Military Engineer Services-MES has published Tender For Repairs To Ro Plant, Stp,Ofi, Mechanical Laundry, Oxygen Manifold System And Allied Works And Repair Maintenance And Overhauling Of Dg Sets ,Amf Panel At Signal Centre And Mdc Under Ge(U),Secunderabad. Submission Date for this Tender is 16-03-2024. Air Fittings and Connectors Tenders in secunderabad Telangana. Bidders can get complete Tender details and download the document.
Sl. No. | Item Description |
1 | M&L for spray painting of 100kg capacity Washing machines at laundry plant MH (incluing inner and outer surface areas and motors also, except stainless steel part/electric panels/belts etc) by apply two coats of metal primer and painting withtwo coats synthetic enamel paint of existing colour after removing all dust & rust and paint by scrapping with scrapping material shall confirm to IS 2032 including marking of SM/MES Number for each washing machine with stencil letter with black or white paint and Font and Size of letter and white washing for PCC based plinth shall be directed by Engr-in-Charge. |
2 | All as per item no.1 but for 50kg washing machines |
3 | M&L for spray painting of drying tubler at laundry plant MH (incluing inner and outer surface areas,motors and econimizer also, except stainless steel part/electric panels/belts etc) by apply two coats of metal primer and painting withtwo coats synthetic enamel paint of existing colour after removing all dust & rust and paint by scrapping with scrapping material shall confirm to IS 2032 including marking of SM/MES Number for each equipment with stencil letter with black or white paint and Font and Size of letter and white washing for PCC based plinth shall be directed by Engr-in-Charge. |
4 | M&L for spray painting of Steam Boilers and chimney at laundry plant MH (incluing inner and outer surface areas,motors,disel tank and econimizer also, except stainless steel part/electric panels/belts etc) by apply two coats of metal primer and painting withtwo coats synthetic enamel paint of existing colour after removing all dust & rust and paint shall confirm to IS 2032 including marking of SM/MES Number for each equipment with stencil letter with black or white paint and Font and Size of letter and white washing for PCC based plinth shall be directed by Engr-in-Charge. |
5 | M&L for spray painting of 50kg capacity hydro extractors at laundry plant MH (incluing inner and outer surface areas and motors also, except stainless steel part/electric panels/belts etc) by apply two coats of metal primer and painting withtwo coats synthetic enamel paint of existing colour after removing all dust & rust and paint shall confirm to IS 2032 including marking of SM/MES Number for each equipment with stencil letter with black or white paint and Font and Size of letter and white washing for PCC based plinth shall be directed by Engr-in-Charge. |
6 | All as per item no.5 but for 25 Kg Hydro extractor |
7 | M&L for spray painting of calander machine at laundry plant MH (incluing inner and outer surface areas and motors also, except stainless steel part/electric panels/belts etc) by apply two coats of metal primer and painting withtwo coats synthetic enamel paint of existing colourafter removing all dust & rust and paint shall confirm to IS 2032 including marking of SM/MES Number for each equipment with stencil letter with black or white paint and Font and Size of letter and white washing for PCC based plinth shall be directed by Engr-in-Charge. |
8 | M&L for spray painting of Air compressor unit at laundry plant MH (incluing inner and outer surface areas and motors also, except stainless steel part/electric panels/belts etc) by apply two coats of metal primer and painting withtwo coats synthetic enamel paint of existing colour after removing all dust & rust and paint shall confirm to IS 2032 including marking of SM/MES Number for each equipment with stencil letter with black or white paint and Font and Size of letter and white washing for PCC based plinth shall be directed by Engr-in-Charge. |
9 | M&L forpainting of MS/GI pipe line of different sizes byapplying two coat of synthetic enameledblack colour paint after removing all dust & rust and paint shall confirm to IS 2032shall be directed by Engr-in-Charge. |
10 | Supply & Fixing following spare parts suitable to Drying Tumbler of capacity 50Kg including taking down old unserviceable spare parts complete all as specified and directed for Make of dry tumbler: Supershine |
11 | Digital Tempreature meter |
12 | Timer |
13 | Auxillary contacts |
14 | Contactor relay M L 1, 3 phase 415 volts |
15 | Contactor relay M L 2, 3 phase 415 volts |
16 | Auxilary relay |
17 | Revenger (Reverse Forward) |
18 | Main Motor -V-belt |
19 | Motor bearings |
20 | Blower bearings |
21 | Reduction gear bearings |
22 | Main bearing |
23 | Solenoid valve |
24 | Push button |
25 | Steam strap 15mm |
26 | Door Locks |
27 | Door Beading |
28 | Exhaust Fan/Blower |
29 | 1/2" Steam Valve |
30 | 3/4" Steam Valve |
31 | Reduction gear V-belt |
32 | Brake actuator |
33 | Supply & Fixing following spare parts suitable to Hydro Extractor of capacity 25Kg including taking down old unserviceable spare parts complete all as specified and directed for Make of Hydro extractor :Supershine |
34 | Contactor M L 1, 3 phase, 415 volts |
35 | Timer relay |
36 | Transformer |
37 | Timer |
38 | Buffer |
39 | Limit switch |
40 | Main motor bearings |
41 | Push button |
42 | Motor to body springs |
43 | Rubber bush for Hydro Extractor |
44 | Hydro Extractor motor bearings |
45 | Bridge rectifier |
46 | Diode |
47 | Body Spring support Bolts |
48 | Bush |
49 | Supply & Fixing following spares suitable toWashing machine 50Kg,includingtaking down old unserviceable spare parts complete all as specified and directed forMake of wahing machine: Supershine |
50 | Digital Tempreature meter |
51 | Timer |
52 | Contactor relay M L 1, 3 phase, 415 volts |
53 | Contactor relay M L 2, 3 phase, 415 volts |
54 | Relay M L 1, 3 phase, 415 volts |
55 | Relay M L 2, 3 phase, 415 volts |
56 | Revenger (Reverse Forward) |
57 | Water Level Indicator |
58 | Steam solenoid Valve |
59 | Drain valve actuator |
60 | Main motor V-belt |
61 | Aux Motor V-belt |
62 | Washing Machine main bearing |
63 | Reduction gear bearing |
64 | Water inlet solenoid valve suitable for 50 kg washing machine |
65 | Water outlet solenoid valve suitable for 50 kg washing machine |
66 | Gland rope |
67 | Main motor bearings |
68 | Aux Motor bearings |
69 | Toggle swtich |
70 | Supply & Fixing following spare parts suitable to Boiler of capacity 600Kg/Hr including taking down old unserviceable spare parts complete all as specified and directed forMake of boiler: Thermax |
71 | Gland Washer (HTN-8) |
72 | Valve seat Assembly |
73 | Metalic Hose 3/8" x 40" |
74 | Oil Seal (HTN-5) |
75 | Oil Seal (HCA-7) |
76 | Ball Bearings (HCA-5) |
77 | Pressure Switch PVF 1.0 |
78 | Pressure Switch PVF 16 |
79 | Metallic Hose 1" x 1.2m |
80 | Limit Switch |
81 | Photocell 8205 |
82 | Sequence controller MA 810 |
83 | Solinoid Coil |
84 | Electrode Assembly |
85 | Electrode Cap |
86 | High Tension Wire |
87 | Packing Hylam |
88 | Packing Asbestos |
89 | Gland Nut (HTN-6) |
90 | Oil Level Indicator |
91 | Sight glass 50mm |
92 | Ignition Transformer 14.5 KV |
93 | Temperature Controller 0-400V |
94 | RTD Assembly 2.5 mtrs |
95 | Safety valve 25mm |
96 | Plug & Socket |
97 | Hooter 4" Dia |
98 | Lip Seal |
99 | Spider for love joy couple |
100 | Burner rod Without nozzle |
101 | Fuel Pump |
102 | Diffuser Plate 132mm dia |
