Bharat Sanchar Nigam Limited-BSNL has published Tender For Repairing Of Badly Tilted Boundry Wall Of Max-I T.E. Compound Keerat Nagar Lakhimpur.. Submission Date for this Tender is 13-03-2024. Lifting Equipment Tenders in lakhimpur Uttar Pradesh. Bidders can get complete Tender details and download the document.




Tender Notice

42734804
Tender For Repairing Of Badly Tilted Boundry Wall Of Max-I T.E. Compound Keerat Nagar Lakhimpur.
Open Tender
Indian
Uttar Pradesh
lakhimpur
13-03-2024

Tender Details

Tender For Repairing Of Badly Tilted Boundry Wall Of Max-I T.E. Compound Keerat Nagar Lakhimpur.

Key Value

Document Fees
INR 590 /-
EMD
INR 4048.0 /-
Tender Value
INR 2.02 Lakhs /-

BOQ Items

Name of Work: Repairing of badly tilted boundry wall of MAX-I T.E. compound Keerat Nagar Lakhimpur.
Sl. No. Item Description
1Sub-Head : Earth Work
2Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan) including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.
3All kinds of soil.
4Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m.
5Sub-Head : Concrete Work
6Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :
71:5:10 (1 cement : 5 fine sand derived from natural sources : 10 graded stone aggregate 40 mm nominal size derived from natural sources)
8Providing and laying cement concrete in retaining walls, return walls, walls (any thickness) including attached pilasters, columns, piers, abutments, pillars, posts, struts, buttresses, string or lacing courses, parapets, coping, bed blocks, anchor blocks, plain window sills, fillets, sunken floor, etc., up to floor five level, excluding the cost of centering, shuttering and finishing :
91:2:4 (1 Cement : 2 coarse sand (zone-III) derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources)
10Centering and shuttering including strutting, propping etc. and removal of form work for :
11Foundations, footings, bases for columns.
12Sub-Head :Reinforced Cement Concrete
13Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level :
141:1.5:3 (1 cement : 1.5 coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)
15Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement :
161:1.5:3 (1 cement : 1.5 coarse sand(zone-III)derived from natural sources : 3 graded stone aggregate 20 mm nominal sizederived from natural sources)
17Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III)derived from natural sources : 3 graded stone aggregate 20 mm nominal sizederived from natural sources).
18Centering and shuttering including strutting, propping etc. and removal of form for :
19Foundations, footings, bases of columns, etc. for mass concrete
20Lintels, beams, plinth beams, girders, bressumers and cantilevers
21Columns, Pillars, Piers, Abutments, Posts and Struts
22Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level.
23Cold twisted bars
24Sub-Head : Brick Work
25Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in foundation and plinth in:
26Cement mortar 1:6 (1 cement : 6 coarse sand)
27Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in superstructure above plinth level up to floor V level in all shapes and sizes in :
28Cement mortar 1:6 (1 cement : 6 coarse sand)
29Sub-Head : Steel Work
30Structural steel work in single section, fixed with or without connecting plate, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete.
31Sub-Head : Finishing
3212 mm cement plaster of mix :
331:6 (1 cement: 6 fine sand)
3415 mm cement plaster on the rough side of single or half brick wall of mix :
351:6 (1 cement: 6 fine sand)
366 mm cement plaster of mix :
371:3 (1 cement: 3 fine sand)
38Finishing walls with water proofing cement paint of required shade :
39New work (Two or more coats applied @ 3.84 kg/10 sqm).
40Sub-Head : Dismantling and Demolishing
41Demolishing brick work manually/ by mechanical means including stacking of serviceable material.
42In cement mortar
43Removing mortar from bricks and cleaning bricks including stacking within a lead of 50 m (stacks of cleaned bricks shall be measured):
44From brick work in cement mortar
45Sub-Head : Road Work
46Fencing with angle iron post placed at required distance embedded in cement concrete blocks, every 15th post, last but one end post and corner post shall be strutted on both sides and end post on one side only and provided with horizontal lines and two diagonals interwoven with horizontal wires, of barbed wire weighing 9.38 kg per 100 m (minimum), between the two posts fitted and fixed with G.I. staples, turn buckles etc. complete. (Cost of posts, struts, earth work and concrete work to be paid for separately) :-Payment to be made per metre cost of total length of barbed wire used.
47With G.I. barbed wire
48Market Rate Items
49Deduct for issuing bricks.
50Credit of bricks bats.
51Removing of JANGALI tree roots along with boundry wall including excavation of earth, cutting and stacking of tree roots and refilling of earth complete as per direction of Engineer in Charge.
Disclaimer :
We takes all possible care for accurate & authentic tender information, however Users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender.
Tell us about your Product / Services,
We will Find Tenders for you

Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy

For Tender Information Services Visit : TenderDetail