Tender For Renovation Of Mig Park At Panampilly Nagar Phase Ii, Ernakulam-Kerala

Greater Cochin Development Authority-GCDA has published Tender For Renovation Of Mig Park At Panampilly Nagar Phase Ii. Submission Date for this Tender is 12-02-2024. Gardening Tenders in Ernakulam Kerala. Bidders can get complete Tender details and download the document.




Tender Notice

41963110
Corrigendum : Tender For Renovation Of Mig Park At Panampilly Nagar Phase Ii
Open Tender
Indian
Kerala
Ernakulam
12-02-2024

Tender Details

Renovation Of Mig Park At Panampilly Nagar Phase Ii

Corrigendum Details

Sr No CorrigendumDate Corrignedum CorrigendumType NewSubmissionDate
1 08-Feb-2024 Date of extension corrigendum Date 12-02-2024

Key Value

Document Fees
INR 2625 /-
EMD
INR 50000.0 /-
Tender Value
INR 20.67 Lakhs /-

BOQ Items

Work Name : RENOVATION OF MIG PARK AT PANMABILLY NAGAR Phase - II
Sl. No. Item Description
1SITE CLEARENCE AND COMPOUND WALL
22.32 : Clearing grass and removal of the rubbish up to a distance of 50 m outside the periphery of the area cleared.
314.1.1 : Repairs to plaster of thickness 12 mm to 20 mm in patches of area 2.5 sq meters and under, including cutting the patch in proper shape, raking out joints and preparing and plastering the surface of the walls complete, including disposal of rubbish to the dumping ground within 50 meters lead:With cement mortar 1:4 ( 1 cement : fine sand)
45.1.2 : Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size
55.2.2 : Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. up tot floor five level excluding cost of centering, shuttering, finishing and reinforcement :1:1.5:3( 1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size)
65.9.1 : Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete
75.9.6 : Centering and shuttering including strutting, etc. and removal of form for:Columns, Pillars, Piers, Abutments, Posts and Struts
85.22.6 : Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
95.22A.6 : Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete above plinth level.Thermo - Mechanically Treated bars of grade Fe-500D or more
1013.1.1 : 12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand)
1113.7.1 : 12 mm cement plaster finished with a floating coat of neat cement of mix:1:3 ( 1 cement : 3 fine sand)
1213.16.1 : 6 mm cement plaster of mix:1:3 ( 1 cement : 3 fine sand)
1313.48.1 : Finishing with Deluxe Multi surface paint system for interiors and exteriors using primer as per manufacturers specifications:Two or more coats applied on walls @ 1.25 ltr/10 sqm over and including one coat of special primer applied @ 0.75 ltr /10 sqm
1413.48.3 : Finishing with Deluxe Multi surface paint system for interiors and exteriors using primer as per manufacturers specifications:Painting Steel work with Deluxe Multi Surface Paint to give an even shade.Two or more coat applied @ 0.90 ltr/10 sqm over an under coat of primer applied @ 0.80 ltr/10 sqm of approved brand and manufacture
15od320659/2023_2024 : Dismantling and disposing Merry go round
16od320662/2023_2024 : Engaging labour for petty repairworks -Coolie
17MOUND
182.8.1 : Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil
194.1.8 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
2060.7.1 : DRYRUBBLE MASONRY _ Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site
2151.6.1.3 : Brick Work with common burnt burnt clay F.P.S (non-modular) bricks of class designation 5.0 in foundation and plinth in cement mortar 1:6 (1 cement:6 coarse sand)
2230.2.28 : Preparation of mounds of various size and shape by available excavated / supplied earth in layers not exceeding 20 cm in depth, breaking clods, watering of each layer, dressing etc., lead upto 50 meter and lift upto 1.5 m complete as per direction of Officer-in-charge.
2313.1.1 : 12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand)
2413.45.1 : Finishing walls with textured exterior pint of required shade:New work (Two or more coats applied @ 3.28 ltr/ 10 sqm ) over and including priming coat of exterior primer applied @ 2.20 kg/ 10 sqm
25LANDSCAPE WORK
264.1.8 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
274.6.1 : Providing and fixing at or near ground level precast cement concrete in kerbs, edgings etc. as per approved pattern and setting in position with cement mortar 1:3 (1 cement : 3 coarse sand), including the cost of required centering, shuttering complete.1:1.5:3 ( 1 cement : 1.5 coarse sand (Zone III): 3 graded stone aggregate 20 mm nominal size)
284.7.1 : Providing and fixing up to floor five level precast cement concrete solid block, including hoisting and setting in position with cement mortar 1:3 ( 1 cement : 3 coarse sand), cost of required centering, shuttering complete:1:1.5:3 ( 1 cement : 1.5 coarse sand (Zone III): 3 graded stone aggregate 20 mm nominal size)
29od320636/2023_2024 : 3 mm thick factory made glass fiber<br>reinforced plastic paneling on stepping stone
3011.3.1 : Cement concrete flooring 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate)finished with a floating coat of neat cement, including cement slurry, but excluding the cost of nosing of steps etc. complete.40 mm thick with 20 mm nominal size stone aggregate
312.8.1 : Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil
3260.7.1 : DRYRUBBLE MASONRY _ Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site
337.1.1 : Random rubble masonry with hard stone in foundation and plinth including levelling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate 20 mm nominal size) up to plinth level with:Cement mortar 1:6 (1 cement : 6 coarse sand)
346.1.1 : Brick work with common burnt clay F.P.S (non modular) bricks of class designation 7.5 in foundation and plinth in:Cement mortar 1:4 (1 cement : 4 coarse sand)
355.3 : Reinforced cement concrete work in beams, suspended floors, roofs, having slope up to 150 landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases up to floor five level excluding the cost of centering, shuttering, finishing and reinforcement, with1:1.5:3 (1 cement : 1.5 coarse sand (Zone III) : 3 graded stone aggregate 20 mm nominal size).
365.9.3 : Centering and shuttering including strutting, etc. and removal of form for:Suspended floors, roofs, landings, balconies and access platform
375.22A.6 : Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete above plinth level.Thermo - Mechanically Treated bars of grade Fe-500D or more
3813.7.1 : 12 mm cement plaster finished with a floating coat of neat cement of mix:1:3 ( 1 cement : 3 fine sand)
3913.1.1 : 12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand)
4013.48.1 : Finishing with Deluxe Multi surface paint system for interiors and exteriors using primer as per manufacturers specifications:Two or more coats applied on walls @ 1.25 ltr/10 sqm over and including one coat of special primer applied @ 0.75 ltr /10 sqm
4116.91.1 : Providing and laying factory made chamfered edge Cement Concrete paver blocks in footpath, parks, lawns, drive ways or light traffic parking etc, of required strength, thickness & size/ shape, made by table vibratory method using PU mould, laid in required colour & pattern over 50mm thick compacted bed of sand, compacting and proper embedding/laying of inter locking paver blocks into the sand bedding layer through vibratory compaction by using plate vibrator, filling the joints with sand and cutting of paver blocks as per required size and pattern, finishing and sweeping extra sand. complete all as per direction of Engineer-in-Charge.60mm thick cement concrete paver block of M-35 grade with approved colour, design & pattern.
4213.52.2 : Finishing with Epoxy paint (two or more coats) at all locations prepared and applied as per manufacturer"s specifications including appropriate priming coat, preparation of surface, etc. complete.On concrete work
43od320655/2023_2024 : Providing and laying Tandur stone in footpath, parks, lawns etc, of required strength, thickness & size/ shape, laid in required colour & pattern over 50mm thick compacted bed of sand, compacting and proper embedding/laying of Bangalore stone into the sand bedding layer, filling the joints with sand and cutting of Bangalore stone as per required size and pattern, finishing and sweeping extra sand. complete all as per direction of Engineer-in-Charge. (Modified DAR 16.91.1)
44od320656/2023_2024 : Rubble stone pitching 22.5 cm thick laid in courses and required profile with hammer dressed stones having no side less than 15 cm, with minimum depth of 20 cm including preparing the bedding surface etc. all complete ( Payment for stone to be made separately)
45od320657/2023_2024 : od340343/2022_2023 :Supplying, Providing & placing of park seating benches with cast iron frame with<br>wooden seating and of size 60" L, 16"W, 20" H at site with primer and required finishes of paint including<br>loading, unloading, carriage etc.and as per direction of officer in charge.<br>Fixing material , in a base of M20 plain cement concrete, Reference ID,DAR 4.1.3.
46od320658/2023_2024 : Supplying and fixingready made waste bins at necessary location
47PLAY EQUIPMENTS AND GYM EQUIPMENTS
48od320635/2023_2024 : Taking out and re-fixing climber play equipment
49od320642/2023_2024 : Supplying SINGLE CROSS TRAINER
50od320643/2023_2024 : Supplying SEAT TWISTER
51PLUMBING
5218.51.1 : Providing and fixing C.P. brass long body bib cock of approved quality conforming to IS standards and weighing not less than 690 gms.15 mm nominal bore
