document | 0 KB |
Sl. No. | Item Description |
1 | Carriage of following materialfrom Centre Stores, Asfabadto site of work through the Kacha and Pakka road including the work of its loading and unloading at the respective ends in the area of EUDC, Firozabad, including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work.(Distance 00-20 Kms.) |
2 | 33 Kv PT |
3 | 33 kv Fuse Set |
4 | ST POLE 11 METER LONG IS 410 SP55 |
5 | ACSR DOG CONDUCTOR |
6 | 11 KV XLPE CABLE 3*185 SQMM |
7 | 11 KV INDOOR JOINTING KIT 3x185 sqmm |
8 | 11 KV OUTDOOR JOINTING KIT3x185 sqmm |
9 | 11 KV VCB OUTGOING CTR 300/150/5A |
10 | 11 KV VCB INCOMING CTR 600/300/5A |
11 | 11 KV POLYMER PIN INSULATOR - 195 NO. 11 KV POLYMER DISC INSULATOR WITH FITTING- 06 NO. T OFF CHANNNEL- 5 NO. TOP CHANNEL - 5 NO. DROPPER CHANNEL - 5 NO. STAY SET COMPLETE- 20 NO. MS CLAMP FOR TOP/DROPPER/X ANGLE FOR ST/PCC POLE - 320 NO. |
12 | Supply & Erection of the Following Material. |
13 | GI PIPE 6* DIA FOR CABLE HOSTING - 40 MTR 11 KV CROSS ARM - 65 NO. 11 KV CROSS ARM CLAMP WITH N&B - 65 NO. 11 KV F CLAMP - 65 NO. T CHANNEL CLAMP WITH N&B - 5 NO. DANGER BOARD WITH CLAMP - 73 NO. BARBERD WIRE - 133 KG STONE PAD - 73 NO. NUT BOLT WITH WASHER - 40 KG CROSS BRACING ANGLE SET - 12 NO. HOISTING CLAMP FOR ST POLE- 10 NO. |
14 | Erection of 11 M long STP Double Pole Structure including duly grouted in cement, sand and brick ballast in ratio 1:2:4, including work of fitting of all accessories, stone pad and clamps suitable for AB cable. Work will be carried out as per RESPO manual and as per direction of supervising engineer including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work. Grouting material i.e. cement, sand, brick ballast/stone ballast etc. shall be arranged by the contractor at his own cost. |
15 | Replacement of 02 No. Bushing rod of 11 KV side of 5 Mva Power Tf No. 1including labour and other charges at 33/11 kv s/s Ram Nagar as per RESPO manual as per direction of supervising engineer including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work. |
16 | Replacement of 01 No. Bushing rod of 11 KV side of 10 Mva Power Tf No. 1including labour and other charges at 33/11 kv s/s Industrial State as per RESPO manual as per direction of supervising engineer including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work. |
17 | Replacement of 02 No. Bushing rod of 11 KV side of 10 Mva Power Tf No. 2 and Gasket seal and oil seal including labour and other charges at 33/11 kv s/s Industrial State as per RESPO manual as per direction of supervising engineer including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work. |
18 | Replacement of 33 kv PT as per RESPO manual incl. Damage PT carriage to centre store Asfabad as per direction of supervising engineer including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work. |
19 | Installation of 33 kv Fuse set as per RESPO as per direction of supervising engineer including the cost of arrangement of labour, T&P, carrier and required accesories etc. required for proper completion of work. |
20 | Erection of the Following. |
21 | 11 KV VCB OUTGOING CTR 300/150/5A |
22 | 11 KV VCB INCOMING CTR 600/300/5A |
23 | A- 11 KV INDOOR JOINTING KIT 3x185 sqmm -04 NO. B- 11 KV OUTDOOR JOINTING KIT3x185 sqmm - 10 NO. |
24 | Laying of the following cable. |
25 | 11 KV XLPE CABLE 3*185 SQMM |
26 | ACSR DOG CONDUCTOR |
27 | PIPE TYPE EARTHING COMPLETE 20 MTR DEEP WITH HELP OF 3" B GLASS PIPE as per RESPO manual and as per direction of supervising engineer including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work. |
28 | Fixing of earthing rod for pole earthing as per RESPO manual and as per direction of supervising engineer including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work. |
29 | Erection and grouting of stays as per RESPO manual and as per direction of supervising engineer including the costof arrangement of labour, T&P, carrier etc. required for proper completion of work. Grouting material i.e. cement, sand, brick ballast/stone ballast etc. shall be arranged by the contractor at his own cost. |
30 | Concreting of pole 0.880 cu. M. each per RESPO manual and as per direction of supervising engineer including the costof arrangement of labour, T&P, carrier etc. required for proper completion of work. Grouting material i.e. cement, sand, brick ballast/stone ballast etc. shall be arranged by the contractor at his own cost. |
31 | Carriage of dismantle material i.e. poles and other accessories of 33 KV, 11 KV and LT line as mentioned above from site to Centre store Asfabad(10 Kms.) |
Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy