Tender For The Installation Of New 400/100/63/25 Kva Distribution Transformers And Increasing Capacity Of Over Loaded Distribution Transformers From 10 Kva To 25 Kva At Various Places Under Edd-Bisalpur In Business Plan 2024-25., bisalpur-Uttar Pradesh

Madhyanchal Vidut Vitran Nigam Limited has published Tender For The Installation Of New 400/100/63/25 Kva Distribution Transformers And Increasing Capacity Of Over Loaded Distribution Transformers From 10 Kva To 25 Kva At Various Places Under Edd-Bisalpur In Business Plan 2024-25.. Submission Date for this Tender is 06-05-2024. Distribution Transformer Tenders in bisalpur Uttar Pradesh. Bidders can get complete Tender details and download the document.




Tender Notice

43121879
Corrigendum : Tender For The Installation Of New 400/100/63/25 Kva Distribution Transformers And Increasing Capacity Of Over Loaded Distribution Transformers From 10 Kva To 25 Kva At Various Places Under Edd-Bisalpur In Business Plan 2024-25.
Open Tender
Indian
Uttar Pradesh
bisalpur
06-05-2024

Tender Documents

Additional Details Available on Click
✓ Tendering Authority
✓ Publication Document
(Tender Document / Tender Notice )

Tender Details

Tender For The Installation Of New 400 / 100 / 63 / 25 Kva Distribution Transformers And Increasing Capacity Of Over Loaded Distribution Transformers From 10 Kva To 25 Kva At Various Places Under Edd-Bisalpur In Business Plan 2024-25.

Corrigendum Details

Sr No CorrigendumDate Corrignedum CorrigendumType NewSubmissionDate
1 15-Apr-2024 Corrigendom Date 22-04-2024
2 22-Apr-2024 Corrigendum Date 30-04-2024
3 30-Apr-2024 Corrigendom12 Date 06-05-2024

Key Value

Document Fees
INR 1180 /-
EMD
INR 5500.0 /-
Tender Value
INR 5.50 Lakhs /-

Attachment

FileName File Description File Size
55a906c7-f27b-45c5-bde6-8f173ae11e53.html Tender Notice 0 KB
BOQ_1591910.xls Tender Document 0 KB
form.pdf Tender Document 0 KB
Tendernotice_1.pdf Tender Document 0 KB
Tendernotice_2.pdf Tender Document 0 KB

BOQ Items

Name of Work: The installation of new 400/100/63/25 KVA distribution transformers and increasing capacity of over loaded distribution transformers from 10 KVA to 25 KVA at various places under EDD-Bisalpur in Business Plan 2024-25.
Sl. No. Item Description
1Safe carriage of following materials from store centre-Pilibhit to various sites under EDD-Bisalpur including loading & unloading (sites/location detail enclosed as per annexure-10).
211/0.4 KV, 400 KVA T/F.
311/0.4 KV, 100 KVA T/F.
411/0.4 KV, 63 KVA T/F.
511/0.4 KV, 25 KVA T/F.
6STP-11mtr/PCC Pole -8.5 mtr.
7Other Balance estimated centrelized material, TF channel, top channel, Disk Insulator complete, pin insulator, Distribution Box, LT XLPE Cable, Stay set Complete, Earthing rod etc.
8Erection of the double STP/PCC Pole including cutting, making holes, fixing of all types of accessories digging of pits complete in all respect, as per RESSPO drawing. All types of clamps, stone pad, nut, bolt washers would be provided by the contractor.
9Erection of stay set with stay wire, stay clamp & stay insulator including with grouting of stay set by concrete of ratio 1:4:8 as per RESSPO norms before back fitting of the pits including binding, climbing, clamping, tightening and nozzeling of stay wire in all respect as per RESSPO norms. All clamps, nuts, bolts, stay insulator, cement. Brick, ballast, sand etc would be provided by the contractor.
10Concreting of STP/PCCat the time of erection of pole in 1:4:8 concrete ratio from bottom of pole to ground leveland plinthing of supports upto 300mm above ground level by using cement, sand & coarse aggregate in ratio 1:4:8 as per RESSPO drawing with watering/curing properly upto proper setting of plinthing. All matrial would be provided by the contractor.
11Earthing of STP/PCC of the line is to be done by inserting the MS earth rod (1800x20mm) into soil by hammering and properly fastning with GI wire to each support by nut & bolt. Earthing rod must be 0.15 Mtr.above from the plinth of the support. All type nut & bolt would be given by the contractor.
12Construction of plinth for 400 KVA T/F of size 5 fit x5 fit x5 fit with the help of first class bricks, cement & coarse sand as per norms. Filling the structure completely by brick blast & plastering work of walls Including CC work on top in ratio 1:2:4 by cement, stone grit & sand and grouting of 2 nos. M.S. channel of size 50x50x5 mm on the top of T/Fs plinth whole work should be done as per RESSPO norms complete in all respect. (All Material will be provided by Contractor own his cost).
13Mounting of following distribution transformers on newly constructed plinth/Double pole, laying of cable jumpering and making all HT/LT connections complete work in all respect.
1411/0.4 KV, 400 KVA T/F.
1511/0.4 KV, 100 KVA T/F.
1611/0.4 KV, 63 KVA T/F.
1711/0.4 KV, 25 KVA T/F.
18Fabrication and grouting of wire mesh fencing of 28 fit running length in rectangular shape height 2 meter with M.S. angle of size 50x50x06 mm. including gate at one side as per norms complete work and painting of same with 2 coats of red oxide and 2 coats of synthetic enamale paint. (All Material will be provided by Contractor own his cost).
19Earthing of T/Fs by boaring type up to water level by providing GI pipe and making connection from boaring site to body and neutral of T/F. (All Material will be provided by Contractor own his cost).
20Earthing of100 KVA , 63 KVA and 25 KVA Distribution transformers by inserting the MS earthing rod complete earthing work in all respectEarthing rod must be 0.15 Mtr. above from the plinth of the support. All type nut & bolt would be given by the contractor.
21Laying of AB cable for suitable 25 KVA,63 KVA,100 KVA and400 KVA Transformers
22Fixing of LT Distribution Box 3 Phase
23Fabrication and Installation of 11 KV fuse set on midway 11 KV double pole structure with mention material As- MS channel 100x50x2028 mm, Iron strip-50x5x305 mm, fuse wire and holding clamps etc. complete work in all respect all required materials provided by contractor on his own cost.
24Safe carriage of received back 10 KVA T/F from site to Store Centre-Pilibhit after opening and dismantaling all connections and descend of 10KVA T/F from PCC pole including loading, unloading at both ends and proper stacking at safe site under EDD-Bisalpur.
Disclaimer :
We takes all possible care for accurate & authentic tender information, however Users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender.
Tell us about your Product / Services,
We will Find Tenders for you

Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy

For Tender Information Services Visit : TenderDetail