Public Works Department-PWD has published General-Arakkulam Akg Padi Bridge-Investigation Work For The Construction Of Akg Padi Bridge In Akg_Padi-Moonnungavayal Panchayath Road Inarakkulamgp Of Idukki Lac-General Civil Work. Submission Date for this Tender is 31-01-2024. Bridge Work Tenders in Idukki Kerala. Bidders can get complete Tender details and download the document.
Sl. No. | Item Description |
1 | Investigation |
2 | 56.1.a:Mobilization including transportation of all necessary plant and equipment"s and materials of boring, field testing and sampling and demobilization after completing the work - For machine boring |
3 | 56.2.a:Setting up boring at each bore hole locations including carrying all necessary plant, equipment and materials of boring and field tests and collection of samples at each bore hole location - For machine boring. |
4 | 56.3.a.1:Boring with rotary power drilling equipment"s in - all types of soil having N value less than 50 excluding hard rock, soft rock or medium rock for strata upto 10m including conducting necessary S.P.T and recovery of undisturbed soil samples at 5m intervals - For ordinary soil. |
5 | 56.3.a.2:Boring with rotary power drilling equipment"s in - all types of soil having N value less than 50 excluding hard rock, soft rock or medium rock for strata upto 10m including conducting necessary S.P.T and recovery of undisturbed soil samples at 5m intervals - For under water. |
6 | 56.5.a:Boring through all classes of rock excluding hard rocks having N value greater than 50 using tungsten carbide drilling bit - In land |
7 | 56.5.b:Boring through all classes of rock excluding hard rocks having N value greater than 50 using tungsten carbide drilling bit - In Water |
8 | 56.4:Boring through all type of hard rock or similar refusal strata of N value greater than 50 using diamond core drilling bit for in land under water and banks of river. |
9 | 56.6:Recovering undisturbed soil samples using thin tube sampler of 75mm.to 100mm length internal dia 500mm length conforming to relevant IS Code at any required depth including clearing the bore hole etc complete. |
10 | 56.7:Conducting standard penetration test in bore hole at any depth. |
11 | 56.8:Recovering disturbed samples and preserving the same in air tight sample containers including waxing labelling packing storing including cost of containers as per IS Code. |
12 | 56.9.1:Erecting platform over 2 nos of 2nd Class Boat using Mango wood planks of not less than 30 mm thick, Mango wood joists of 100 mm x 70 mm at 60 cm intervals including labour and hire of all materials and dismantling the platform after completion of work etc complete. excluding hire of boats (A Platform of minimum size 6.00 m x 5.00 m will be required) |
13 | 56.10:Hire charges for providing 2 nos of 2nd Class boat with boatman for erecting the platform over which the boring plant is to be erected, and 1 no of 2nd Class boat with 1 boatman for conveying the departmental staff and labour engaged from the banks to platform and back etc. |
14 | 56.12.c:Total station surveying and preparation of site plan - In hilly terrain |
15 | 56.13:Providing access to the site clearing site and making good for surveying in order to provide clear line of site devoid of any hindrance due to vegetation etc. and clearing areas for station points (This item is applicable only for sites without access such as in case of new road formation, bridge and building sites at in accessible locations). |
16 | 56.14.a:Cross sectional details - River. |
17 | 56.15.a:Hydraulic Velocity Calculation - River. |
18 | 56.11.a:Compilation of all field data with recommendation for a suitable foundation after conducting necessary lab test (report in triplicate) - Machine boring for 5 bore holes. |
19 | Other tests |
20 | OD78509/2021-2022:Testing charges for CBR Test of soil samples collected from the site in the laboratory including the charges of labour engaged for conducting the test in the lab etc including the collection of subgrade soil samples carefully by excavating pit for a laboratory test and refilling back and compacting the excavated pit to lines and levels with excavated materials as directed by the departmental officers at site. |
Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy