Uttar Pradesh Projects Corporation Limited has published Tender For Balance Work Of Construction Of 60 Seated Male Hostel Building At Govt. Polytechnic Debai Distt.- Bulandshahar. Submission Date for this Tender is 27-03-2024. Civil Work Tenders in debai Uttar Pradesh. Bidders can get complete Tender details and download the document.
Sl. No. | Item Description |
1 | Making Plinth protection/Apron |
2 | Making drain alongthe apron with analysis. |
3 | S/F of factory wired street light luminiare single peace cast aluminium body, flat glass with IP-65 protection suaitable for 150 watt MH lamp including integral control gear,150 watt MH lamp on pole |
4 | Interlocking tiles |
5 | Earth filling in under apron & interlocking tiles |
6 | Excavating trenches in all kind of soil of required width for pipes, cables etc. including excavation for sockets and dressing of sides, ramming of bottoms, depth upto 1.5 m. including getting out the excavated soil & then returning the soil as required in layers not exceeding 20 cm in depth including consolidating each deposited layer by ramming, watering, etc & disposing of surplus excavated soil as directed with in a lead of 50 cm. a) Pipes 80mm to 300mm diameter. |
7 | Providing, laying and jointing PVC pipes including testing of joints etc. complete b) 160mm diameter |
8 | Providing & laying cement concrete 1:5:10 (1 cement : 5 coarse sand :10 graded stone aggregate 40mm nominal size) alround PVC pipes including bed concrete as per standard design. b)150mm diameter PVC Pipe. |
9 | Constructing brick massonary manhole a)Inside size 90x80 cm and 45 cm deep including C.I.cover with frame (light duty) 455x610 mm internal dimensions, total weight of cover and frame to be not less than 38 kg (weight of cover 23 kg and weight of frame 15 kg) :Inside size 90x80 cm and 45 cm deep including C.I.cover with frame (light duty) 455x610 mm internaldimensions, total weight of cover and frame to be not less than 38 kg (weight of cover 23 kg and weight of frame 15 kg) :Inside size 90x80 cm and 45 cm deep including C.I.cover with frame (light duty) 455x610 mm internal dimensions, total weight of cover and frame to be not less than 38 kg (weight of cover 23 kg and weight of frame 15 kg) : |
10 | Earth work in excavation in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan) including dressing of sides of ramming of bottoms, lift upto 1.5 m incuding getting out the excavated soil and disposal of surplus excavated soil as directed, with in a lead of 50 m. |
11 | Same as above |
12 | Brick work 1:4 Cment : coarse sand 3.00 dia 230 mm thickX 3.00 mtr Depth |
13 | R.C.C. Work in slab |
14 | M.S. Work in R.C.C. |
15 | S/Fixing of Man hole Cover |
16 | Drilling of 100 mm dia bore hole with M.S. casing pipe. |
17 | Supply,assembling,lowering and fixing in vertical position in bore well,PVC 100 mm Casing pipe Complete |
18 | Supply,assembling,lowering and fixing in vertical position in bore well,PVC Sloted Casing pipe 100 mm Complete |
19 | Filling of Gravel (5-10 mm size ). |
20 | Filling of Gravel (3-6 mm size ). |
Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy