Uttar Pradesh Jal Nigam-UPJN has published Tender For Nagar Panchayat Dewa Re-Organization Water Supply Scheme Distt Barabanki. Submission Date for this Tender is 29-02-2024. Water Supply Project Tenders in Barabanki Uttar Pradesh. Bidders can get complete Tender details and download the document.
Sr No | CorrigendumDate | Corrignedum | CorrigendumType | NewSubmissionDate |
1 | 13-Feb-2024 | Prebid Meeting Date | Date | 29-02-2024 |
Sl. No. | Item Description |
1 | Construction of Pump House of size (3.60mx 3.00m x 3.00) cum chlorinating room size (1.8mx2.60m x 3.0m) as per type design. |
2 | Zone-1 |
3 | Zone-2 |
4 | Rising Main Zone 1 &2 |
5 | Supply of following sizes of D.I pipesclass K-7/9 withalljointingmaterialsasperIS- 8329/2000 or its latest amendments including F.O.R. destination and all taxes and insurance etc. complete |
6 | 200 mm dia DI.K-9 |
7 | Supply of D.I. D/F specials including F.O.R. destinationandalltaxesandinsuranceetc. complete |
8 | Supply of following sizes of D.I double flangedsluicevalveasperI.S:14846:2000 working pressure 10 Kg/cm2 F.O.R. destination and all taxes and insurance. |
9 | 200 mm |
10 | Carting of following sizes D.I.D/F Sluice valve and specials from departmental store to site of work and lowering theminto the trenches, fixing in position and jointing them with pipelines and testing etc. complete (including supply of jointing materials) |
11 | 200 mm |
12 | Excavationfor pipe line trenches in ordinary soil(loam,clayorsand)includingliftupto 1.5m and refilling, watering, ramming of excavated earth into trenches anddisposal of surplus earth up to 50m from the center of the foundation trenches. |
13 | Carting of following sizes D.I. pipes class K- 7/9 and specials to the site of work lowering them in to trench and laying true to alignment includingtestingofpipelinebutexcluding cost of trenching and cutting of pipes etc. for making of length but including making joints. |
14 | 200 mm |
15 | Dismantling of following type road and stackingofusefulmaterial andtemporary reinstatementofroadwitholdmaterialsetc. complete. |
16 | Bituminous Road |
17 | CC Road |
18 | Reinstatement of following type road and stackingofusefulmaterial andtemporary reinstatementofroadwitholdmaterialsetc. complete. |
19 | Bituminous Road |
20 | CC Road |
21 | Supply of all material labour, T&P etc. Required and construct of Sluice Valve Chamber Masonry Type as per type design. |
22 | Thrust Block |
23 | Supply of all materials labour T&P etc. complete and construction of R.C.C. (M30 Grade)Over Head Tank of following capacity and staging above ground level with all work complete, including cost of soil testing. All the components of OHT will be casted in M30 concrete & specially in M-30 construction of water bearing structure with cement, coarse sand and approved stone grit as per I.S. 11682, I.S.3370 part (I) & (II) and I.S.456.Minimum depth of foundation below original ground level will be 2.5M. Seismic effects and wind load should be taken into consideration as I.S. 1893 for earthquake resistance and as per I.S. 875 part-III for wind load on structure (this area is in seismic Zone IV and high damage risk zone for wind).The cost of OHT should be quoted assuming the bearing capacity of soil as 8 M.T.per sqm. including 1M wide RCC staircase from ground level to balcony. M.S. ladder made of 50x50x6 mm angle section and 20mm plain M.S. bars (specification of M.S. should be as per IS 800-2007) with hand rails of 20mm medium class G.I. pipes on both sides in three rows from balcony to top dome resting on an RCC platform (75cmx75cm and 10cm thick) projecting from top ring beam and one aluminum ladder inside the tank body (from manhole in top dome to bottom as per design and specification approved by Engineer in charge. 