103 | Nozzle 6.5 GPH, 45 Degree |
104 | Disel line Y strainer 25mm dia |
105 | Disel line globe Valve 25mm dia |
106 | Steam line Y strainer 25mm Dia |
107 | Steam line Globe valve 25mm Dia |
108 | Steam line Y strainer 40mm Dia |
109 | Supply & Fixing following spares suitable to Washing machine 100Kg including taking down old unserviceable spare parts complete all as specified and directed for Make of washing machines: Supershine &Megha laundry |
110 | Digital tempreature meter |
111 | Timer |
112 | Contactors ML 1, 3 Phase, 415 Volts |
113 | Contactors ML 2, 3 Phase, 415 Volts |
114 | Contactor relay M L 1, 3 phase, 415 volts |
115 | Revenger (Reverse Forward) |
116 | Water Level Indicator |
117 | Steam solenoid valve |
118 | Drain valve actuator |
119 | Main motor V-belt |
120 | Aux motor V-belt |
121 | Washing Machine main bearing |
122 | Reduction gear bearing |
123 | Indicator |
124 | Water inlet solenoid valve suitable for 100 kg washing machine |
125 | Water outlet solenoid valve suitable for 100 kg washing machine |
126 | Gland rope |
127 | Door Lock Knobs |
128 | Steam Valve (Globe) |
129 | Main motor bearings |
130 | Aux motor bearings |
131 | Toggle swtich |
132 | Supply & Fixing following spare parts suitable to Air Compressor of capacity 5HP including taking down old unserviceable spare parts complete all as specified and directed. |
133 | Limit switch |
134 | Motor bearings |
135 | Compressor Bearings |
136 | Piston Kit |
137 | Oil (20 W 40) |
138 | Supply only following items all as specified and directed. |
139 | Wax (Candle Powder) |
140 | Grease (Castrol Make) |
141 | Chemical salt |
142 | PPM Testing Liquid Set |
143 | Laundrex softener chemical |
144 | Laundrex Det |
145 | Laundrex boost |
146 | Laundrex neutral |
147 | Meghana Liquid Bleach |
148 | Supply & Fixing spare parts suitable to calender Machinesincludingtaking down old unserviceable spare parts complete all as specified and directed for Make of calender machines: Supershine &Megha laundry Eqpts |
149 | Variable frequency drive |
150 | Padding cloth |
151 | Blower Motor Rewinding |
152 | Temperature Meter |
153 | Speed Regulator |
154 | Push buttons (Red, Green,Blue) |
155 | NO-Element |
156 | NC-Element |
157 | Toggle Switch |
158 | Steam Solenoid Coil 15 mm |
159 | FLR Unit |
160 | Steam inlet Braided hose pipe 1" x 2 ft |
161 | Pneumatic cylinders servicing only except spares |
162 | Wax for cleaning chest |
163 | Guide Ribbons |
164 | Painting for feeding plate |
165 | Grease for chain and gear wheel teeth |
166 | Steam trap servicing |
167 | Air line and steam line with all connectors |
168 | Lubrication oil and gear oil |
169 | Steam line Y strainer 25mm dia |
170 | Disconnecting ofMotor from washing machine/ Hydro extractor/ Drying tumbler/flat bed press machine/bioler/any other equipment in laundry plant etc and material and labour for re-winding of electric motor with super enameled copper wire of good quality with same gauge and same size complete with all accessories including varnishing the winding for improvement of insulation by heating method and reassembling, installing, commissioning and testing after repair / rewinding, greasing and gland packing & necessary balancing arrangement with rubber bushes complete including transportation charges from site to work shop and back to its original position complete all as specified and directed for the following capacities:- |
171 | (a)up to 2 Hp |
172 | (b)above 2 HP to 5Hp |
173 | ©above 5Hp to 10Hp |
174 | M&L descaling of the following laundry equipments with approved descaling chemicals complete all as specified and directed. |
175 | Washing machine of 100 Kg capacity |
176 | Washing machine of 50 Kg capacity |
177 | 600 Kg/hr boiler |
178 | Supply & Fixing following spare parts suitable to Hydro Extractor of capacity 50Kg including taking down old unserviceable spare parts complete all as specified and directed forMake Hydro extractor :Megha laundry Eqpts |
179 | Contactor M L 1, 3 phase, 415 volts |
180 | Timer relay |
181 | Transformer |
182 | Timer |
183 | Buffer |
184 | Limit switch |
185 | Main motor bearings |
186 | Push button |
187 | Motor to body springs |
188 | Rubber bush for Hydro Extractor |
189 | Hydro Extractor motor bearings |
190 | Bridge rectifier |
191 | Diode |
192 | Body Spring support Bolts |
193 | Bush |
194 | Supply & Fixing following spare parts suitable to Air Compressor suitable for capacityup to 2HP including taking down old unserviceable spare parts complete all as specified and directed |
195 | Limit switch |
196 | Motor bearings |
197 | Compressor Bearings |
198 | Piston Kit |
199 | Oil (20 W 40) |
200 | Drain out the fuel from the fuel tank of Boiler of capacity up to 1000ltrs and keeping it in separate container safely, disconnecting all the fuel lines and other mechanical connections and taking out the fuel tank for cleaning, internally and externally by removing all the accumulated dirt/ sediment, leak testing the tank and welding/ brazing including one coat ofsynthetic enamel paint, refixing the tank in its original position, replacing the drain plug and PVC pipe, calibrating the fuel tank, refilling the drained out fuel back into the tank and marking of liters in gauge and provision of locking arrangements complete all as directed by Engr-in-charge. |
201 | S&F in MS Pipe line laid in trenchs/duct/ug/surface/wall/flooralongwith aluminium Cladding insulation including following accessories complete all as directed by Engr-In-Charge at the Loundry Plant at Military Hospital |
202 | 2 1/2" MS C Class Pipe |
203 | 2 1/2" MS T/E Flanges |
204 | 2 1/2" MS Long Bends |
205 | 25mm C Class Pipe |
206 | 25mm T/E MS Flange |
207 | 1"x 6" MS long Bends |
208 | 1"x 6" MS Nipples |
209 | 1" Elbow |
210 | 1" Tee |
211 | 1" Steam Traps |
212 | 1" MS Union |
213 | 1" Axe Nipples |
214 | Bolts and Nutssuitbale to existingPipes at Loundry plant , MH |
215 | 1/2" Teflon tapes |
216 | 1" globe valves |
217 | Welding Rods |
218 | Metallic Sheet |
219 | Cutting Wheels |
220 | M&L for door bedding for 50/100kg washing machines/drying tublers located MH laundry plant including taking down old unserviceable one complete all as directed by Engr-in-Charge. |
221 | Supply, lay, connect test and commissioning of solid copper conductor cable XLPE insulated screened PVC tape innersheathed, unarmoured electric power cable heavy duty with aluminium conductor 1100 volts grade corss sectional area of 16 Sqmm single Core confirming to IS:7098 Part-I laid in trenches/floors complete testing and commissioning complete all as directed. |
222 | All as per Item No. 25 above but for 25Sqmm single core all as directed by Engineer-in-Charge |
223 | All as per Item No. 25 above but for 50Sqmm single core all as directed by Engineer-in-Charge |
224 | Supply and Lay Galvanised, medium grade, ISI Marked as pe3r IS-1239 part - I galvanized, with all fittings such as bends, tees, elbows, reducers, unions, plugs, sockets etc., laid in trenches complete all as specified and as directed of following bores : - |
225 | 25mm dia bore |
226 | 40mm dia bore |
227 | 50mm dia bore |
228 | Supply and fixing Gun-metal glove or gate valve with iron wheel head, screwed both ends for iron pipe and fixed of Following sizes: |
229 | 25mm dia bore |
230 | 40mm dia bore |
231 | 50mm dia bore |
232 | S&F 2000 Ltrs capacity rotational mountain polythene water storatge water tank tripple layered as per IS-1270 - 1989 hoisted 2500 dia ball valve brass eith plythene float and fly nut and fixed in position including suitable inlet & outlet pipe ine connections & necessary platform complete including removing existing unserviceable tank complete all as directed. |
