Uttar Pradesh Housing And Development Board-UPAVP has published Tender For Construction Work Of Internal Drains And Culverts In Sector 15 At Majhola Yojna No 4 Phase 2 Vistar Moradabad. Submission Date for this Tender is 08-04-2024. Drainage Tenders in Moradabad Uttar Pradesh. Bidders can get complete Tender details and download the document.
Sl. No. | Item Description |
1 | Excavation in foundation in ordinary soil (Loam, clay or sand) including lift upto 1.50 metre and lead upto 50 m and including filling, watering and ramming of excavated earth into the trenches or into the space between the building and the sides of foundation trenches . |
2 | Base Cement Concrete in foundation in proportion 12:6:1 with 40 mm gauge stone ballast, coarse sand (2.20 to 3.60 F. M.) and cement including supply of all materials, labour and T & P etc. required for proper completion of work. |
3 | Base Cement Concrete in foundation in proportion 8:4:1 with 40 mm gauge stone ballast, coarse sand (2.20 to 3.60 F. M.) and cement including supply of all materials, labour and T & P etc. required for proper completion of work. |
4 | M-150 class brick work in 1:6 cement coarse sand of 1.50 - 2.00 F.M mortar in foundation/plinth in including supply of all materials, labour and T&P etc. required for the proper completion of the work as per direction of E/I. |
5 | Flush pointing with cement mortar consisting of 1 part cement and 2 parts of the fine sand of 1.25 fineness modulus on brick work including supply of all material, labour and T & P etc required for proper completion of the work . |
6 | Struck pointing with cement mortor consisting of 1 part cement and 2 parts of F. sand of 1.25 Fineness modules on brick work including supply of all materials, labour and T&P etc. required for the proper completion of the work. |
7 | P.C.C. work with cement approved coarse sand of 2.20 -3.60 F.M and 20 mm graded stone gritin proportion of 1:2:4 including supply of all materials, labour, T&P etc.required for proper completion of the work. |
8 | R.C.C. in slab 1 : 1.5 : 3 with cement mortar consisting of 1 part cement and 1.50 parts of C. sand of 2.20 to 3.60 fineness modules including supply of all material, labour and T&P etc. required for proper completion of the work. |
9 | Mild steel or TMT Bars ( Fe-500D or Higher) in plane work such as rein forced cement concrete or rein force brick work (when not included in an over all rates ) wrought to required shape as necessary including banding for proper completion of the work and including supply of all steel. |