5318.7.2 : Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot & cold water supply, including all CPVC plain & brass threaded fittings including fixing the pipe with clamps at 1.00 m spacing.This includes jointing of pipes & fittings with one step CPVC solvent cement and testing of joints complete as per direction of Engineer -in-Charge.Internal work - Exposed on wall20 mm nominal outer dia pipes
5418.9.2 : Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot & cold water supply including all CPVC plain & brass threaded fittings.This includes jointing of pipes & fittings with one step CPVC solvent cement, trenching , refilling & testing of joints complete as per direction of Engineer- in-Charge.External work20 mm nominal outer dia pipes
5518.9.3 : Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot & cold water supply including all CPVC plain & brass threaded fittings.This includes jointing of pipes & fittings with one step CPVC solvent cement, trenching , refilling & testing of joints complete as per direction of Engineer- in-Charge.External work25 mm nominal outer dia pipes
5618.17.1A : Providing and fixing gun metal gate valve with C.I. wheel of approved quality (screwed end) :20 mm nominal bore
5718.19.2.1 : Providing and fixing gun metal non-return valve of approved quality (screwed end):32 mm nominal boreHorizontal
58od320653/2023_2024 : Supply, installation, testing and commissioning of high pressure float valve with bronze construction, brass floats,with screwed end fittings with all supports andfixings all as specified and as shown on drawings and complying to relevant standards<br>25 mm Float Valve
59od320654/2023_2024 : Providing and placing UG tank polyethylene water storage tank :ISI 12701 marked, with cover and suitable locking arrangement and making necessary holes for inlet, outlet and overflow pipes but without fittings and the base support for tank. od 18.48
6018.61.4 : Providing and fixing C.I dirt box strainer for bulk type water meter with nuts, bolts, rubber insertions etc. complete conforming to IS : 2373 :20 mm dia
6118.37.1 : Constructing masonry chamber 60x45x50 cm inside, in brick work in cement mortar 1:4 ( 1 cement : 4 coarse sand) for water meter complete with C.I double flap surface box 400x200x200 mm ( inside ) with locking arrangement and RCC top slab 1:2:4 mix ( 1 cement : 2 coarse sand : 4 grades stone aggregate 20 nominal size), i/c necessary excavation, foundation concrete 1:5:10 ( 1 cement : 5fine sand : 10 graded stone aggregate 40mm nominal size) and inside plastering with cement mortar 1:3 ( 1 cement : 3 coarse sand) 12 mm thick, finished with a floating coat of neat cement complete as per standard design:With common burnt clay F.P.S. ( non modular ) bricks of class designation 7.5
622.6.1 : Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil
634.1.11 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:5:10 (1 cement : 5 fine sand : 10 graded stone aggregate 40 mm nominal size)
646.1.1 : Brick work with common burnt clay F.P.S (non modular) bricks of class designation 7.5 in foundation and plinth in:Cement mortar 1:4 (1 cement : 4 coarse sand)
655.1.2 : Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size
665.9.3 : Centering and shuttering including strutting, etc. and removal of form for:Suspended floors, roofs, landings, balconies and access platform
675.22.6 : Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
68od320660/2023_2024 : Supply and fixing of CImanhole frame and cover of lockable type ( Double Sealed ) over openings of under ground sump, overhead tank, rain water Sump, soak pits.<br>600X600 mm size - Heavy Duty cover ( 2.5 ~10 Tonload bearing )
69od320661/2023_2024 : Supply, installation, testing & commissioning of PRESSURE PUMP 20 LPM @ 15m HEAD, with control panel,automatic changover switch,with all necessaryvalves, flexible connections, pressure gauges, strainers, supports, fixings and fittingselectrical/ control panels, power and control cabling , cable trays, automatic level controller, etc.as specified and as shown on drawings and complying to relevant standards.
70GARDENING
71od320631/2023_2024 : Planting trees byDigging pit in all kinds of soil and refilling the same with a thorough mix of good quality fertile soil, river sand, dried cow dung manure and leaf mould mixed in the ratio of 1:1:1:1, removal of rubbish and surplus earth if any, including lead, lift etc. as directed by the engineer in charge and planting trees supplied with roots covered with appropriate natural containers from the source of availability including all conveyance, transported without any damage to the root pods, covering the stem with necessary hay etc., caring and protecting the plants transported and unloaded at site till planting in pits of size 120 cm diameter, and 120 cm deep, ARECA PALM 1.80 M HEIGHT . Appropriate Length of softwood props shall be provided as supports for the plants as directed. The trees have to be maintained for a period of 3 months after the entire planting of trees is completed. The Rate shall include necessary labour, supply of materials, safe keep of plants, cost of conveyance, removal of rubbish and surplus earth etc. Complete.
72od320633/2023_2024 : Planting PHILADENDRON SELLOUM PLANTS by excavating planting bed 45 cm deepat specified area shown in the planting plans and refilling the same with a thorough mix of good quality fertile soil, river sand, dried cow dung manure and leaf mould mixed in the ratio of 1:1:1:1, removal of rubbish and surplus earth if any, including lead, lift etc. as directed by the engineer in charge and supplying good healthy cuttings of groundcovers free of all pests and deceases from the source of availability including all conveyance, transported without any damage to the cuttings, covering, caring and protecting the groundcovers transported and unloaded at site. The Groundcovers have to be maintained for a period of 3 months after the entire planting is completed. The Rate shall include necessary labour, supply of materials, safe keep of Groundcovers, cost of conveyance, removal of rubbish and surplus earth etc. Complete.
73od320634/2023_2024 : Planting DIANELLA TASMANICA PLANTS by excavating planting bed 45 cm deepat specified area shown in the planting plans and refilling the same with a thorough mix of good quality fertile soil, river sand, dried cow dung manure and leaf mould mixed in the ratio of 1:1:1:1, removal of rubbish and surplus earth if any, including lead, lift etc. as directed by the engineer in charge and supplying good healthy cuttings of groundcovers free of all pests and deceases from the source of availability including all conveyance, transported without any damage to the cuttings, covering, caring and protecting the groundcovers transported and unloaded at site. The Groundcovers have to be maintained for a period of 3 months after the entire planting is completed. The Rate shall include necessary labour, supply of materials, safe keep of Groundcovers, cost of conveyance, removal of rubbish and surplus earth etc. Complete.
74od320637/2023_2024 : Planting ALPININA PLANTS by excavating planting bed 45 cm deepat specified area shown in the planting plans and refilling the same with a thorough mix of good quality fertile soil, river sand, dried cow dung manure and leaf mould mixed in the ratio of 1:1:1:1, removal of rubbish and surplus earth if any, including lead, lift etc. as directed by the engineer in charge and supplying good healthy cuttings of groundcovers free of all pests and deceases from the source of availability including all conveyance, transported without any damage to the cuttings, covering, caring and protecting the groundcovers transported and unloaded at site. The Groundcovers have to be maintained for a period of 3 months after the entire planting is completed. The Rate shall include necessary labour, supply of materials, safe keep of Groundcovers, cost of conveyance, removal of rubbish and surplus earth etc. Complete.
75od320638/2023_2024 : Planting trees byDigging pit in all kinds of soil and refilling the same with a thorough mix of good quality fertile soil, river sand, dried cow dung manure and leaf mould mixed in the ratio of 1:1:1:1, removal of rubbish and surplus earth if any, including lead, lift etc. as directed by the engineer in charge and planting trees supplied with roots covered with appropriate natural containers from the source of availability including all conveyance, transported without any damage to the root pods, covering the stem with necessary hay etc., caring and protecting the plants transported and unloaded at site till planting in pits of size 120 cm diameter, and 120 cm deep, PLUMARIA OBTUSA- 2.5 M . Appropriate Length of softwood props shall be provided as supports for the plants as directed. The trees have to be maintained for a period of 3 months after the entire planting of trees is completed. The Rate shall include necessary labour, supply of materials, safe keep of plants, cost of conveyance, removal of rubbish and surplus earth etc. Complete.
76od320639/2023_2024 : Planting EUGINIA PLANTS by excavating planting bed 45 cm deep at specified area shown in the planting plans and refilling the same with a thorough mix of good quality fertile soil, river sand, dried cow dung manure and leaf mould mixed in the ratio of 1:1:1:1, removal of rubbish and surplus earth if any, including lead, lift etc. as directed by the engineer in charge and supplying good healthy cuttings of groundcovers free of all pests and deceases from the source of availability including all conveyance, transported without any damage to the cuttings, covering, caring and protecting the groundcovers transported and unloaded at site. The Groundcovers have to be maintained for a period of 3 months after the entire planting is completed. The Rate shall include necessary labour, supply of materials, safe keep of Groundcovers, cost of conveyance, removal of rubbish and surplus earth etc. Complete.
77od320641/2023_2024 : Planting BIRD OF PARADICE PLANTS by excavating planting bed 45 cm deepat specified area shown in the planting plans and refilling the same with a thorough mix of good quality fertile soil, river sand, dried cow dung manure and leaf mould mixed in the ratio of 1:1:1:1, removal of rubbish and surplus earth if any, including lead, lift etc. as directed by the engineer in charge and supplying good healthy cuttings of groundcovers free of all pests and deceases from the source of availability including all conveyance, transported without any damage to the cuttings, covering, caring and protecting the groundcovers transported and unloaded at site. The Groundcovers have to be maintained for a period of 3 months after the entire planting is completed. The Rate shall include necessary labour, supply of materials, safe keep of Groundcovers, cost of conveyance, removal of rubbish and surplus earth etc. Complete.
78od320644/2023_2024 : Planting BROAD LEAF LADY PALM by excavating planting bed 45 cm deepat specified area shown in the planting plans and refilling the same with a thorough mix of good quality fertile soil, river sand, dried cow dung manure and leaf mould mixed in the ratio of 1:1:1:1, removal of rubbish and surplus earth if any, including lead, lift etc. as directed by the engineer in charge and supplying good healthy cuttings of groundcovers free of all pests and deceases from the source of availability including all conveyance, transported without any damage to the cuttings, covering, caring and protecting the groundcovers transported and unloaded at site. The Groundcovers have to be maintained for a period of 3 months after the entire planting is completed. The Rate shall include necessary labour, supply of materials, safe keep of Groundcovers, cost of conveyance, removal of rubbish and surplus earth etc. Complete.
79od320645/2023_2024 : Planting GARDENIA SHRUBS by excavating planting bed 45 cm deepat specified area shown in the planting plans and refilling the same with a thorough mix of good quality fertile soil, river sand, dried cow dung manure and leaf mould mixed in the ratio of 1:1:1:1, removal of rubbish and surplus earth if any, including lead, lift etc. as directed by the engineer in charge and supplying good healthy cuttings of groundcovers free of all pests and deceases from the source of availability including all conveyance, transported without any damage to the cuttings, covering, caring and protecting the groundcovers transported and unloaded at site. The Groundcovers have to be maintained for a period of 3 months after the entire planting is completed. The Rate shall include necessary labour, supply of materials, safe keep of Groundcovers, cost of conveyance, removal of rubbish and surplus earth etc. Complete.
80od320647/2023_2024 : Planting CALATHEA LUTAE PLANTS by excavating planting bed 45 cm deepat specified area shown in the planting plans and refilling the same with a thorough mix of good quality fertile soil, river sand, dried cow dung manure and leaf mould mixed in the ratio of 1:1:1:1, removal of rubbish and surplus earth if any, including lead, lift etc. as directed by the engineer in charge and supplying good healthy cuttings of groundcovers free of all pests and deceases from the source of availability including all conveyance, transported without any damage to the cuttings, covering, caring and protecting the groundcovers transported and unloaded at site. The Groundcovers have to be maintained for a period of 3 months after the entire planting is completed. The Rate shall include necessary labour, supply of materials, safe keep of Groundcovers, cost of conveyance, removal of rubbish and surplus earth etc. Complete.
