Indo Tibetan Border Police Force-ITBP has published Tender For Providing, Fixing And Installation Frp Huts In Menchuka Valley, Dist-Shi-Yomi (A.P.) (Sh:Civil Work For Base Of Frp Hut). Submission Date for this Tender is 27-04-2024. Civil Work Tenders in West Siang Arunachal Pradesh. Bidders can get complete Tender details and download the document.
Sr No | CorrigendumDate | Corrignedum | CorrigendumType | NewSubmissionDate |
1 | 10-Apr-2024 | ITBP/SHQLKB/ENGR/24-244 | Date | 27-04-2024 |
Sl. No. | Item Description |
1 | Y-Junction Base GR 307303 Map sheet no 82H/13 is 06 Km from last road head. |
2 | Excavation work by mechanical means (Hydraulic excavator)/ manual means in foundation trenches or drains (not exceeding 1.5m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soils as directed, within a lead of 50 m.Ordinaryroack |
3 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:5:10 (1 cement : 5 coarse sand (zone-III) derived from natural sources : 10 graded stone aggregate 40 mm nominal size derived from natural sources) |
4 | Random rubble masonry with hard stone in foundation and plinth including levelling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate 20 mm nominal size) upto plinth level with : Cement mortar 1:6 (1 cement : 6 coarse sand) |
5 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m. |
6 | Reinforced cement concrete work in well-steining, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III): 3 graded stone aggregate 20 mm nominal size) |
7 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level. Mild steel and Medium Tensile steel bars |
8 | Centering and shuttering including strutting, propping etc. and removal of form for Foundations, footings, bases of columns, etc. for mass concrete |
9 | Tarnsportationand installation of FRP hut from BHQto site 224 KM by road & 6 Km on foot etc. excliding the cost of FRP hut.Completed as per directions ofEngineer-in- Charge: |