Bridge And Roof Company I Limited has published Tender For Design, Engineering, Manufacturing, Procurement & Supply, Installation, Testing & Commissioning Of Cumulative 2.30Mwp Roof Mounted Grid Connected Solar Photo Voltaic Power Plant Including 10 Years Comprehensive Maintenance Contract (Cmc) Post 1. Submission Date for this Tender is 17-04-2024. Civil Work Tenders in kolkata West Bengal. Bidders can get complete Tender details and download the document.
Sr No | CorrigendumDate | Corrignedum | CorrigendumType | NewSubmissionDate |
1 | 02-Apr-2024 | DRAWING | Other | 17-04-2024 |
2 | 02-Apr-2024 | CORRIGENDUM-1 | Date | 17-04-2024 |
3 | 13-Apr-2024 | CORRIGENDUM-II | Technical Bid | 17-04-2024 |
Sl. No. | Item Description |
1 | SMPK SOLAR |
2 | Supply of all materials for the job of 2.3 MWp Solar Power Plant :Design, engineering, manufacture, supply & delivery of all the equipments and materials including transit insurance to the site for 2.3 MWp Solar Power Plant consisting of SPV modules, Module mounting Structure (Ballast type) along with cement blocks, SCBs / AJBs, PCUs / Inverters, DCDB / ACDB, Transformers, VCBs/ACBs/MCCBs, CTs, PTs, Isolator(s), fuse unit(s) with protection system complete including control & relay panel, DC system with battery charger & battery bank, Central Monitoring & Control System comprising of SCADA & Plant Monitoring Desk, Solar Weather station, power & control cables with hardware, metering system, Lighting & Lightening protection system, earthing system, security system, Fire fighting i.e Fire extinguisher With sand bucket ( 4 Kg ABC type ), First-AID box, Rubber Hand Glove, Fire Bucket stand, Danger Board, Safety material & other safety systems etc, water supply system, auxiliaries as required for the completion of the entire Solar Power Project on turnkey basis as per technical specification enclosed along with tender document and tentative BOM as per DPR enclosed. The final Design along with BOM shall be submitted by the bidder to B And R/ SMPK for final approval. |
3 | Installation of all materials for the job of 2.3 MWp Solar Power Plant : Installation, Testing & Commissioning of2.3 MWp Solar Power Plant consisting of SPV modules, Module mounting Structure (Ballast type) along with cement blocks, SCBs / AJBs, PCUs / Inverters, DCDB / ACDB, Transformers, VCBs/ACBs/MCCBs, CTs, PTs, Isolator(s), fuse unit(s) with protection system complete including control & relay panel, DC system with battery charger & battery bank, Central Monitoring & Control System comprising of SCADA & Plant Monitoring Desk, Solar Weather station, power & control cables with hardware, metering system, Lighting & Lightening protection system, earthing system, security system, Fire fighting i.e Fire extinguisher With sand bucket ( 4 Kg ABC type ), First-AID box, Rubber Hand Glove, Fire Bucket stand, Danger Board, Safety material & other safety systems etc, water supply system, auxiliaries as required for the completion of the entire Solar Power Project on turnkey basis as per approved technical specificationand BOM.The final Design along with BOM shall be submitted by the bidder to B And R/ SMPK for final approval. |
4 | Civil Work: Carrying out all civil works for Control room(s), sub-station(s), fencing, Construction of foundations for module mounting Structures,Inverters / PCUs, Transformers, ACDB, DCDB, HT & LT switchgears & switchgear panels, relay & control panels, cable trenches, indoor lights, switchyard light etc. and all other allied equipment foundations as required; erection, testing, commissioning of all the supplied equipments storage & other auxiliaries for carrying out works at site till commissioning and hand over to owner, and all other enablingcivilworks enabling 2.3 MWp solar power project work complete in all respects as per the scope of work on turnkey basis as perCivil technical specification enclosed along with tender document and tentative BOM as per DPR enclosed. The final Design along with BOM shall be submitted by the bidder to B And R/ SMPK for final approval. The tentative Layout and Drawings are enclosed along withTender Document. The work shall be carried out as per relevant IS standardandCPWD standards |
5 | 10 YearsComprehensive Operation and Maintenance (O & M) of the 2.3 MWp solar power plant after 1 year defect liability period from date of commissioning for 10(Ten ) years including arrangement & replacement of spares, consumables, tools, tackles, testing equipments & instruments, manpower, charges payable to all government agencies, liaison with all government agencies, insurances, all administrative work, maintaining records and submission of reports to all concerned authorities as per foregoing specification on turnkey basis. |
6 | The individual items shall at least meet the technical requirements mentioned in the “Technical Specifications". |
7 | "NOTE:- THE ABOVE RATE SHALL BE INCLUSIVE OF ALL TAXES & DUTIES, ROYALTIES, CESS, FEE, ENVIORMENTAL & POLLUTION, FITNESS & SAFETY CLEARANCE CHARGES (IF ANY), OR ANY OTHER INCIDENTAL CHARGES ETC BUT EXCLUDING GST." |