Tripura State Electricity Corporation Limited-TSECL has published Extension Of Ht Line Including Construction Of 10X25kva Sub- Station For Providing External New Service Connection To Bsnl 4G Tower At Different Locations Of Padmabil & Tulashikhar Sub-District Under Electrical Division- Khowai. Submission Date for this Tender is 07-03-2024. Overhead Line Tenders in khowai Tripura. Bidders can get complete Tender details and download the document.
Sl. No. | Item Description |
1 | Supply |
2 | 9 Mtr long PCC Pole |
3 | Stay Set complete |
4 | Stay Insulator (HT) |
5 | Stay Wire (7/2.5 mm) |
6 | Stay Clamp |
7 | ACSR Weasel Conductor (6/1/2.59mm) |
8 | G.I. Wire (8 SWG) |
9 | 11KV Disc Insulator (Polymeric) |
10 | 11KV Disc Fittings |
11 | 11KV Pin Insulator (Polymeric) |
12 | M.S. Channel (100x50x50x6mm) |
13 | M.S. Channel (75x40x40x6mm) |
14 | M. S. Angle (65x65x6mm) |
15 | Nut & Bolts with washer (Assorted Size) |
16 | 11KV G.O.S 3-Phase (Polymeric) |
17 | 11KV D.O.F 3-Phase (Polymeric) |
18 | 11KV L.A (9KV, 5KA) (Polymeric) |
19 | 25KVA Transformer |
20 | 70 sqmm PVC Cable |
21 | 16 sqmm PVC Cable |
22 | Reel Insulator |
23 | Al. Lugs (70 sqmm-10) |
24 | Cut-out 100 Amp |
25 | 40mm dia G.I. Pipe, 2.5 mtr long |
26 | 60Kg Salt & 55Kg Charcoal (For 1 Pit) |
27 | Bracket clamp (50x6mm flat) |
28 | PVC sleeves |
29 | Wooden Plunk |
30 | Erection |
31 | Erection of 9.0 mtrs length of PCC pole at any kind of soil upto a depth of 1/6 th of pole height, including excavation of earth, refilling the pit with soil upto the ground level, remming and making complete in all respect i/c Hand-Cart carriage & Mannual carriage with necessary loading & unloading. |
32 | Erection of Stay set direct in earth complete with 19mm x 1800 mm long stay rod, anchor plate of size 300 x 300 x 8 mm, thimble, turn buckle, 7/3.15 mm dia G.I Standed stay wire and stain insulator etc. with supply if M.s clamp, nuts & Bolts etc. as required. and making complete in all respect. |
33 | Erection of MS Channel Cross Arm 0.6 to 2.8 mtr long 100x50x50x6mm (Excluding the cost of Bkt clamp, N&B) |
34 | Erection of MS Channel Cross Arm 1.3 to 2.8 mtr long 75x40x40x6mm (Excluding the cost of Bkt clamp, N&B) |
35 | Erection of MS Channel Cross Arm 0.3 to 1.2 mtr long 75x40x40x6mm (Excluding the cost of Bkt clamp, N&B) |
36 | Erection of MS Channel Cross Arm 1.0 to 2.5 mtr long 65x65x6mm (Excluding the cost of Bkt clamp, N&B) |
37 | Erection of 11KV polymer pin insulator |
38 | Erection of 11KV disc insulator set with necessary fittings. |
39 | Laying & stringing of 1KM (Single Conductor) ACSR 6/1/2.59 mm dia "WEASEL" including hoisting & binding etc. Complete as required. |
40 | Laying & stringing of 1KM (Single Conductor) 8SWG GI wire including hoisting & binding etc. Complete as required. |
41 | Erection of 11KV 200Amps GOS unit set of three nos including necessary connection complete as per technical specification. |
42 | Erection of 11KV 200Amps DOF unit set of three nos including necessary connection complete as per technical specification. |
43 | Erection of 9KV, 5KA single pole metal oxide gapless type LA including necessary connection complete as per technical specification. |
44 | Installing/Positioning of 11/.0430KV, 3-Phase 25KVA Distribution Transformer on pole with nessary connections & fitting fixing of all allied accessories components as required for making complete in all respect for energizing. |
45 | Earthing with G.I pipe 2.5mtr long and 40mm dia including excavation, refilling with alternate layer of Salt & Charcoal as per drawing |
46 | Providing of three phase service connection laying of PVC cable from nearby electrical Pole to the premises up to 35 Meter in length supported by GI-wire, Reel insulator i/c fitting, fixing of Energy Meter (Department supply which shall be collected from respective Electrical Sub- Division) as required |
47 | Fabrication of cross arms by MS Channel/MS Angle as per specification |
48 | Erection of 11 KV protective Guarding by GI Wire 8 SWG as per technical specification, across road/River/Telecom line etc. in horizonta formation complete. |
49 | Maintaning adequate clearance from overhead live conductors by Trimming of thee branches for Way Leaves. |
50 | Fitting, fixing of LT Cut-out (Set of 3 nos) on wooden plank (Preferably Korai wood) of size 24x10x1.5 inch and cable connections with termination by lugs/thimbles complete (i/c supply of wooden plank, screwes & M.S. clamp excluding cost of thimble) |
Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy