Military Engineer Services-MES has published Tender For Manning And Operation Including Repair And Maint Of 10 Mw Capacity Captive Power Plant (Cpp) At Naval Base Karwar Under Ge (Sb) Karwar. Submission Date for this Tender is 14-02-2024. Electrification Work Tenders in vasco Goa. Bidders can get complete Tender details and download the document.




Tender Notice

41690732
Corrigendum : Tender For Manning And Operation Including Repair And Maint Of 10 Mw Capacity Captive Power Plant (Cpp) At Naval Base Karwar Under Ge (Sb) Karwar
Open Tender
Indian
Goa
vasco
14-02-2024

Tender Details

Manning And Operation Including Repair And Maint Of 10 Mw Capacity Captive Power Plant ( Cpp ) At Naval Base Karwar Under Ge ( Sb ) Karwar

Corrigendum Details

Sr No CorrigendumDate Corrignedum CorrigendumType NewSubmissionDate
1 02-Feb-2024 CORRIGENDUM NO 1 Other 07-02-2024
2 07-Feb-2024 Bid Auto Extn Corrigendum Bid Auto Extn Corrigendum 14-02-2024

Key Value

Document Fees
INR 1000 /-
EMD
INR 201840.0 /-
Tender Value
INR 1.26 Crore /-

BOQ Items

NAME OF WORK:MANNING AND OPERATION INCLUDING REPAIR AND MAINT OF 10 MW CAPACITY CAPTIVE POWER PLANT (CPP) AT NAVAL BASE KARWAR UNDER GE (SB) KARWAR.
Sl. No. Item Description
1Manning & Operation of 10.0 MW (4 X 2.5 MW) capacity 11 KV Captive Power Plant (CPP) installed at NSRY complex round the clock in three shifts (for three 0600 hrs to 1400 hrs, 1400 to 2200 hrs and 2200 hrs to 0600 hrs) for all days in a week including weekly, monthly, quaterly routine checks completeall as specified in maintenance manual & or directed by Engr in charge. The installation comprise of the following equipments :-
2a) D.G Set of capacity 2500 KW 11KV with compressed air starting system comprising of structural chimmney exhaust silencer assembly, air filter system, plate type heat exchanger, batteries with charger, AMF Panel & complete accessories -04 Sets
3Engine Make :- KOEL, Type 9 PA 61 - 280 With rated BHP 3600
4Alternator Make :- BHEL Frame G62592 ofCapacity 3125 KVA
5b) DG Set of capacity 62.5 KVA415 Volts with exhaust silencer assembly batteries with charger AMF panel & complete accessories - 01 No
6Engine Make :- Greaves Type 3YDC MK - III
7Alternator Make :- STMPFORD Type UC 22 GofCapacity 62.5 KVA
8c) Lube Oil priming pump Make :- Crompton Greaves 5.5 KW/7.5HP3Phase1440 RPM -03 No
9d) Lube Oil priming pump Make :- Prime 5.5 KW / 7.5 HP 3 Phase 1440 RPM - 01 No
10e) HT water pump (Pre heating module) Make :- Kirloskar BrothersLtd 2.2 KW / 3 HP 3 Phase 2840 RPM - 04 Nos
11f) LT Water pump Make :- Kirloskar Brother Ltd 7.5 KW / 10 HP 3 phase 2900 RPM - 04 Nos
12g) Cooling tower fan motor Make :- Laxmi hydraulics Pvt. Ltd. 5.5 KW / 7.5 HP 3 Phase 720 RPM with cooling tower - 04 Nos
13h) Air compressor with electric motor Make :- Bharat bijaleeLtd. 9.3 KW / 12.5 HP 3Phase 1450 RPM - 01 No
14j) Drip tank with transfer pump Make : BharatBijlee Ltd. 1.1 KW / 1.5 HP3 Phase 1415 RPM with tank - 01 No
15k) Chemicalmixing pump Make :- Kirloskar brothers Ltd. 2.2 KW / 3 HP 3 Phase 2840 RPM with tank - 01 No
16L) Fuel Oil centrifuge pump Make :-Crompton GreavesLtd3KW / 4 HP 3 Phase 2865 RPM - 02 Nos
17m) Seperator feed pump Make :- Crompton greaves Ltd 0.37 KW / 0.5 HP 3 Phase 2820 RPM -01 No.
18n) Fuel unloading pump Make :- Bharat bijaiee Ltd. 3.7 KW / 5 HP 3 Phase 1430 RPM with strainer -02 Nos
19o) Fuel transfer pump Make :- Bharat bijalee Ltd, 1.1 KW / 1.5 HP 3Phase 1415RPMwith tank -02 Nos
20p) Raw Water pump Make :- Kirloskar brothers Ltd. 3.7 KW / 5 HP 3 Phase 2870 RPM with water softening plant & storage tanks - 02 Nos
21q) Axial flow fan motor Make :- Crompton Graves Ltd. 7.5 KW / 10 HP 3 Phase 1430 RPM - 06 Nos
22r) Generator control panel with measuring instrumentscontrol relays&switch gears - 04 Nos
23s) AVR Exciting panel for D.G sets - 04 Nos
24t) D.G Set synchronising panel with auto / manual synchronising with metering & protection devices -01 No
25u) Storage tanks : Vertical Fuel storage tank - 60 KL capacity each - 02 Nos, day tank 600 ltrs capacity each - 04 Nos, HSD clean oil tank 4.5 KL -01 No
26v) Air conditioning system comprising of 2 Nos air conditioning units with one set fine filters ducting with supply air diffusers including electrical starters cabling etc
