Tender For Providing, Fixing And Installation Frp Huts In Menchuka Valley, Dist-Shi-Yomi (A.P.) (Sh:Civil Work For Base Of Frp Hut), West Siang-Arunachal Pradesh

Indo Tibetan Border Police Force-ITBP has published Tender For Providing, Fixing And Installation Frp Huts In Menchuka Valley, Dist-Shi-Yomi (A.P.) (Sh:Civil Work For Base Of Frp Hut). Submission Date for this Tender is 27-04-2024. Civil Work Tenders in West Siang Arunachal Pradesh. Bidders can get complete Tender details and download the document.




Tender Notice

43122048
Corrigendum : Tender For Providing, Fixing And Installation Frp Huts In Menchuka Valley, Dist-Shi-Yomi (A.P.) (Sh:Civil Work For Base Of Frp Hut)
Open Tender
Indian
Arunachal Pradesh
West Siang
27-04-2024

Tender Details

Tender For Providing, Fixing And Installation Frp Huts In Menchuka Valley, Dist-Shi-Yomi (A.P.) (Sh:Civil Work For Base Of Frp Hut)

Corrigendum Details

Sr No CorrigendumDate Corrignedum CorrigendumType NewSubmissionDate
1 10-Apr-2024 ITBP/SHQLKB/ENGR/24-244 Date 27-04-2024

Key Value

Document Fees
Refer document
EMD
INR 27116.0 /-
Tender Value
INR 13.55 Lakhs /-

BOQ Items

Name of Work: Providing, fixing and installation FRP huts in Menchuka Valley, Dist-Shi-Yomi (A.P.) (SH:Civil work for base of FRP hut)
Sl. No. Item Description
1Y-Junction Base GR 307303 Map sheet no 82H/13 is 06 Km from last road head.
2Excavation work by mechanical means (Hydraulic excavator)/ manual means in foundation trenches or drains (not exceeding 1.5m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soils as directed, within a lead of 50 m.Ordinaryroack
3Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:5:10 (1 cement : 5 coarse sand (zone-III) derived from natural sources : 10 graded stone aggregate 40 mm nominal size derived from natural sources)
4Random rubble masonry with hard stone in foundation and plinth including levelling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate 20 mm nominal size) upto plinth level with : Cement mortar 1:6 (1 cement : 6 coarse sand)
5Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m.
6Reinforced cement concrete work in well-steining, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III): 3 graded stone aggregate 20 mm nominal size)
7Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level. Mild steel and Medium Tensile steel bars
8Centering and shuttering including strutting, propping etc. and removal of form for Foundations, footings, bases of columns, etc. for mass concrete
9Tarnsportationand installation of FRP hut from BHQto site 224 KM by road & 6 Km on foot etc. excliding the cost of FRP hut.Completed as per directions ofEngineer-in- Charge:
Disclaimer :
We takes all possible care for accurate & authentic tender information, however Users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender.
Tell us about your Product / Services,
We will Find Tenders for you

Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy

For Tender Information Services Visit : TenderDetail