233 | Excavation in trenches in hard/dense soil not exe-1.5 mtr deep and not exe 1.5 mtr wide and getting out complete all as specified. |
234 | Returning filling in and including spreading, leveling, watering and well remaining in layer not exceeding 25 cm complete all as specified |
235 | Removal of surplus soil to a distance not exceeding 50 mtr and depositing under directed at a level not exce1.5 mtr above the starting point all as specified |
236 | Cleaning of Sewer collection chamber at E coy and FAEof MCEME by using mechanical means and cleaning the complete chamber including sludge of capacity 50000 liter complete all as specified and directed. Note: i) Quoted rates inclusive of all arrangements required for complete cleaning of the sump and the sewage / sludge to bo removed from the site and deposited to the outside Amryareas as per HMWS&SB guidelines. |
237 | Cleaning of Sewer collection chamberusing mechanical means and cleaning the complete chamber including sludge of capacity 25000 liter complete all as specified and directed. Note: i) Quoted rates inclusive of all arrangements required for complete cleaning of the sump and the sewage / sludge to bo removed from the site and deposited to the outside Amryareas as per HMWS&SB guidelines. |
238 | Supply and fixing stainless steelgrade (SS-304) pipe / square barvarying from 10 mm to 32mm dia with all fittings and fixturesfor provision of air grid laid in floors or fixed to wall, ceiling etc including necessary welding joints etc. and taking down old onecomplete all as specified. Note: The above item is uned for making cover of collection chamber / sattling tank of existing STP |
239 | Supplying, laying and testing of mild steel tubes 50 mm bore , ISI marked (IS-1239)(ISI marked) heavy grade with all fittings and fixtures laid in floors or fixed to wall, ceiling etc including necessary welding works including taking down old onecomplete all as specified . |
240 | Supply & fixing CI butterfly valve, flanged type,confirming to IS 13095 suitable for 50 mm bore pipe complete all as specified. |
241 | Supply & fixing CI butterfly valve flanged type, confirming to IS 13095 suitable for 65 mm bore pipe complete all as specified. |
242 | Supply & fixing CI butterfly valve flanged type, confirming to IS 13095 suitable for 80 mm bore pipe complete all as specified. |
243 | Supply & fixing CI butterfly valve, flanged type,confirming to IS 13095 suitable for 100 mm bore pipe complete all as specified. |
244 | Supply and replace column / suction pipe of sewage pumps including necessary fittings of doa 80 mm complete all as directed |
245 | Testing of water samples for bacteriological and chemical analysis as mentioned below from Pump Houses viz RCPH, GLPH, RAMC, GRPH High level , Safilguda, 36 JCO mercury, CTW, A Coy, B Coy "C" Coy E "Coy", HQ Coy, MH OHT, DGQA, DAD and certain other areas.complete all as specified and directed. Note: Testing of water for meter o water for Testing of water and Treated water in Each PH consider as One Job (a) Sample of Water for the above media test are to collected in transparent container/ Jar/bottle separately for each test against each pump house. ( Hyginenically clean bottles). 9b0 Sample of water to be collected shall be forwarded to Govt Lab. |
246 | Testing of Sewage Water Samples for BOD and COD testing analysisof 80 KLD STP at FAE complete all as specified and directed. (a) BOD (b) COD (a) PH Level (d) Total Suspended Soild (TSS) (e) Outlet Coliform Note: Testing of Sewage Water Treated sewage Water for total 06 STPs in three month Basis. (i.e Treated Sewage water in Each STPs consider as one Job) (a) Sample of Sewage Water for the above media test are to collected in transparent container/Jar/bottle separately for each test against each STPs. (Hygienically clean bottles). (b) Sample of water to be collected shall be forwarded to Govt Lab / any authorized Lab |
247 | Supply and replace unserviceable doors / covers of machinaries installed at mechanical laundry by using MS shhet of 2 mm thick including 2 coats of synthetic enamelled paint over a coat of redoxide primer complete all as directed. Note: Quoted rates inclusive of all arrangements required including bending and weldingduring execution |
248 | M&L for attending, repair and rectification of Boiler complaintsalongwith necessary T&P, safety devices as per site requirement for the following type of complaints complete all as specified and directed:- |
249 | M&L for attending, repair and rectification of Washing Machine complaintsalongwith necessary T&P, safety devices as per site requirement for the following type of complaints complete all as specified and directed:- |
250 | M&L for attending, repair and arresting of steam in pipe line complaintsalongwith necessary T&P, safety devices as per site requirement for the following type of complaints complete all as specified and directed:- |
251 | Advance Maintenance Free G.I. SAFE EARTHINGElectrodewith PIPEof not less than 50 mm outer dia) and two meterlength, The electrode should be ofgalvinised (80 -100 micron) along with earth lead as Galvanised steel strip of size 32 X6 mm7.5 m . The GI Electrode shall be pre-filled with Cristaline Conductive Material (CCM) . The GI electrode shall be surrounded with 25 kg BackFill compoundto provide maximum contact between the electrode and Back Fill Compound. The earting pitcover should be factorty built (sizeTOP- 10 Inch, Bottom -13 Inch, Height 10.25 Inch ) made of heavy duty Polypropylenecomplete all as specified and directedmakeASHLOK/INDELEC/JMV /TERCEL/TRUE POWER |
252 | M&L PCC 1:2:4 type B1 using 20 mm graded stone aggregate for motor plinth complete all as directed |
253 | Supply and replace Trolley wheel made of Teflon with bush of wheel size 6 inch an base 4 inch complete all as specified and directed |
254 | M&L chimney repair complete all as specified and directed by Engineer-in-charge |
255 | supply and fix fully automatic star delta starter without sheet metal enclousure, panel mounting type with timer, relay and contractor incl push button 2 nos for panel door mounting,of suitable rating for use at 25 HP Pump set connecting, testing complete all as directed at site. Make : BCH/ C& S/ L& T |
256 | Disconnecting, transporting, dismantling the induction motor of capacity 1 HP for the following repairs and reassembling the same after repairs incl transporting andre-installation at site duly connected electrically and water supply inlet and outlet connections all as specified and directed. Note :The cost of the items replaced will be paid separately under respective items of Sch "A" |
257 | Dismantling the Hydro Extractor 25 Kg induction motor of capacity 5.0 HP for the following repairs and reassembling the same after repairs, re-installation at site duly connection electrically and water in and outlet connections all as specified and directed. Note :Note : The cost of the items replaced will be paid separately under respective items of Sch "A" |
258 | (a)Rewinding complete with appropriate guage of supper enamelled copper wire as per existing guage and turns with insulating materials of best quality including varnishing (insulation) and all as directed. |
259 | Dismantling the Hydro Extractor 50 Kg induction motor of capacity 7.5 HP for the following repairs and reassembling the same after repairs, re-installation at site duly connection electrically and water in and outlet connections all as specified and directed. |
