Aurangabad Municipal Corporation has published Tender For Replacing Drainage Line At Various Places At.Kotwalpura, Garampani In Ward No.50. Submission Date for this Tender is 13-02-2024. Drainage Tenders in Aurangabad Maharashtra. Bidders can get complete Tender details and download the document.
Sl. No. | Item Description |
1 | WORK PORTION (PART-A) Removing rich mix cement concrete including stacking the spoils as directed with all leads, lifts etc, complete. SSR No.46.13 |
2 | Excavation for Trenches in earth, soil of all types, sand, gravel and soft murum, including removing the excavated material up to a distance of 50 m. beyond the building area and stacking and spreading as directed, dewatering, preparing the bed for the foundation and necessary back filling, ramming, watering including shoring and strutting etc. complete. (Lift upto 1.5 m.) SSR No Section E Particular No.01 |
3 | Excavation for foundation / pipe trenches in hard murum and boulders, W.B.M. road including removing the excavated material upto a distance of 50 M beyond the area and lifts as below, stacking and spreading as directed by Engineer-in-charge. normal dewatreing, preparing the bed for foundation and excluding backfilling, etc. complete.(Bd-A-3/259) Lift 0 to 1 .5 M SSR NO Section E ParticularNo.05 |
4 | Excavation for foundation / pipe trenches in soft rock and old cement and lime masonry foundation asphalt road including removing the excavated material upto a distance of 50 M beyond area and lifts as below, stacking as directed by Engineer-in charge, normal dewatering, preparing the bed for foundation and excluding backfilling, etc. complete. ( Bd-A-4/259) Lift 0 to 1 .5 M SSR No Section E partifular NO.05 |
5 | Excavation for foundation / pipe trenches in hard rock and concrete road by chiselling, wedging, line drilling, by mechanical means or by all means other than blasting including trimming and levelling the bed, removing the excavated material upto a distance of 50 metres beyond the area and lifts as below, stacking as directed by Engineer-in-charge, normal dewatering, excluding backfilling, etc. complete by all means. (Bd-A-1/259) Lift 0 to 7 Page 1 of 381 1.50 M SSR No. Section E Particular No.07 |
6 | Removing existing pipe line of the following pipe size stone ware pipes / R.C.C. pipes excluding cost of necessary excavation and refilling of the trenches, breaking the joints, lifting the pipes and stacking to the place as directed by the Engineer - in - charge with all leads and lifts including cleaning the surfaces etc. complete.(200mm Dia pipe) SSR No as Per Rate Analysis SSR No 24 2B3 |
7 | Providing ISI standard stonewere pipes, joints, including all taxes(Central and local),inspection charges, railway freight, loading unloading from railway wagons, loading into trucks, transport to departmental stores/ stacking,etc.complete. MJP DSR item no 1 Page No 87SSR No as Per Rate Analysis SSR No 24 2B3 |
8 | 225mm |
9 | 250mm |
10 | 300mm |
11 | Lowering, laying and jointing in proper grade and alignment Stoneware pipes with cement joints in CM1:1 proportion following diameter including cost of conveyance from stores to site of works, cost of jointing material, labour, giving hydraulic testing, etc.complete MJP DSR page no . Section 9, DSR item no 2 page no 87(250mm dia SWG pipe). SSR No as Per Rate Analysis SSR No 24 2B3 |
12 | 225mm |
13 | 250mm |
14 | 300mm |
15 | Providing and laying cement concrete pipe of IS 458:2003 NP-2 class of 450mm diameter in proper line, level and slope including providing and fixing collars in cement mortar 1:2 and curing etc. complete. SSR No.11.08 |
16 | Providing and constructing on sewer, B. B. masonry circular manhole with concentric cone 0.9 M dia. at bottom and 0.5 M dia. at top and upto a depth of 1.0M with 23 cm brick work in CM 1:4 proportion smooth rendering, Rebate of 2300 per 30 cm 0.90m as per rate analysis. (1.5m depth) |
17 | 1.0 m Depth |
18 | 1.5 m Depth |
19 | Providing and constructing on sewer, B. B. masonry circular manhole with concentric cone 1.2 M dia. at bottom and 0.5 M dia. at top and upto a depth of 2.00 M with 23 cm brick work in CM 1:4 proportion excluding excavation including foundation concrete 250 mm thick and haunches and channels in C. C. 1:2:4 proportion, finishing channels in smooth rendering, providing C.I. dapuri type steps each weighing 5.5 kg., 1:2:4 coping and providing and fixing approved make and quality S.F.R.C. frame and cover of 56 cm dia. etc. complete as directed by Engineer in charge.As per rate analysis |
20 | Providing and constructing Brick Masonry inspection trap Chamber 90cm x 45cm including 1:4:8 C.C foundation, 1:2:4 C.C.channels/half round glazed stoneware pipe channel, salt glazed stone-ware intercepting trap with rodding pipe set in 1:4:8 cement concrete block, brick masonry plastering inside and Outside, fixed in cement concrete with R.C.C. Cover medium duty 140 kg. etc complete SSR No.42.15 |
21 | Refilling the trenches with available excavated stuff with soft material first over pipe line and then hard material in 15cm layers with all leads and lfts including consolidation, surcharging, etc. complete.As per Rate analysis |
22 | Providing steel fiber reinforced concrete (S.F.R.C.) frame, cover heavy duty/ medium duty of rectangular or circular in shape of approved make including loading unloading, transportation, all taxes etc. complete as directed by engineer in charge (as per 18 circular HD 540/630mm with frame.As per rate analysis |
23 | 540 mm HD Circular SFRC |
24 | 90 X 60mm Rectangular SFRC |
25 | Repairing to existing manhole chambers after fixing pipes with necessary brick works, benching, channeling, plastering etc. complete.(as per rate analysis). |
26 | RaisingB.B. masonry circular manhole of 0.9m dia.without conical shape excluding excavation, brick masonry in CM 1:4 proportion 23 cm thick, plastering with smooth finish in CM 1:2 proportion, fixing S.F.R.C. frame and co ver ( Excluding cost of SFRC Cover)including cost of all materials and labour, etc. complete. as per rate anaylsis |
27 | Fixing of SFRC frame and cover to manhole chamber / rectangular S.F.R.C. cover and frame in c.c. M-15 (concrete 1:2:4 prop) etc. complete (as per rate analysis) 22-circular HD 540/630 with frame.Asper sanctioned rate |
28 | Transportation of surplus material from work site to any disposal place as directed by the Engineer - in - charge with a lead of ___3.00____ km including and stacking etc. complete. As per sanctioned rate |
29 | ROYALTY (PART-B) Royalty as per govertment of maharastra revenue and forest departmentsgazettle no 67 date 15 may 2015 ( charges for metal, sand, murum )…etc complete. As per Rate Analysis |
30 | Contractor has to quote on only Work Portion (Item No.01 to 18) |