1 m wide R.C.C. M25 balcony around the tank at the junction point of vertical wall and conical wall. Proper railing of 20mm dia medium class G.I. pipe (in 3 rows) on both sides of stair case, around the balcony, at each landing and from landing with top ring beam upto manhole on the top dome and at the periphery of top dome. The G.I. Pipes will be supported on M.S. posts made of or RCC post, spaced at intervals not more than 1.5m.Proper ventilator at top dome in circular shape of 1.2 m dia. along with an R.C.C. cover of minimum 1.50m dia and with mosquito net of standard quality along with expanded metaled jali between top dome and RCC cover. Water level indicator fabricated with good quality minimum 45mm x 45mm x 6mm M.S. angle with indicator board scale made 50x50x6mm M.S. angle section, of 3mm thick M.S. plate should have a clear width of minimum 25cm painted with good paint with brass wire rope, pulley, copper ball float, pointer etc. Lightening conductor should be as per I.S.S.2309 or its latest amendments of latest electricity rules. C.I. manhole cover of min 60x60cm size with locking arrangement, Supply, fixing & jointing of C.I.D./F Pipes (for inlet, outlet, washout and overflow pipes) and specials, duck foot bend and fixing of the sluice valve at outlet and wash put pipe with all specials; construction of sluice valve chamber, floor and apron with semi circular drain around the apron with 25mm PCC 1:2:4 over 75 mm PCC 1:4:8, Apex painting on outer surface of OHT, painting on MS ladder, railing, vertical pipe etc. as per approved make; excavation in all type of soil and all other works required for proper and complete construction |
24 | Zone 1 1000KL / 18M |
25 | Zone 2 1000KL/ 20M |
26 | Distribution Zone 1 and 2 |
27 | Excavation of earth in ordinary soil (loam, clay or sand)forlayingofpipelineincludingrefilling anddisposal of surplus earth for different size of pipe lift up to1.5m and50 m away. |
28 | Supplyoffollowingsizesofpipeincludingrail way freight and cartage as per IS 8329/2000 and IS4984/2016ortheirlatestamendmentsupto divisional store including all taxes etc. complete. |
29 | HDPE Pipe (Grade PE-100) PN-6 |
30 | 90mm diaO.D. |
31 | 110mm dia O.D. |
32 | 140 mm dia O.D. |
33 | 160 mm dia O.D. |
34 | DI Pipe K-7 |
35 | 200mm dia |
36 | 250mm dia |
37 | Supply of specials for above HDPE Pipe @ 5% of pipe supply. (including specials required for electrofusion jointing.) |
38 | Supply of specials for above DI Pipe @ 10% of pipe supply |
39 | Carting, laying and jointing by Electrofusion Method of the following sizes ofpipe intothetrenchesincludingcostofall jointingmaterial,labour,T&Pandtestingetc, complete. The rate includes all material, labour and T&P for electrofusion jointing of HDPE pipe. |
40 | HDPE Pipe (Grade PE-100) PN-6 |
41 | 90mm diaO.D. |
42 | 110mm dia O.D. |
43 | 140 mm dia O.D. |
44 | 160 mm dia O.D. |
45 | DI Pipe K-7 |
46 | 200mm dia |
47 | 250mm dia |
48 | Supply of following types of fitting including rail wayfreight,cartageuptostore, all taxesand insurance.D.I.D/FSluiceValve/ScourValveas per IS 14846:2000 suitable for working pressure10 kg/cm2. |
49 | D.I.D/F Sluice Valve |
50 | 80mm dia |
51 | 100mm dia |
52 | 125mm dia |
53 | 150mm dia |
54 | 200mm dia |
55 | 250mm dia |
56 | Scour Valve 80mm dia |
57 | Fire Hydrant (Sluice Valve Type) |
58 | 80mm dia |
59 | CI Single ball type Air Valve |
60 | 25mm dia |
61 | CartingoffollowingsizesD.I.D/FSluicevalve andspecialsfromdepartmentalstoretositeof work and lowering them into the trenches, fixing inpositionandjointingthemwithpipelinesand testing etc. complete (including supply of jointing materials) |
62 | D.I.D/F Sluice Valve |
63 | 80mm dia |
64 | 100mm dia |
65 | 125mm dia |
66 | 150mm dia |
67 | 200mm dia |
68 | 250mm dia |
69 | Scour Valve 80 mm dia |
70 | Fire Hydrant (Sluice Valve Type) |
71 | 80mm dia |
72 | CI Single ball type Air Valve |
73 | 25mm dia |
74 | Supply of all type materials and construct following chamber as per type design with supply of all labour, T & P etc. complete. |
75 | Masonry Type |
76 | Fire Hydrant Chamber |
77 | Air Valve Chamber |
78 | Surface Box Type |
79 | Dismantlingoffollowingtyperoadandstacking of useful material and temporary reinstatement of road with old materials etc. complete. |
80 | B.O.E Road |
81 | Bituminous Road |
82 | CC Road |
83 | Interlocking Road |
84 | Reinstatement of following type road and stacking of useful material and temporary reinstatement of road with old materials etc. complete. |
85 | B.O.E Road |
86 | Bituminous Road |
87 | CC Road |
88 | Interlocking Road |
89 | Provision for crossings of nalas & culvert includingsiftingoftelephonecablesetc.Along the alignment of pipeline including supply of C.I. tytonpipeand specialsetc.complete.(3.5M. Wide Road) |
90 | Provision forInstallation of ductpipesby Augerboringmethodincludingmakingofentry andexitpitsupto3mtrdepth,allrelatedcivil works like excavation etc. lowering of pipe segmentsinthejackingpit,layingjointingof pipeline through jacking process as per the instruction of Engineer-in-charge all complete. |
91 | 200-250mm dia (2Nos.) |
92 | 90-140mm dia(3Nos.) |
93 | MCS Room |
94 | Construction ofMCS,Centralized ControlRoomincludingSupplyof all materials, labour, T&P, complete |
95 | Boundary Wall Gate and approchroad and site devlopment |
96 | Supply all materials, labour, T&P etc. required for proper completion of work as per type design. |
97 | Supplyandfixing3.6M&1.20MwideMSGatewith pillersincludingfabrication andsupplyofsteeland construction of boundary pillarsetc. completefor pump house |
98 | Provideallmaterials,labour,T&Petc.Requiredfor propercompletionofworkandconstructInterlocking Tiles approach road, laid dry and joints intact with coarse sand mortar including preparation of base etc. |
99 | Earth filling inside the water works campus |
100 | New / Shifting of House Connections |
101 | Making ferrule connection in. Distribution mains with saddle piece, service connections, fittings, and fixing of G.M. Ferrule of 15 mm size inculding tapping the main and. cutting threading and fitting GI pipe and specials including supply of all binding materials such as white lead and teflon tape including making hole in wall and plastering the same with mortar including cost ofortar and also including the cost of crossing the drainluding all labour, T&P complete as per direction of EIC. |
102 | Materials for above old and new connections |
103 | 20mm dia HDPE Pipe (12.5KG/CM2) PN -10 |
104 | 15 mm dia (OD) GI pipe Class- B |
105 | Elbow 15 mm GI for above pipe |
106 | Elbow 20mm (OD) HDPE |
107 | 15 mm dia ISI Marked Ferrule |
108 | 90 mm to 110 mm dia Saddle |
109 | 125 mm to 160 mm dia Saddle |
110 | 200 mm to 250 mm dia Saddle |
111 | Adopter 20 mm OD |
112 | GI Union 20 mm Dia Class B |
113 | 20 mm PP compresion metal insert female thread adopter |
114 | Stop Cock/Tap |
115 | Dismantlingoffollowingtyperoadandstacking of useful material and temporary reinstatement of road with old materials etc. complete. |
116 | B.O.E Road |
117 | Bituminous Road |
118 | CC Road |
119 | Interlocking Road |
120 | Reinstatement of following type road and stacking of useful material and temporary reinstatement of road with old materials etc. complete. |
121 | B.O.E Road |
122 | Bituminous Road |
123 | CC Road |
124 | Interlocking Road |
125 | Excavation of earth in ordinary soil (loam, clay or sand)forlayingofpipelineincludingrefilling anddisposal of surplus earth for different size of pipe lift up to1.5m and50 m away |
126 | E&M Works |
127 | For Zone- 01 (New Tubewell-02 Nos 1300 LPM ) |
128 | Transportation of Rig Machine & its T&P/equipment"s to the site of work including loading & unloading, baricating, erection & dismantling etc. |
129 | Transportation of Air Compressor and its T&P including loading & unloading, erection & dismantling etc. |
130 | Transportation of OP Unit and its T&P including loading & unloading. erection & dismantling etc. |
131 | Transportation of Tubewell assembly including loading & unloading. erection & dismantling etc. |
132 | Drilling of Bore (Including water arrangement) |
133 | Barricading |
134 | Logging of Bore |
135 | Drilling of 600mm dia bore from G.L. to 65 m BGL. |
136 | Drilling of 500mm dia bore from 65 m BGL to 100m BGL. |
137 | Drilling of 500mm dia bore from 101m BGL to 165m BGL. |
138 | Welding and lowering of TW Assembly (including electrodes welding set and generator etc. required for completion of work) as per following : Lowering of 300mm X 200mm dia (tube well assembly in bore hole and shrouding of pea gravel between annular space of bore hole and T.W. assembly from G.L. to 150m BGL. |
139 | Lowering of 300mm dia MSERW 7.1mm thick plain pipe from GL to 60 m BGL. |
140 | Lowering of 200mm die MSERW plain/slotted pipe 7.1mm thick from 60 m BGL to 100m BGL. |
141 | Lowering of 200mm dia MSERW plain/slotted pipe 7.1mm thick from 101m BGL to 150m BGL. |
142 | Supply including loading & unloading of TW assembly of MSERW pipe. |
143 | 300mm dia size MSERW housing pipe 7.1mm thick including with 1 no 300 X 150mm dia M.S reducer 16mm thick, 1 noM.S. well cap 12mm thick ,required M.S. ring 100X12mm thick, M.S. S/I clamp ,T.W. Support (I Section) etc complete in all respect . |
144 | 200mm dia MSERW 7.1mm thick plain /slotted pipe including with required M.S ring 100X12mmthick , 1 noM.S. bail plug , required center guide etc comp in all respect. |
145 | Supply of Pea Gravel Size 1.6mm to 4.80mm of Lalkuwan quarry duly screened , washed and proper stacking at site. |
146 | Development of "Tubewell |
147 | Cutting of T.W. cover by gas cutter, re-welding of T.W. cover by Electric welding after complete development of work. |
148 | By Air compressor of 250 PSI capacity including T&P, labour and material required for completion of work. |
149 | Cutting of T.W. cover by gas cutter, re-welding of T.W. cover by Electric welding after complete development of work. |
150 | By 3 Cusec OP Unit orSutaible capacity including T&P, labour and material required for completion of work. |
151 | Chemical and bacteriological test |
152 | Supply, Inatallation, Commissioning & Testing of Pumping Plant,Chlorinating Plant & Stabilizer - 2 SET (For one pumping plant for Rebore and one for old TW) |
153 | 1300 LPM, 60 m head (or suitable head as per site condition and direction of engineer in charge) 2900rpm submersible clear water pumping plant suitable to operate on 415+ %5 volt, 50 Hz, 3 phase A.C. supply (as per IS 8034-1989) along with Main piping and valves of 150 MM dia 5.4 mm thick M.S. column pipe 30m(or suitable length as per site condition and direction of engineer in charge) ,D/F Pipe 1.0m long 01 No.,D/F Pipe 1.5m long 02 No., D/F Bend 01 No., A/F Tee, 01 No., D/F Reflex Valve 1No., Enlarger / Reducer 1 No, Gauges with air line fittings, Earthing material, tool kit, 2 Ton Chain pully block, SCADA Compatable Chlorinating Systeme, Internal Electrification of pump house,Supply & Installation of sutable sizearmoured cable including lugs itc. Complete works & Painting etc. spare column pipe heavy duty 2no |