260 | (a)Rewinding complete with appropriate guage of supper enamelled copper wire as per existing guage and turns with insulating materials of best quality including varnishing (insulation) and all as directed. |
261 | Dismantling the washing Machine 100 Kg induction motor of capacity 10.5 HP for the following repairs and reassembling the same after repairs, re-installation at site duly connection electrically and water in and outlet connections all as specified and directed. |
262 | (a)Rewinding complete with appropriate guage of supper enamelled copper wire as per existing guage and turns with insulating materials of best quality including varnishing (insulation) and all as directed. |
263 | Dismantling the washing Machine 100 Kg induction motor of capacity 3.0 HP for the following repairs and reassembling the same after repairs, re-installation at site duly connection electrically and water in and outlet connections all as specified and directed. |
264 | (a)Rewinding complete with appropriate guage of supper enamelled copper wire as per existing guage and turns with insulating materials of best quality including varnishing (insulation) and all as directed. |
265 | S&F in replacement of following spare parts suitable to Oil fired incinerator capacity 60 Kg/ Hrs automatic waste feeding system fuel tank including taking down old unserviceable spare parts complete as under |
266 | M&L for Diesel Mono block fully automatic burners of Cat part No LO -20 including necessary spare ie, Sequence control, Ignition coil, transformer including necessary accessories. Make : Alfa Therm or its techno commercial equivalent make approve by GE. |
267 | M&L descaling of Primary Chamber 800 Degree Centigrade + 50 Degree Centigrade by Hydro chloric acid 33% concentration till the scaling is removed and cleaning of the chamber with fresh water. |
268 | M&L descaling of Secondary Chamber 1050 Degree Centigrade + 50 Degree Centigrade by Hydro chloric acid 33% concentration till the scaling is removed and cleaning of the chamber with fresh water. |
269 | M&L descaling of Secondary Chamber- static solid hearth mild cleaning by new technology method of the chamber with fresh water. |
270 | Repair & Replacement and servicing of automatic through hydraulic Ram pusher, hydraulic power pack. |
271 | Dismantling/Removing of oil fired incinerator Ventury Scribbing System ID Fan winding from motor,re-winding and Re-assembling the original position |
272 | Dismantling/Removing of FD Fan of Oil fired incinerator winding from motor,re-winding and Re-assembling the original position |
273 | S&F spare parts suitable to RO Plants of capacity 500 LPH-02 Nos including taking down old unserviceable spare parts complete all as specified and directed |
274 | Filter for RO Plant 500 LPH |
275 | Carbon Sand |
276 | Sand |
277 | 40x40 Membrane |
278 | Flow meter |
279 | Pressure guage |
280 | PTMT Ball Valve |
281 | Pump NRV of suitable size |
282 | UV System |
283 | PVC Pipe |
284 | Disconnection RAW water feed pump 0.5HP and re-winding,including replacement of unserviceable bearings of suitable size and re-assembling the motor including installation complete all as specified and directed. |
285 | Disconnecting High pressure pump 500 LPH and re-winding, including replacement of unserviceable bearings of suitable sizeand re-assmbling the motor including instalation complete all as specified and directed. |
286 | Mebrane housing for 40x40 RO membranes. |
287 | DG SETS M&L for Maintenance of DG set and carrying out ‘B’ check and replacement of ‘B’ check kit filters such as Oil filter, by pass filter, fuel filter,CR element and CR plates complete with ‘O’ rings and draining of Engine oil and topping up with the new engine oil complete testing all as specified and directed by the Engr-in-Charge for the following capacity DG sets:-Note :-(i) Engine oil shall be measured and paid separately (ii) Labour & transportation shall be arranged by contractor,quoted rate deemed to be inclusive in the unit rate. Make: KIRLOSKER/ CUMMINS /GREAVES/ GREAVES COTTON/ASIATIC/ RUSTON (a)up to 18 KVA DG Set |
288 | (b) above 18 KVA and up to 30kVA DG Set |
289 | (c)above 40 KVA and up to 63 KVADG Set |
290 | (e)125 KVA DG Set |
291 | Attending the daily checking the DG set of any capacity/make DG Sets in various locations in Zone A&B Areas , AMF Panels, by Technician & helper for checking all components and rectifythe fault and give report to concern JE complete all as directed by Engr-in-charge. Note :- Spare Parts for rectify the fault is measured and paid seperately. |
292 | M&L for Renewal/ repairs of unserviceable automatic voltage regulator (AVR) upto 125 KVA DG set including all spares, testing all as specified and directed by Engr-in-Charge. Make:- As per OEM approved make. |
293 | M&L for Renewal/ repairs of unserviceable automatic voltage regulator (AVR) above 125KVA and upto 320 KVA DG set including all spares, testing all as specified and directed by Engr-in-Charge. Make:- As per OEM approved make. |
294 | M&L for Dismantling of exhaust pipe of the DG set by unscrewing nuts and bolts and taking down the pipe with muffler removing the burnt out asbestos rope and well wrapping with new aluminium metal cladding with glass wool including cleaning the silencer, and fixing the same in its original position complete all as directed by Engr- in- Charge for the following capacity DG Sets. (a)up to30KVA |
295 | (b)40KVA to 182.5 KVA DG set. |
296 | M&L for Disconnecting all electrical connections from the unserviceable self starter of any make/ capacity model 24 volts and taking down the self starter and transporting to civil workshop for carrying out repairs, complete overhauling the system including replacing the unserviceable parts like bearings, carbon brushes, clutch plates etc & assemblingincluding after repair refixing the self starter in its original position,making all connection as per DG Set OEM recomendation, testing and commissioning complete all as directed by Engr-in-charge. Note:- Supply only Armature coil, field coil shall be measured and paid separately under relevant items of this Schedule. |
297 | Supply only Armature coil for self starter of any make, any capacity and any model 24 Volts including testing complete all as directed by Engr-in-charge |
298 | rewinding of field coil for self starter of 24 volts with fine enamelled copper conductor of same gauge with "F" class insullation, size twins and weight with necessary insulating materials, guage of conductor suitablef any make, any capacity and any modelcomplete all as directed by Engr-in-charge. |
299 | M&L for Disconnecting all electrical connections from the unserviceable self starter of any make/ capacity model 12 volts and taking down the self starter and transporting to civil workshop for carrying out repairs, complete overhauling the system including replacing the unserviceable parts like bearings, carbon brushes, clutch plates etc & assemblingincluding after repair refixing the self starter in its original position,making all connection as per DG Set OEM recomendation, testing and commissioning complete all as directed by Engr-in-charge. Note:- Supply only Armature coil, field coil shall be measured and paid separately under relevant items of this Schedule. |
300 | Supply only Armature coil for self starter of any make, any capacity and any model 12 Volts, 180/200 AH complete all as directed by Engr-in-charge |