27Notefor item No.1 above :-
28a) Contractor has to employ minimum following staff for Manning and operation of the plant :-
29i) One No MCM / Supervisor having minimum qualification Diploma in Mechanical / Electrical Engineering from recognized institute with adequate experience in one shift of 8 hrs (Total - 01 Nos per day)
30ii) OneNo. FGM Highly skilled / operator having minimum qualificationITI in Fitter / Electricianfrom recognized institutewith adequate experience in each shift of 8 hrs (Total 03 Nos Per day)
31iii) One No. FGM skilled / assistant operator having minimum ITI qualification in Electrician / Mechanic trade from Govt. recognized institute with adequate experience in each shift of 8 hrs (Total 03 Nos Per day)
32iv) One No Electrician highly skilled / operator having minimum qualification Diploma in Electrical Engineering from recognized institute with adequate experience in one shift of 8 hrs(Total 01 Nos Per day)
33v) One No Mate / helper minimum 10 th pass with adequate experience in two shift of 8 hrs (Total - 02 Nos per day)
34b) Unit rates quoted above shall be deemed to be included the cost of stationery & communication and safety gears / clothing for operating staff.
35c) The contractor has to maintain various records as mentioned in particular specifications and as directed by EIC in binded book / registers
36d) Fuel (Diesel) and water for CPP will be issued by the department under schedule B items in free of cost However proper record of fuel consumption will be maintained in binded book by the contractor and put up to the Engineer - in - Charge weekly.
37e) The Contractor shall pay the wages to the opreators/helpers (as applicable) through e payment i.e. Aadhar linked bank accounts (credit to their bank account). GE shall ensure that e-payment made to the opreator / helper and their wages shall not be less than minimum wages fixedd by state Govt or Central Govt whichever is more. Monthly e banking statement shall be furnished by contractor to the GE and the same shall be kept in record duly verified.
38f) It is responsibility of contractor to deposit the employees provident fund (EPF) to the connected authority as per the prevealing scales as laid down by Ministry of labour for all opreator/helper(as applicable) and necessary proof to this regard shall be submitted to the Engineer-in- incharge for verification and record. The quoted rate shall be deemed to be included of above provisions. In case contractor fails to produce the proof of EPF, shall be liable for action as deemed fit. Decision of GE in this regard shall be final and binding.
39g) The contractors shall maintain all the registers under various labour law rules 2017 and shall be produced to GE and as well as officers detailed by labour department.
40h) Therate quoted shall deemed to be inclusive of safety gear and required tools for minor maintenaince. In case of failure to provide tools kit and safety kits (gum boots-02pairs, hand glooves) penalty of RS.3000/- per person per month will be recovered and levied.
41i) The contractor shall provide 02 uniforms to each opreator and design of uniform shall be got approved. In case of failure, a penalty of RS.1200/- per month per uniform and will be levied and recovered from the dues
42j) In case of failure due to absence of opreative staff, the contractor shall be liable to pay compensation at twice the cost of a day"s manning and opreation derived from pro rata rate of Schedule "A" quoted rates.
43k) The contractor shall be responsible formaintainingthe completearea (i.e. inside boundary) such as building , lawn, garden, out side bus bay yard , hard standing , footpath etcin neat and clean position . All necessaryT&P for cutting /cleaning of grass and vegetationwill be arranged by contractor without any extra cost.
44M& L forservicing of Turbocharger comprising of following works & Dynamic balancing of the Rotor Shaft tobe carried out by qualified team of engineers from Manufacturers Authorised Repair Workshop:-
45i) Dismantlingthe turbochargerfrom the installed position& removing , loading, transporting the turbochargercartridge to OEM authorised& approved workshop for dynamic balancing.