154 | Fully automatic ServoVoltage Stabilizer having(40 KVA or suitable capacity as per actual site requirements and as per direction of Engineer in Charge) fully copper winding 3- phase A.C. Supply 50 Hz.input voltage 90-150 V output voltage 360 - 440 V with T/F oil ,power cable & earthing etc.complete in all respect. |
155 | Armoured Cable as per Requirement with laying and Installation |
156 | CE / UL certified Intelligent smart energy meter |
157 | Motor OperatedActuator with Sluice Valve (150mm) |
158 | CE / UL certified Electromagneticflowmeter of size:150mm |
159 | Digital Soft starter (30 KW (or suitable size as per site condition and direction of engineer in charge) |
160 | Auto phase reversal unit with inbuilt time delay & enclosure conforming to IEC: 60947-1 & IEC:60947-b-1) (160 Amps) |
161 | CE / UL certified Hydrostatatic type sub soil water level transmitter |
162 | CE / UL certified Pressure Transmitter |
163 | Complete Cabling for tubewell including all power & control cables of all equipment at pumphouse and OHT |
164 | Fully Automation of T/W through SCADA complete in all respect including mobile based app development and interconnection with MCS and Central Control Room Lucknow |
165 | RequiredEquipment to be installed atOHT Zone-1 |
166 | Motor operated Sluice Valve with Actuator 400 mm Size |
167 | Electromagnetic Flowmeter of400 mm Size |
168 | Cost of Cutting of outlet pipe and installation of flowmeter |
169 | Trial & Run of pumping plant |
170 | Three Month Trial & Run, handing over of T/W, Pumping plant, accessorieswithSodium hypochloride solution, vehicle, watch & ward . |
171 | SUPPLY ,INSTALLATION TESTING & COMMISSIONINGOF SCADA FOR Rebore T/W & OHT |
172 | Automation ofOHTincluding automation of interconnected tubewells, Level sensors etc. |
173 | For Zone- 02(New Tubewell-02 Nos 1200 LPM) |
174 | Transportation of Rig Machine & its T&P/equipment"s to the site of work including loading & unloading, baricating, erection & dismantling etc. |
175 | Transportation of Air Compressor and its T&P including loading & unloading, erection & dismantling etc. |
176 | Transportation of OP Unit and its T&P including loading & unloading. erection & dismantling etc. |
177 | Transportation of Tubewell Assembly including loading & unloading. erection & dismantling etc. |
178 | Drilling of Bore (Including water arrangement) |
179 | Barricading |
180 | Logging of Bore |
181 | Drilling of 600mm dia bore from G.L. to 65 m BGL. |
182 | Drilling of 500mm dia bore from 65 m BGL to 100m BGL. |
183 | Drilling of 500mm dia bore from 101m BGL to 165m BGL. |
184 | Welding and lowering of TW Assembly (including electrodes welding set and generator etc. required for completion of work) as per following : Lowering of 300mm X 200mm dia (tube well assembly in bore hole and shrouding of pea gravel between annular space of bore hole and T.W. assembly from G.L. to 150m BGL. |
185 | Lowering of 300mm dia MSERW 7.1mm thick plain pipe from GL to 60 m BGL. |
186 | Lowering of 200mm die MSERW plain/slotted pipe 7.1mm thick from 60 m BGL to 100m BGL. |
187 | Lowering of 200mm dia MSERW plain/slotted pipe 7.1mm thick from 101m BGL to 150m BGL. |
188 | Supply including loading & unloading of TW assembly of MSERW pipe. |
189 | 300mm dia size MSERW housing pipe 7.1mm thick including with 1 no 300 X 200mm dia M.S reducer 16mm thick, 1 noM.S. well cap 12mm thick ,required M.S. ring 100X12mm thick, M.S. S/I clamp ,T.W. Support (I Section) etc complete in all respect . |
190 | 200mm dia MSERW 7.1mm thick plain /slotted pipe including with required M.S ring 100X12mmthick , 1 noM.S. bail plug , required center guide etc comp in all respect. |