301 | rewinding of field coil for self starter of 12 volts with fine enamelled copper conductor of same gauge with "F" class insullation, size twins and weight with necessary insulating materials, guage of conductor suitablef any make, any capacity and any modelcomplete all as directed by Engr-in-charge. |
302 | M&L for Disconnecting the oil cooler of capacity up to 100 KVA DG set of any make/ model from the existing locations duly removing of all mechanical connections and taking down the same for complete servicing opening the parts and cleaning thoroughly by using suitable cleaning material and acid and reassembling and refixing in its original position, testing and commissioning complete all as directed by Engr-in-charge |
303 | M&L for Disconnecting the oil cooler of capacity above 100kVA to 250KVA DG set of any make/ model from the existing locations duly removing of all mechanical connections and taking down the same for complete servicing opening the parts and cleaning thoroughly by using suitable cleaning material and acid and reassembling and refixing in its original position, testing and commissioning complete all as directed by Engr-in-charge |
304 | M&L for Renewal/ replacement of existing unserviceable air cleaning element inner and outer with necessary ‘O’ rings for the DG sets of following capacities as that of existing make and model complete all as directed by Engr-in-charge: - Make for item No.10 to 10.02:OEM recomended (a) Upto 100 KVA DG Set |
305 | (b) above 100 KVA and up to 182.5 KVA DG Set |
306 | M&L for Disconnecting all the incoming and outgoing rubber hoses and draining out the water from the choked radiator assembly of the existing make and model and various capacities of DG sets and taking down the radiator assembly by unscrewing all mechanical/electrical connections from the existing mounting, transporting the same to civil workshop for carrying out servicing, opening the top and bottom covers ofradiator assembly cleaning thoroughly the chocked pipe of the radiator by using chemical detergent, lime caustic soda, cotton etc., cleaning of all the deposited sediments in the pipes/tubes including arresting of leakage by means of soldering, brazing and transporting back to site and refixing the same in its original position with suitable size nuts, bolts and washers and Anti vibrating mounting(AVM) pads as required as per OEM recomendation etc., for the following DG sets all as specified and directed by Engr-in-Charge: (a) Upto 100 KVA DG Set |
307 | (b) above 100 KVA and up to 182.5 KVA DG Set |
308 | M&L for Renewal of battery cable leads of copper conductor and with brass lugs terminal, for the 12V, 150/180 /200 AHbatteries to self stater as that of existing size and length complete all as directed by Engr-in-charge |
309 | S&FAutomatic cut off type Battery Charger suitable for 12 V,up to 10 Amp Battery complete all as directed by Engr-in-charge. Make SMPS/ Phonix |
310 | S&F Automatic cut off type Battery Charger suitable for 24 V, up to 10 Amp Battery complete all as directed by Engr-in-charge. Make SMPS/ Phonix |
311 | M&L for Renewal/replacement of "V" belts for the following capacity DG sets as perexisting size and model complete all as directed by Engr-in-charge. Make:- FENNER/ DUNLOP (a) Upto 100 KVA DG Set |
312 | (b) above 100 KVA and up to 182.5 KVA DG Set |
313 | M&L for Renewal/replacement of fan belts for the following capacity DG sets as perexisting size and model complete all as directed by Engr-in-charge. Make:- As per OEM Recomendation (a) Upto 100 KVA DG Set |
314 | (b) above 100 KVA and up to 182.5 KVA DG Set |
315 | M&L for Renewal/replacement of Dynamo belts for the following capacity DG sets as perexisting size and model complete all as directed by Engr-in-charge. Make:- As per OEM Recomendation (a) Upto 100 KVA DG Set |
316 | (b) above 100 KVA and up to 182.5 KVA DG Set |
317 | M&L disconnecting & removingthe unservicable DC wiring from DG set of any type/any make/any model/any capacity and rewiring withthe same with suitable new copper wire to existing guage wire by providing flexible pipe including making all electrical connections as per OEM recomendation for satisfactory completion of job & checking of electrical/electronic spares working condtion and testingetc complete all as specified and directed. Note: (i) The rate quoted deemed to be inclusive of new copper wire cost in the unit rate. |
318 | M&L for replacement of existing unserviceable water temperature gauge with new water temperature gauge for the DG set of any description inclduing making necessary electrical /mechanical connections and taking down old unserviceable one complete all as directed by Engr-in-charge. Make: OEM recomended make |
319 | M&L for replaceemnt of existing unserviceable lubricant oil temperature gauge with new lubricant oil temperature gauge for the DG set of any capacityinclduing making necessary electrical /mechanical connections and taking down old unserviceable one complete all as directed by Engr-in-charge. Make: OEM recomended make |
320 | M&L for replacement of existing unserviceable oil pressure gauge with new oil pressure gauge for the DG SET of any capacityinclduing making necessary electrical /mechanical connections and taking down old unserviceable one complete all as directed by Engr-in-charge. Make: OEM recomended make |
321 | M&L for replacement of unserviceablesolenoid switch with new solenoid switch 12voltsfor DG set of any make and any capacityinclduing making necessary electrical /mechanical connections and taking down old unserviceable one complete all as directed by Engr-in-charge. Make :-OEM recomended |
322 | M&L for replacement of unserviceablesolenoid switch with new solenoid switch 24voltsfor DG set of any make and any capacityinclduing making necessary electrical /mechanical connections and taking down old unserviceable one complete all as directed by Engr-in-charge. Make :- OEM recommended |
323 | S&F in repairs the following spare parts for any type/make of DG sets, as and when required by the department complete all as specified and directed. Make for item no 23 to 23.10:- OEM recommended |
324 | Starting/Ignition - key/button |
325 | Volt Meter 0-500V |
326 | Amps Meter |
327 | Frequency Meter |
328 | S.D Valve assembly |
329 | Oil safety control |
330 | Water safety control |
331 | Water separator bowl 3247715 |
332 | Hour Meter |
333 | Radiator Metal Pipes |
334 | Supply and filling the new engine oil 20W/40 for toping up upto the required level complete all as directed by Engr-in-chargeMake :- CASTROL/ INDIAN OIL/ SERVO |
335 | Supply and filling the new engine oil 15W/40 for toping up upto the required level complete all as directed by Engr-in-chargeMake :- CASTROL/ INDIAN OIL/ SERVO |
336 | S&F in replacement of Line Voltage Monitors (LVMS) of existing make to DG set of 100 KVA to 625 KVA capacity listed parameters including testing complete all as specified and as directed. Make :- OEM recommended |
337 | S&F in replacement of Line Voltage Monitors (LVMS) of existing make to DG set capacity up to100 KVAcapacity listed parameters including testing complete all as specified and as directed. Make :- OEM recommended |
338 | Drain out the fuel from the fuel tank of DG set of capacity 500 Ltrs and above and keeping it in separate container safely, disconnecting all the fuel lines and other mechanical connections and taking out the fuel tank for cleaning, internally and externally by removing all the accumulated dirt/ sediment, leak testing the tank and welding/ brazing including one coat ofsynthetic enamel paint, refixing the tank in its original position, replacing the drain plug and PVC pipe, calibrating the fuel tank, refilling the drained out fuel back into the tank and marking of liters in gauge and provision of locking arrangements complete all as directed by Engr-in-charge. |
