| 1 | Earth work excavation in all classes of soils such as hard stiff clay, stiff black cotton, hard red earth, shales, murram, ordinary earth, earth mix with 50% fair sized boulders etc., with initial lead and lifts including laying, spreading, leveling, sectioning breaking clods etc., includingall incidental charges etc., complete as per standard specification . for FoundationsSS 20B TNDSS NO. 23 &24 V, VI (S2) VI 9 |
| 2 | Cement concrete of mix 1:4:8 (One cement four sand and eight aggregates) using 40mm gauge hard broken including cost conveyance of all materials to site including labour charges, transporting and placing in position including shoring, strutting forming protective bunds, cofferdams bailing out of water labour for mixing compacting, finishing and curing, working at depths, tools and plants and incidental charges such as sheeting, shoring and bracing and their subsequent removal etc., complete as per standard specification.TNDSS NO.28 V,VI S25 |
| 3 | Supplying & Erecting of steel centering for sides & soffiots including necessary supports & strutting upto 3.29m height for plane surfaces in all floors with all cross bracings using mild steel sheets of size 90 x 60cm & 10 gauge stiffened, welded with steel angle of size 25 x 25 x 3mm for boarding laid over silver oak joists(Country wood) of size 10 x 6.5cm spaced @ about 90cm c/c and supported by casurina props of 10 - 13cm dia. spaced @ 75cm c/c etc., complete complying with standard specifications and as directed by the departmental officers. Rate for 10m2.for the following items.(RCC floor slab, roof slab, Rectangular/ square, Tee/ Ell beams, Lintels, staircase waist slabs, Landing slabs, Landing beam, Portico beam etc., ).TNDSS NO.86 K, 86 A a)WithoutStrutting : |
| 4 | Plain Cement Concrete 1:2:4 Mix (one part cement, two part sand and four part of aggrigate) using 20mm size ISS HBG metal machine crushed from approved quarry including cost and conveyance of all materials to site, loading and unloading charges and labour charges for mixing, laying and curing etc. complete. Complying with std. specifications. |
| 5 | Providing and laying, spreading and compacting graded stone aggregates to Wet Mix Macadam 250mm thick specification including premixing the materials with water at OMC in mechnanical mix plant carriage of mixed material by tipper to site laying in uniform layers with pavers in Sub Base/ Base course on well prepared surface and compacting with vibratory roller to acheive the desired density including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc.,complete as per clause 406 of MORTH |
| 6 | Supplying and laying Precast Designer Paver Block confirming to IS 1568-2006 specification manufacturing and laying standard of M40 grade 83mm thick (table clauses 5 and 9.14) suitable for bus terminals ,industrial complexes, road on expensive soils etc., including the cost of paver block of size 225mm x 12.50 mm x 83mm and conveyance of materials to work site mentioned in the tender schedule cost of loading and unloading handling during over Stone dust of 100mm thick (excluding the cost of M- Sand) conveyance paver block cutter to site and hire charges of vibrators and block cutter operator and labour for leveling the M- Sand to paver block etc., complete ISI 15658-2006. |