191 | Supply of Pea Gravel Size 1.6mm to 4.80mm of Lalkuwan quarry duly screened , washed and proper stacking at site. |
192 | Development of "Tubewell |
193 | Cutting of T.W. cover by gas cutter, re-welding of T.W. cover by Electric welding after complete development of work. |
194 | By Air compressor of 250 PSI capacity including T&P, labour and material required for completion of work. |
195 | Cutting of T.W. cover by gas cutter, re-welding of T.W. cover by Electric welding after complete development of work. |
196 | By 3 Cusec OP Unit orSutaible capacity including T&P, labour and material required for completion of work. |
197 | Chemical and bacteriological test |
198 | Supply, Inatallation, Commissioning & Testing of Pumping Plant,Chlorinating Plant & Stabilizer - 3 SET (3 no pumping plant for new TW) |
199 | 1200 LPM, 60 m head (or suitable head as per site condition and direction of engineer in charge) 2900rpm submersible clear water pumping plant suitable to operate on 415+ %5 volt, 50 Hz, 3 phase A.C. supply (as per IS 8034-1989) along with Main piping and valves of 150 MM dia 7.1 mm thick M.S. column pipe 30m(or suitable length as per site condition and direction of engineer in charge) ,D/F Pipe 1.0m long 01 No.,D/F Pipe 1.5m long 02 No., D/F Bend 01 No., A/F Tee, 01 No., D/F Reflex Valve 1No., Enlarger / Reducer 1 No, Gauges with air line fittings, Earthing material, tool kit, 2 Ton Chain pully block, SCADA Compatable Chlorinating Systeme, Internal Electrification of pump house,Supply & Installation of sutable sizearmoured cable including lugs itc. Complete works & Painting etc. spare column pipe heavy duty 2no |
200 | Fully automatic ServoVoltage Stabilizer having(40 KVA or suitable capacity as per actual site requirements and as per direction of Engineer in Charge) fully copper winding 3- phase A.C. Supply 50 Hz.input voltage 90-150 V output voltage 360 - 440 V with T/F oil ,power cable & earthing etc.complete in all respect. |
201 | Armoured Cable as per Requirement with laying and Installation |
202 | CE / UL certified Intelligent smart energy meter |
203 | Motor OperatedActuator with Sluice Valve (150mm) |
204 | CE / UL certified Electromagneticflowmeter of size:150mm |
205 | Digital Soft starter(30KW (or suitable size as per site condition and direction of engineer in charge) |
206 | Auto phase reversal unit with inbuilt time delay & enclosure conforming to IEC: 60947-1 & IEC:60947-b-1) (160 Amps) |
207 | CE / UL certified Hydrostatatic type sub soil water level transmitter |
208 | CE / UL certified Pressure Transmitter |
209 | Complete Cabling for tubewell including all power & control cables of all equipment at pumphouse and OHT |
210 | Fully Automation of T/W through SCADA complete in all respect including mobile based app development and interconnection with MCS and Central Control Room Lucknow |
211 | RequiredEquipment to be installed atOHT Zone-2 |
212 | Motor operated Sluice Valve with Actuator 400 mm Size |
213 | Electromagnetic Flowmeter of 400 mm Size |
214 | Cost of Cutting of outlet pipe and installation of flowmeter |
215 | Trial & Run of pumping plant |
216 | Three Month Trial & Run, handing over of T/W, Pumping plant, accessorieswithSodium hypochloride solution, vehicle, watch & ward . |
217 | SUPPLY ,INSTALLATION TESTING & COMMISSIONINGOF SCADA FOR Rebore T/W & OHT |
218 | Automation ofOHTincluding automation of interconnected tubewells, Level sensors etc. |
219 | SUPPLY ,INSTALLATION TESTING & COMMISSIONINGOF SCADA MCS (MASTER CONROL STATION) FOR ZONE- 01 TO 2 |
220 | SCADA MCS (MASTER CONROL STATION) Complete in all respect. |