339 | S&F in replacement of Rectifiers of existing Make to DG Set of 100 KVA to 250 KVA capacity with all listed parameters including testing complete all as specified and directed. |
340 | S&F in replacement of Rectifiers of existing Make to DG Set capacity up to 100 to 125 KVA capacity with all listed parameters including testing complete all as specified and directed. |
341 | M &L for Removing of defective engine oil control pressure switch supply & fix new engine oil control pressure switch suitable for up to 100KVADG setcomplete all as directed by Engr-in-charge.Make as per OEM Recommendation. |
342 | M&L for Removing of defective engine oil control pressure switch supply & fix new engine oil control pressure switch suitable for above 100 KVA to 250 KVADG setcomplete all as directed by Engr-in-charge.Make as per OEM Recommendation. |
343 | M&L disconnecting & removingthe unservicable AC wiring from AMF panel ofDG set of any type/any make/any model/any capacity and rewiring withthe same with suitable new copper wire to existing guage wire by providing flexible pipe including making all electrical connections as per OEM recomendation for satisfactory completion of job & replacement of electrical/electronic spares and testingetc complete all as specified and directed. Note: (i) The rate quoted deemed to be inclusive of new copper wire cost in the unit rate. (ii) Electrical/Electrnoc spares shall be measured & paid separately under relevant items. |
344 | Supply only following spare parts:- (a)Push buttons. |
345 | (b) AMF Panel Hooter |
346 | (c) Earth fault relay.Make: OEM recomeded |
347 | (d) Over load relay.Make: OEM recomeded |
348 | (e) Over/Under voltage relay.Make: OEM recomeded |
349 | (f) Auxilary relays 12v/6Amps Make: OEM recomeded |
350 | (g)Power Contactor4 pole,02 NO +NC,400Amps,Make: L&T/Tc/ABB/SIEMENS/Schnieder/GE |
351 | (h)Power Contactor4 pole,02 NO +NC,250AmpsAmps,Make: L&T/Tc/ABB/SIEMENS/Schnieder/GE |
352 | (i)Power Contactor4 pole,02 NO +NC,200Amps,Make: L&T/Tc/ABB/SIEMENS/Schnieder/GE |
353 | (j)Power Contactor4 pole,02 NO +NC,160Amps,Make: L&T/Tc/ABB/SIEMENS/Schnieder/GE |
354 | (l)Power Contactor4 pole,02 NO +NC,100Amps,Make: L&T/Tc/ABB/SIEMENS/Schnieder/GE |
355 | (m) Single phase preventer,make:minilec/GIC |
356 | (n) Auxiliary Relays 24Volts / 6A Make: OEM recomeded |
357 | (o) PLC based AMF relay unit Make: OEM recomeded |
358 | (p)Low lube oil safety switch Make: OEM recomeded |
359 | (q)Booster Relay 24Volts / 10A Make: OEM recomeded |
360 | (r) Battery charger 24 V /10A panel mounting type Make: OEM recomeded |
361 | (s) Battery charger 12 V /10A panel mounting type Make: OEM recomeded |
362 | (t)Coolant temparature sensor Make: OEM recomeded |
363 | (u)Power contactor 4 pole, 02NO+02NC,63 Amps ,Make: L&T/Tc/ABB/SIEMENS/Schnieder/GE |
364 | (v)contactor operating coilofPower contactor 4 pole, 02NO+02NC,400 Amps ,Make: L&T/Tc/ABB/SIEMENS/Schnieder/GE |
365 | (w)contactor operating coil ofPower Contactor4 pole,02 NO +NC,250AmpsAmps,Make: L&T/Tc/ABB/SIEMENS/Schnieder/GE |
366 | (x) contactor operating coil of Power Contactor4 pole,02 NO +NC,200Amps,Make: L&T/Tc/ABB/SIEMENS/Schnieder/GE |
367 | (y)contactor operating coilofPower Contactor4 pole,02 NO +NC,160Amps,Make: L&T/Tc/ABB/SIEMENS/Schnieder/GE |
368 | (z)contactor operating coilofPower Contactor4 pole,02 NO +NC,130Amps,Make: L&T/Tc/ABB/SIEMENS/Schnieder/GE |
369 | (aa)contactor operating coil ofPower Contactor4 pole,02 NO +NC,100Amps,Make: L&T/Tc/ABB/SIEMENS/Schnieder/GE |
370 | (ab) contactor operating coilofPower contactor 4 pole, 02NO+02NC,63 Amps,Make: L&T/Tc/ABB/SIEMENS/Schnieder/GE |
371 | M&L for Removing the defective charging dynamo of capacity 24 Volt DC any make, model, any capacity and opening it, by removing all nuts and bolts, cleaning with necessary cleaning agent and overhauling lubricating of therewinding the damaged winding of field coilswith super enameled copper wire suitable tosame existing size/guage & reconnecting the same, refixing back, in original position including making all necessary electrical/mechanical connectionstesting and commissioning complete all as directed by Engr-in-charge. |
372 | M&L for Removing the defective charging dynamo of capacity 12 Volt DC any make, model, any capacity and opening it, by removing all nuts and bolts, cleaning with necessary cleaning agent and overhauling lubricating of therewinding the damaged winding of field coilswith super enameled copper wire suitable tosame existing size/guage & reconnecting the same, refixing back, in original position including making all necessary electrical/mechanical connectionstesting and commissioning complete all as directed by Engr-in-charge. |
373 | M&L for replacementof unserviceable spares for water manifold and Radiator spares upto 63 KVA DG set for the following spares:- (a)Radiator rubber hoses. |
374 | (b)Clamp for hump hose. |
375 | (c) Hose clamps. |
376 | (d) hump hose. |
377 | M&L for replacementof unserviceable spares for water manifold and Radiator spares above 63 and upto 182.5 KVA DG set for the following spares:- (a)Radiator rubber hoses. |
378 | (b)Clamp for hump hose. |
379 | (c) Hose clamps. |
380 | (d) hump hose. |
381 | M&L for replacementof unserviceable spares for water manifold and Radiator spares above 182.5 kVA and upto 250 KVA DG set for the following spares:- (a)Radiator rubber hoses. |
382 | (b)Clamp for hump hose. |
383 | (c) Hose clamps. |
384 | (d) hump hose. |
385 | M&L forInhibitor corrosion (coolant additive concentrate) required for top up (TVS Make) complete all as directed by Engr-in-charge. |
386 | Supply and topping up of acid mixture suitable for lead acid batteries of 12 volts complete all as directed by Engr-in-charge. |
387 | Supply and topping up of distilled water suitable for lead acid batteries of 12 volts complete all as directed by Engr-in-charge. |
388 | S&F battery brass terminaland jelly complete all as specified and directed. |
389 | M&L for Disconnecting all connection & remove the PT pump from engine and transport to OEM authorised service center and Calibration of PT pump for maximum efficiency by OEM Authorised Service center & replacement of PT Pump kit, gear gasket, etc in its original position by making all necessary connections complete whichever required under AGE E/M-I(U) AOR for smooth functioning of fllowingDG Set capacities complete all as directed by Engr-in-charge (a) DG Set capacity up to 63KVA |
390 | (b) DG set capacity above 63KVA to 182.5KVA |
391 | M&L for remove the fuel injection pump from the engine transport to an authorized service centre for service, calibration and to adjust by replacing the followingun serviceable worn-out spares with new appropriate make minor spares and bringing and fixing to the engine and tune up for maximum efficiency all as specified and as directed for DG set capacityup to 63 KVA :- Note: Major spares required will be measured and paid seperately. |
392 | Supply only orfice for up to 63KVA capacity DG set |
393 | Supply only Barrel and Plunger for up to 63KVA capacity DG set |
394 | Supply only FIP Bearingfor up to 63KVA capacity DG set |
395 | M&L for remove the fuel injection pump from the engine transport to an authorized service centre for service, calibration and to adjust by replacing the following un serviceable worn-out spares with new appropriate make minor spares and bringing and fixing to the engine and tune up for maximum efficiency all as specified and as directed for DG set capacity above 63 KVA and upto 182.5KVA :- Note: Major spares required will be measured and paid seperately. |