81od320648/2023_2024 : Planting trees byDigging pit in all kinds of soil and refilling the same with a thorough mix of good quality fertile soil, river sand, dried cow dung manure and leaf mould mixed in the ratio of 1:1:1:1, removal of rubbish and surplus earth if any, including lead, lift etc. as directed by the engineer in charge and planting trees supplied with roots covered with appropriate natural containers from the source of availability including all conveyance, transported without any damage to the root pods, covering the stem with necessary hay etc., caring and protecting the plants transported and unloaded at site till planting in pits of size 120 cm diameter, and 120 cm deep, TERMINALIA VERIGATED- 1.8 M . Appropriate Length of softwood props shall be provided as supports for the plants as directed. The trees have to be maintained for a period of 3 months after the entire planting of trees is completed. The Rate shall include necessary labour, supply of materials, safe keep of plants, cost of conveyance, removal of rubbish and surplus earth etc. Complete.
82od320650/2023_2024 : Planting FICUS PANDA PLANTS by excavating planting bed 45 cm deepat specified area shown in the planting plans and refilling the same with a thorough mix of good quality fertile soil, river sand, dried cow dung manure and leaf mould mixed in the ratio of 1:1:1:1, removal of rubbish and surplus earth if any, including lead, lift etc. as directed by the engineer in charge and supplying good healthy cuttings of groundcovers free of all pests and deceases from the source of availability including all conveyance, transported without any damage to the cuttings, covering, caring and protecting the groundcovers transported and unloaded at site. The Groundcovers have to be maintained for a period of 3 months after the entire planting is completed. The Rate shall include necessary labour, supply of materials, safe keep of Groundcovers, cost of conveyance, removal of rubbish and surplus earth etc. Complete.
83od320651/2023_2024 : Planting HELICONIA PSITTACORUM PLANTSby excavating planting bed 45 cm deepat specified area shown in the planting plans and refilling the same with a thorough mix of good quality fertile soil, river sand, dried cow dung manure and leaf mould mixed in the ratio of 1:1:1:1, removal of rubbish and surplus earth if any, including lead, lift etc. as directed by the engineer in charge and supplying good healthy cuttings of groundcovers free of all pests and deceases from the source of availability including all conveyance, transported without any damage to the cuttings, covering, caring and protecting the groundcovers transported and unloaded at site. The Groundcovers have to be maintained for a period of 3 months after the entire planting is completed. The Rate shall include necessary labour, supply of materials, safe keep of Groundcovers, cost of conveyance, removal of rubbish and surplus earth etc. Complete.
84od320652/2023_2024 : Planting Buffalo grassby excavating planting bed 30 cm deepat specified area shown in the planting plans and preparing the same with thorough mix of good quality fertile soil, river sand, dried cow dung manure and leaf mould mixed in the ratio of 1:1:1:1, removal of rubbish and surplus earth if any, including lead, lift etc. as directed by the engineer in charge and supplying and planting Grass Buffalo grass sod, machine cut at a uniform soil thickness of 15 mm, plus or minus 6 mm, at the time of cutting, measurement for thickness shall exclude top growth and thatch.Individual pieces of Buffalo grass sod shall be cut to the supplier’s standard width and length. Maximum allowable deviation from standard widths and lengths shall be plus or minus 15 mm on width and plus or minus five percent on length. Broken pads and torn or uneven ends will not be acceptable. Standard size sections of Buffalo grass sod shall be strong enough that it can be picked up and handled without damage. Buffalo grass sod shall not be harvested or transplanted when its moisture content (excessively dry or wet) may adversely affect its survival. Before harvesting, the turfgrass shall be mowed uniformly at a height of 25 to 60 mm on winter season grasses and 20 to 40 mm on summer season. Grass turfgrass sod should be transported unloaded at site with care and protection and without any damage. The planted Grass turfgrass have to be maintained for a period of 3 months after the entire planting is completed. The Rate shall include necessary labour, supply of materials, safe keep of Grass , cost of conveyance, removal of rubbish and surplus earth etc. Complete.
8550.2.26.1 : Filling with contractor own earth (excluding rock) in open areas in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m as per direction of site Engineer-in-charge.
Disclaimer :
We takes all possible care for accurate & authentic tender information, however Users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender.
Tell us about your Product / Services,
We will Find Tenders for you

Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy

For Tender Information Services Visit : TenderDetail