}

Tender For Temporary Water Supply Scheme At.Jakekur (Jakpaur Storage Tank) , Ta.Omerga, Dist.Dhrashiv Under Scarcity, Osmanabad-Maharashtra

Rural Development Department has published Tender For Temporary Water Supply Scheme At.Jakekur (Jakpaur Storage Tank) , Ta.Omerga, Dist.Dhrashiv Under Scarcity. Submission Date for this Tender is 08-04-2024. Water Supply Project Tenders in Osmanabad Maharashtra. Bidders can get complete Tender details and download the document.




Tender Notice

43086564
Tender For Temporary Water Supply Scheme At.Jakekur (Jakpaur Storage Tank) , Ta.Omerga, Dist.Dhrashiv Under Scarcity
Open Tender
Indian
Maharashtra
Osmanabad
08-04-2024

Tender Details

Tender For Temporary Water Supply Scheme At.Jakekur (Jakpaur Storage Tank) , Ta.Omerga, Dist.Dhrashiv Under Scarcity

Key Value

Document Fees
INR 1000 /-
EMD
INR 14195.0 /-
Tender Value
INR 14.19 Lakhs /-

BOQ Items

Name of Work:- Temporary Water Supply SchemeAt.Jakekur (Jakpaur Storage Tank), Ta.Omerga, Dist.Dhrashiv Under Scarcity
Sl. No. Item Description
1SUB WORK-WATER COLLECTION PIT IN SUBMERGENCE OF DAM
2Item No 1. :- Excavation in general in soft material comprising of soft soil, soft murum, sand, hard murum with boulders in wet or dry condition for Head Works i.e. Intake Well, Connecting Pipe, Jack Well, Pump House, Supply Well, etc. for lift 0 to 1.5M and lead of 150 M including barricading, guarding, disposing off surplus excavated stuff within a radius of 0.5 km. as directed by Engineer-in-charge, etc. complete excluding refilling. For Head Works on river or dam submergence
3Lfit 0.00 to 1.50 M
4Lfit 1.50 to3.00 M
5Lfit 3.00 to4.50 M
6Lfit 4.50 to6.00 M
7Item No 2. :- Excavation in general in hard material comprising of soft rock, hard rock, Manjara rock, etc. by blasting / controlled blasting, chiselling as required in wet or dry condition for Head Works i.e. Intake Well, Connecting Pipe, Jack Well, Pump House, Supply Well, etc. for lift 0 to 1.5 M and lead of 150 M including barricading, guarding, disposing off surplus excavated stuff within a radius of 0.5 km. as directed by Engineer-in-charge, excluding refilling. For Head Works on river or dam submergence
8Lfit 4.50 to6.00 M
9Item No 3. :- Dewatering the excavated trenches and pools of water in the building trenches / pipeline trenches, well works by using pumps and other devices including disposing off water to safe distance as directed by Engineer-in-charge (including cost of machinery, labour, fuel), etc. complete. (Bd-A-9/261)
10Item No 4. :- Excavation for foundation/pipe trenches in earth, soils of all types, sand gravel and soft murum, íncluding removing the excavated material upto distance of 50 meter and lift as below, stacking and spreading as directed, manual dewatering , preparing the bed for foundation and excluding backfilling etc. complete. Lift 0 to 1.5 M
11SUB WORK-PUMPING MACHINERY
12Item No 1. :- Providing, erecting and giving tests of Submersible monoblock Pump set (with Bronze / Stainless steel(CF8M) Impeller) Horizontal / Vertical -up to 3 stages (Motor with water lubricated bearing to accept entire hydraulic thrust). 5 HP
13Item No 2. :- Providing and supplying in standard lengths Polyethelene Pipes, confirming to IS 4984 / 14151 / 12786 / 13488 with nesessary jointing material like mechanical connector i. e. thread / insert joint / quick release coupler joint / compression fitting joint or flanged joint excluding coupler/specials, including transportation and freight charges, inspection charges, loading / unloading charges, conveyance to the departmental stores & stacking the same in closed shade duly protecting from sunrays & rains, excluding GST levied by GI & GOM in all respect etc. complete. Note:- H.D.P.E. Pipes shall be as per latest IS Specifications Also HDPE pipes upto 110 mm Dia shall be in coil form. PE-100, 6 Kg/Sq.cm: 90 mm
14Item No 3. :- Supplying & erecting automatic control panel for 3 Ph, 415 volt, A.C. Submersible/centrifugal pump set up to 7.5 HP - 10 H.P. consisting of DOL starter having relay range 28-42 AMP,S.P.P., Combined ammeter/voltmeter, phase indicating lamp enclosed in CRCA powder coated Vibration proof enclosure with IP 54 protection. Control Panel should offer single phasing, phase reversal, phase imbalance etc.
15Item No 4. :- Supplying & erecting flat flexible 3 core 4 sq.mm PVC sheathed submersible type copper cable suitably clamped at fixed intervals with column pipe assembly complete.
16SUB WORK-RISING MAIN
17Item No 1. :- Excavation for foundation/pipe trenches in earth, soils of all types, sand gravel and soft murum, íncluding removing the excavated material upto distance of 50 meter and lift as below, stacking and spreading as directed, manual dewatering , preparing the bed for foundation and excluding backfilling etc. complete.Lift 0 to 1.5 M
18Item No 2. :- Providing and supplying in standard lengths Polyethelene Pipes, confirming to IS 4984 / 14151 / 12786 / 13488 with nesessary jointing material like mechanical connector i. e. thread / insert joint / quick release coupler joint / compression fitting joint or flanged joint excluding coupler/specials, including transportation and freight charges, inspection charges, loading / unloading charges, conveyance to the departmental stores & stacking the same in closed shade duly protecting from sunrays & rains, excluding GST levied by GI & GOM in all respect etc. complete. Note:- H.D.P.E. Pipes shall be as per latest IS Specifications Also HDPE pipes upto 110 mm Dia shall be in coil form.PE-100, 6 Kg/Sq.cm: 90 mm
19Item No 3. :- Providing and supplying necessary Specials , sundries items
20Item No 4. :- Providing and supplying ISI mark CI D/F reflux valves (non-return valves ) of following dia including railway freight, inspection charges, unloading from railway wagon, loading into truck, transportation upto departmental stores, unloading, stacking excluding GST levied by GOI & GOM in all respect etc. complete.Reflux valves as per I.S.5312 Part I (1984) a) Reflux valves - PN -1 Without byepassarrangement 80 mm
21Item No 5. :- Lowering, Laying and Jointing H. D. P. E./M. D. P. E. pipes in proper position including all specials by compression fitting/electrofusion and butt fusion jointing procedure as per relevent IS Code complete with all materials for jointing procedure like Electrofusion machine, Electric heater/butt fusion welding machine with hydraulic jack, top loading clamp etc. and all labours as directed by engineer in charge as per IS-7634 Part II. 90 mm
22Item No 6. :- Lowering, laying and jointing in position following C.I.D/F Reflex valves, Butterfly valves and Sluice valves including cost of all labour jointing material, including nut bolts and giving satisfactory hydraulic testing etc. complete.80 mm
23Item No 8. :- Refilling the trenches with available excavated stuff with soft material first over pipeline and then hard material in 15 cm layers with all leads and lifts including consolidation, surcharging, etc. complete.
24Item No 9. :- Providing and Supplying Fusion Welding PPR Fitting as per IS 15801 approved by CBRI and Comatible to PPR C Pipes (Poly Propylene Random CoPolymor) Rates including transportation, Internal testing, loading, unloading, excluding GST Levied by GOI and GOM in all aspec.Flanged Ended Ball Valve 90 mm
25Item No 10. :- Dismantling dead pipeline of M.S./ R.C.C./ C.I./ P.S.C. and G.I./ A.C./ P.V.C./ S.W./ H.D.P.E. pipe including cost of necessary excavation and refilling of trenches, breaking the joints, lifting the pipes and stacking to the place as directed by Engineer-in-charge with all leads and lifts including cleaning the surface, etc. complete. For G.I. / A.C. / P.V.C. / S.W. / H.D.P.E. 80 mm
26SUB WORK-TRIAL RUN , CHEMICAL , ELECTRIC POWER SUPPLY , ELECTRIC CHARGES.
27Item No 1. :-Commissioning, running and maintaining the scheme to quantities, rated capacity, including managing necessary personnel such as operator, valveman, etc. as per requirements of the scheme and who should also administer chemical dose for a period of 1 month for individual scheme and 3 months for regional scheme, together with training of personnel spared by MJP / Local Body and handing over the scheme to Local Body after completion of the above period as directed by Engineer-in-charge. Note : Required chemicals to be supplied by Department free of cost and electricity bill will also be paid by the Department. a) For single village without WTP
28Item No 2. :- Chemical and Materials
29Item No 3. :- Electricity Charges
30Item No 4. :- Provision for power supply at head works site for pumping machinery & lighting etc. including cost of poles condutctor etc. complete including charges of MSEB Quotation for pumping machinery etc.
31SUB WORK-GST Charges
32Item No 1. :-Provision for GST Charges
Disclaimer :
We takes all possible care for accurate & authentic tender information, however Users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender.
Tell us about your Product / Services,
We will Find Tenders for you

Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy

For Tender Information Services Visit : TenderDetail