396 | Supply only orfice for above above above 63 KVA and upto 182.5KVAcapacity DG set |
397 | Supply only Barrel and Plunger for above 63 KVA and upto 182.5KVAcapacity DG set |
398 | Supply only FIP Bearingfor above 63 KVA and upto 182.5KVA capacity DG set |
399 | M&L for remove the fuel injection pump from the engine transport to an authorized service centre for service, calibration and to adjust by replacing the followingunservicable worn-out spares with new appropriate make minor spares and bringing and fixing to the engine and tune up for maximum efficiency all as specified and as directed for DG set capacity above 182.5 KVA and upto 250KVA :- Note: Major spares required will be measured and paid seperately. |
400 | Supply only orfice for above 182.5 KVA and upto 250KVA capacity DG set |
401 | Supply and fix self starter Motor, 24 volts, Make LUCAS or its equivalent make approved by OEM of DG Set suitable for existing DG set above 82.5 KVA to 250 KVA including making all necessary electrical/mechanical connection as per recomendation of OEM of DG Set & dismantling/taking out old unserviceable self starter Motor from existing positioncomplete all as directed by Engr-in-charge |
402 | Supply and fix self starter Motor, 12 volts, Make LUCAS or its equivalent make approved OEM of DG Set suitable for existing DG set capacity up to82.5 KVAincluding making all necessary electrical/mechanical connection as per recomendation of OEM of DG Set & dismantling/taking out old unserviceable self starter Motor from existing positioncomplete all as directed by Engr-in-charge |
403 | M&L for Servicing of DG Set panel"s MCCB Breaker indoor/outdoor type of any make/model/capacity, checking of switching ON/OFF& tripping system, checking of all electrical mechanical components of AMF panel and Setting the same for proper working of Breaker, testing of operation manually and auto mode complete all as directed by Engr-in-charge. Note:-All the mechanical parts are thoroughly cleaned by suitable cleaning agent & moving parts are properly lubricated |
404 | Supply,install, test, commissioning & run the DG set"sFly-wheel Ring of Fly-wheel Assembly of existing model,sizesuitable to DG Set of capacity up to 125 KVA including taking down old Unserviceable complete all asdirected by Engr-in-Charge. |
405 | Supply,install, test, commissioning & run the DG set"sFly-wheel Ring of Fly-wheel Assembly of existing model,sizesuitable to existing DG Set of capacity above 125kVA up to 250 KVA including taking down old Unserviceable complete all asdirected by Engr-in-Charge. |
406 | Disconnectthe Radiator and kept aside safely and taking down the old unserviceable water pump from the existing engine of DG set any make/model, capacity up to 125 KVAsupply and fixing of new water pump &kit,reassembling the same and refixing the pump to the engine of DG set, refixing Radiator and testing,including making all Electrical/mechanical connections,commissioning as per OEM recomendation complete all as directed by Engr-in-charge. |
407 | Disconnectthe Radiator and kept aside safely and taking down the old unserviceable water pump from the existing engine of DG set any make/model, capacity above 125KVA andup to 250 KVAsupply and fixing of new water pump &kit,reassembling the same and refixing the pump to the engine of DG set, refixing Radiator and testing,including making all Electrical/mechanical connections,commissioning as per OEM recomendation complete all as directed by Engr-in-charge. |
408 | Supply, Fix & test run the DG set after replacing Diesel feeder Pumpof existing model,sizesuitable to DG Set of capacityup to 125 KVA including taking down old unserviceable complete all asdirected by Engr-in-Charge. |
409 | Supply, Fix Diesel benjo Hose pipes of 1.0 Meter length with both edges brass clampsof existing modelsuitable to DG Set of capacity up to 125 KVA including taking down old unserviceable complete all asdirected by Engr-in-Charge. |
410 | Supply, Fix Diesel benjo Hose pipes of 1.0 Meter length with both edges brass clampsof existing modelsuitable to DG Set of capacity above 125kVAup to 250 KVA including taking down old unserviceable complete all asdirected by Engr-in-Charge. |
411 | M&L for disconnecting all electrical & mechanical connections,Dismantle the Engine (make KIRLOSKER/ CUMMINS /GREAVES/ GREAVES COTTON/ASIATIC/ RUSTON)from 100KVA to 250 KVA DG set capacities located at various location under AGE E/M-I(U)and transported to OEM Authorised service center for complete overhauling, replacing the followingunservicable worn-out spares with new appropriate make minor spares & major spares (minor spares- up to Rs2500/Each), after assembling the spares the Engine again shfted to original existing place and reassembled to alternator& radiator,AMF panel/Electrical panel board of DG set complete testing,commissioningall as per OEM recomendation and as directed by Engr-in-charge.The quoted rate inclusive ofManpower, Crane charges for transporting engine to wokshop and back after repairs Note: -(i)Major Spare parts shall be measured and paid separately. |
412 | Gear fuel Pump |
413 | Total Gakets Set |
414 | Core & cooler set |
415 | Shaft rocker arm |
416 | Oil seal |
417 | Ball Bearings set |
418 | Main Bearings set(STD) |
419 | Material and labour for repairs to Alternator of following DG Set, transporting the same to theOEM authorised service center/work shop and carrying out the repairs such as taking out the burnt out winding and rewinding the alternator with copper wire of same guage turns and weight, checking of commentator, brushescomplete and refixing the same in its existing position after transporting back to the site and connecting up electric connections with suitable lugs complete and testing all as specified and directed. Note: Copper winding material will be measured and paid seperately under relevant Item |
420 | Upto 100 KVA capacity |
421 | Above 100 KVA and upto 125 KVA Capacity |
422 | Supply only High conductivity copper conductor winding material including necessary insulation material as required for complete all as specified and directed by Engr-in-Chrage |
423 | M&L taking down defective Turbo Charger Assembly duly disconnecting the mechanical and electrical connections from DG Set, opening and thoroughly checking to carry out repairs complete to the Turbo Charger Kit and spares as required at site including any mechanical and reassembling and refixing the turbo charger assembly to its original position and reconnecting the same for the following capacities including testing complete all as specified and directed. |
424 | DG Set of capacity above 40 KVA and up to 82.5 KVA |
425 | DG Set of capacity above 100 KVA and up to to 182.5 KVA |
426 | M&L for calibration of water pump complete, overhauling, replacing of gaskets, nuts, washers etc and reassembling the same and refixing the pump to the engine and testing including taking down the old unservicable water pump of any capacity of DG set from the engine and taking it out side work to workshop, complete all as specified and directed:- |
427 | DG Set of capacity 7.5 KVA To 40 KVA |
428 | DG Set of capacity above 40 KVA and up to 82.5 KVA |
429 | DG Set of capacity above 100 KVA and up to to 182.5 KVA |
