Uttar Pradesh Rajya Vidyut Utpadan Nigam Limited-UPRVUNL has published Tender For Preventive Breakdown Maintenance Of Bfp Cep Vac Pump Preventive And Breakdown Maintenance Of Boiler Feed Pump, Booster Pump, Hydraulic Coupling, Condensate Extraction Pump And Vacuum Pumps Of Unit 8And9 Of Dtps , Kasimpur Aligarh.. Submission Date for this Tender is 30-04-2024. Electrification Work Tenders in Aligarh Uttar Pradesh. Bidders can get complete Tender details and download the document.
FileName | File Description | File Size |
74780961-50fb-4742-9a6f-8e7af01ab15f.html | Tender Notice | 0 KB |
BOQ_1593083.xls | Tender Document | 0 KB |
tenderdocstet02.pdf | Tender Document | 0 KB |
Tendernotice_1.pdf | Tender Document | 0 KB |
Tendernotice_2.pdf | Tender Document | 0 KB |
Sl. No. | Item Description |
1 | BOILER FEED PUMP TYPE FK-6D-30 (WEIR MAKE). |
2 | Threading out of BFP Cartridge. Time of Completion 48 Hrs |
3 | Threading in spare/repaired BFP Cartridge assembly. Time of Completion 48 Hrs |
4 | Inspection, Replacement & rectification of NDE Mechanical seals of Boiler Feed Pumps. Time of Completion 08 Hrs |
5 | Inspection, Replacement and Rectification of DE Mechanical seals of Boiler Feed Pumps. Time of Completion 08 Hrs |
6 | Inspection and Rectification of NDE Thrustcum Journal bearings of BFP. Time of Completion 06 Hrs |
7 | Inspection of Thrust pads of NDE bearings of Boiler Feed pumps. Time of Completion 06 Hrs |
8 | Inspection and Rectification of DE journal bearing of BFP. Time of Completion 06 Hrs |
9 | Attending leakages from stuffing box of BFPs. Time of Completion 24 Hrs |
10 | Inspection and Re-visioning of DE water-jackets of Boiler Feed Pumps. Time of Completion 08 Hrs |
11 | Inspection and Re-visioning of NDE water-jackets of Boiler Feed Pumps. Time of Completion 08 Hrs |
12 | Replacement / Refitting of Damaged half coupling, (Pump /Hydraulic coupling /motor), with new one. Time of Completion 06 Hrs |
13 | Replacement/Refitting of complete (both side) damaged coupling between motor & hydraulic coupling / between hydraulic coupling & BFP side, with new one. Time of Completion 10 Hrs |
14 | Checkingandadjustmentofradialandaxial alignment of BFP with hydraulic coupling. Time of Completion 06 Hrs |
15 | BOOSTER PUMP TYPE FA 1B-56 |
16 | Inspection and Rectification of NDE Thrustcum journal bearing of Booster pump. Time of Completion 06 Hrs |
17 | Inspection and Rectification of DE journal bearing of Booster pump. Time of Completion 06 Hrs |
18 | Inspection and Rectification of DE mechanical seals of Booster pump. Time of Completion 08 Hrs |
19 | Inspection and Rectification of NDE mechanical seals of Booster pump. Time of Completion 08 Hrs |
20 | Replacement of Damaged half coupling, (Booster Pump side/motor side), with new one. Time of Completion 06 Hrs |
21 | Replacement of complete (both side) damaged coupling between motor & Booster Pump, with new one. Time of Completion 10 Hrs |
22 | De-assembly / checking / servicing and rectification of defective booster pump assembly. Time of Completion 24 Hrs |
23 | Replacement of spare / repaired booster pump assembly and its commissioning. Time of Completion 24 Hrs |
24 | Checking and adjustment ofradialandaxial alignment of Booster pump with BFP motor. Time of Completion 06 Hrs |
25 | HYDRAULIC COUPLING TYPE R-16K (VOITH MAKE) |
26 | Inspection and Re-visioning of cam controller assembly. Time of Completion 08 Hrs |
27 | Servicing and rectification of internals of Hydraulic coupling their reassembly and commissioning. Time of Completion 48 Hrs |
28 | Inspection and Rectification of thrust bearing no.3 and 4 of Hydraulic coupling. Time of Completion 10 Hrs |
29 | Checking and adjustmentofradialandaxial alignment of hydraulic coupling with BFP motor. Time of Completion 06 Hrs |
30 | MOTOR |
31 | Replacement/Servicing of bearing of Motor. (Booster Pump side /Hydraulic Coupling side). Time of Completion 06 Hrs |
32 | Servicing / cleaning of water cooler of BFP Motor. Time of Completion 24 Hrs |
33 | CONDENSATE EXTRACTION PUMP TYPE EN 7H-32 |
34 | Servicing/Overhauling of Condensate extraction pump Type EN7H-32. Time of Completion 48 Hrs |
35 | Inspection and rectification ofThrustBearingand journal bearing of condensate extraction pumps. Time of Completion 06 Hrs |
36 | Re-alignment and adjustment of condensate extraction pump with motor. Time of Completion 02 Hrs |
37 | Vacuum Pump TC-11 make NASH |
38 | Complete servicing/overhauling of vacuum pump Type- TC-11 Make: NASH. Time of Completion 10 Days |
39 | Replacement/Servicing of DE bearing of main vacuum pump. Time of Completion 24 Hrs |
40 | Replacement/Servicing of NDE bearing of main vacuum pump. Time of Completion 06 Hrs |
41 | Replacement of DE/NDE gland of main pump. Time of Completion 02 Hrs |
42 | Alignment & adjustment of vacuum pump with motor. Time of Completion 06 Hrs |
Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy
For Tender Information Services Visit : TenderDetail