430 | M & L for dismantling & disconnecting all connection of the cylinder heads from diesel engine and sent to OEM authorised Service center for calibration and repairs by replacing the spares such as Valves, Value Guides, Valves seats and repairs kit and re-assembling to its original position with necessary Engine cylinder head gasket and O rings for the following capacities including testing complete all as specified and directed:- |
431 | DG Set of capacity 7.5 KVA To 40 KVA |
432 | DG Set of capacity above 40 KVA and up to 82.5 KVA |
433 | DG Set of capacity above 100 KVA and up to to 182.5 KVA |
434 | M&L preparation of old painted surfaces of the DG Sets of the 7.5 KVA to 25 KVA capacity including degreasing and spray painting the DG sets with one coat of synthetic enamel paint of approved colour and writing SM/MES No including painting on concrete surfaces of foundations with black paint complete all as specified and directed. |
435 | M&L preparation of old painted surfaces of the DG Sets of the above 25 KVA and up to 82.5 KVA capacity including degreasing and spray painting the DG sets with one coat of synthetic enamel paint of approved colour and writing SM/MES No including painting on concrete surfaces of foundations with black paint complete all as specified and directed. |
436 | M&L preparation of old painted surfaces of the DG Sets of the above 82.5 KVA and up to 182.5 KVA capacity including degreasing and spray painting the DG sets with one coat of synthetic enamel paint of approved colour and writing SM/MES No including painting on concrete surfaces of foundations with black paint complete all as specified and directed. |
437 | M & L earthing complete with galvanised steel earth plate electrode 60cmx 60cmx 6mm thick buried directly in ground earth pit not less than 2.25 mtr deep below normal ground level) with top edge of plate not less than 1.5m below ground level, connecting to the Galvanised iron earth strip 32 x 6mm dia, by means of nuts, bolts,check nuts and washer etc of galvanised iron and earth lead protected by provision of GI pipe medium grade 40mm bore from earth elelctrode to test pointincl provn of concrete pit in PCC (1:2:4) type B-1 using 20mm graded stone agagregates with 40mm thick cover of RCC (1:2:4) reinforced with XPM sheet (weight not less than 4Kg/Sqm) and frame of angle iron 25 x 25 x 6mm with lugs 2 Nos and with 8mm dia MS bar handle made to shape, GI pipe medium grade 20mm bore pipe for watering perforated at bottom 1.75 mtr long placed on top edge of earth plate, common salt and charcoal filling test point with fixing arrangement, funnel, wire mesh and earth work in hard/dense soil, returning in and removal of surplus soil to a distance not exceeding 50mtr, complete all as specified in electrical plate No 3 of SSR Part I and connection to earth test point including testing on completion all as directed. Note:- Item of earthing includes cost of 7.5m long galvanised iron earth strip of 32 x 6mm size and protection pipe of 40mm bore GI medium grade. |
438 | M&L on load change over switch 400 Amps capacity suitable for 3 phase, 4 pole, 415 Volts,font handle operated suitable in open execution type for fixing in existing panels including necessary lugs,glands.,nuts,bolts inclduing taking down old unserviceable one complete all as specified and directed Make:- Havells/L&T/Standard/HPL |
439 | M&L on load change over switch 200 Amps capacity suitable for 3 phase, 4 pole, 415 Volts,font handle operated suitable in open execution type for fixing in existing panels including necessary lugs,glands.,nuts,bolts inclduing taking down old unserviceable one complete all as specified and directed Make:- Havells/L&T/Standard/HPL |
440 | M&L Off load change over switch 200 Amps capacity suitable for 3 phase, 4 pole, 415 Volts,side handle operated with sheet metal enclosure suitable for fixing in existing panels including necessary lugs,glands.,nuts,bolts inclduing taking down old unserviceable one complete all as specified and directed Make:- Havells/L&T/Standard/HPL |
441 | M&L Off load change over switch 400 Amps capacity suitable for 3 phase, 4 pole, 415 Volts,side handle operated with sheet metal enclosure suitable for fixing in existing panels including necessary lugs,glands.,nuts,bolts inclduing taking down old unserviceable one complete all as specified and directed Make:- Havells/L&T/Standard/HPL |
442 | Supply,test,install & commsissioning ofBus bar chambers(including 4 bus bars i.e R,Y,B and neutral),3-Ph with netral,1100volts,50Hzincluding suitable sheet metal enclosure along with necessary screws,nuts,bolts and other Misc accessroies and making connections(input &out put) with cable terminal ends complete for the following current carrying capacities (a)4-Way, 100 Amps Make: Havells/L&T/Standard |
443 | (b)4-Way,250Amps |
444 | Disconnecting & taking out unserviceable MCCB and Supply,test,install & commissioning of newMCCB 4 pole, 315 Amps to 400Amps, 50kA, 415volts,50 Hz with adjustable settings & thermal,magnetic realse,suitable for exisitng panel(frame size shall be matched with existing one) of the following capacities for fixing in panel board/sheet metal enclosures/distribution boards with necessary cable connections,suitablel lugs, glands,nuts,bolts and screws complete all as specified and directed. Make:- Havells/L&T/Standard/HPL. |
445 | Supply&Fixing of3 pole MCB,32-63amps,C-curve,10kA,50Hz,440v in existing panel including necessary wiring & misc accessroies for satisfactory completion of job and taking down old unserviceable one complete all as directed by Engineer-in-Charge. Make:L&T/Schnieder/Seimens |
446 | Supply&Fixing of 200/5 Amps Current transformers -03Nos(in three phases) including necessary wiring & misc accessroies for satisfactory completion of job taking down old unserviceable one complete all as directed by Engineer-in-Charge. |
447 | S&F twin core 4 Sqmm service wire 1100V grade heavy duty with PVC insulated aluminium stranded conductor served with inner sheatning of PVC tape andPVC sheathed including taking down old unserviceablecomplete all as directed. Make- Finolex/Havells/Standard /Finecab. |
448 | S&F twin core 6 Sqmm service wire 1100V grade heavy duty with PVC insulated aluminium stranded conductor served with inner sheatning of PVC tape andPVC sheathed including taking down old unserviceable complete all as directed . Make- Finolex/Havells/Standard /Finecab. |
449 | S&F twin core 10 Sqmm service wire 1100V grade heavy duty with PVC insulated aluminium stranded conductor served with inner sheatning of PVC tape and PVC sheathed including taking down old unserviceable complete all as directed. Make- Finolex/Havells/Standard /Finecab. Notes for all items :- (a) Daily Collecting of complaintsfromJE/AGEisresponsiblity of Contractor. After collecting Complaints from Complaint Register or Insturction by JE by Phone/SMS, complaint should be completed within 12 Hours of complaint receiving, Major complaints/AMF panel wiring/Rewinding etc items should becompleted within 05 days, (b)Minimum 01 Technician with all tools, ladder and testing Equipment, as per the site requirement shall be provided by contractor. (c) Every month complete testing for serviceablity of DG Set for all Generator shall be done and reports submitted to Engr- in -Chage at the end of every month (if items required shall bepaid under relevant items given above). (d)Documents required for complaints like Stationery, Complaint Register, Slips & Site Order Book shall be provided by the contactor.(e) safety precautions shall be responsible by the contractor. (f) Contractor to comply all the respective notes of Particular Specifications attached. |