46ii) Mechanical cleaning , assesmment & working condition evaluationof the turbocharger
47iii) Complete overhaul & servicing of the turbocharger
48iv) Dismantling of the Cartridge , Mechanical cleaning of the rotorandAssessment of therotor shaft& condition evaluation
49v)Replacement of Standard Overhaul Sparepartsas required at site and directed by GE.
50vi) Dynamic balancing of the rotor shaft & balancing of the rotor complete
51vii) Re Assemblingthe complete cartridge & transporting back to the site
52viii)Re Assemblingthe complete turbocharger with the cartridge, re- installing & commisioning of turbocharger assembly with the DG sets complete as per OEM Standards
53ix) Documentation & submission of the service & test reports as per prescribed format.
54M&L for Complete overhauling/servicing of FRP cooling tower, removal of complete scales, dirt etc. by using chemicals, cleaning the sump louvers, PVC fins, fan assembly, replacing of spray nozzels with connected pipe, renewal of nuts and bolts, leak arresting of the FRP tank, replacing of PVC fins.Repairing to the leakage portion by lining with FRP material including replacement of rusted nut and bolts and replacing of bird screens at air intake portion and testing of the cooling tower of CPP as specified as directed. by Engr-In-Charge. Note : Items under schedule item No 3 herein below shall be measured & paid as supply only item.
55Supply Only following routineSpares for Cooling Tower as per the requirement at site.
56FRP fins for cooling tower as per existing size at site.
57Nozzles as per existing size at site.
58M&L for taking down the damaged fan assembly of FRP cooling tower and connected fitting from the position and supply & fix by new fan assembly 1300mm minimum with 04 blades fan hub assembly made out of DIE Cast aluminium, with necessary clamp supports, nut & bolts by SS metal, including testing the cooling tower.
59M&L for carry out the repair to cooling tower fan motor 7.5HP flange mounted extended shaft type, including taking down from position, transporting to local work shop, dismantling the motor, replacing damaged unserviceable shaft, bearings, rusted nuts & bolts including servicing of motor, varnishings to winding etc. reassemble and installation to position and testing comissioning.
60M&L for replacing the cooling tower motor base frame, base plate, Nut & bolts with new all as per the existing size and shape.
61M&L for taking down the defective unserviceable fan blades set of 1300 mm sweep from the cooling tower fan motor and supply and fix the newfan blade of 1300 mm sweepwith suitable clamps nut & bolts etc. Including connecting the power supply and testing all as specified as directed by Engr-in-charge
62M & L for Maint/ Servicing of 62.5 KVA DG set , removing tapped cover after removing inlet / outlet pipe removing engine head replacingunserviceable valve seat & valve guide inlet & outlet as required replacing engine main gasket sheet cleaning the oil sump, cleaning/ replacement of fuel oil filter, cleaning of air filter, repair to the self starter assembly,Replacement of the fuel injection nozzles, repair and caliberation of the FIP, cleaning & checking of all diesel hose pipes, replacement of engine oil, repalcemet of battery terminals & battery leads, servicing of self starter dynamo by replacing carbon brushes beairngs & bushes andreassembling the engine head & tappered cover in original possition including all as specified in "C" check of engine manufacturer.Note :- Rate quoted includes cost of new items for replacement The engine oil for filling/topup will be meausued and paid seperately.
63M & L for Maint/ Servicing of diesel engine of air compressor type DA 16, BHP 16.2 cylinder , removing tappet cover after removing inlet / outlet pipe removing engine head replacingunserviceable valve seat & valve guide inlet & outlet as required replacing engine main gasket sheet cleaning the oil sump, cleaning/ replacement of fuel oil filter. Note :- Rate quoted includes cost of new items for replacement The engine oil for filling/topup will be meausued and paid seperately.
64M & L for Servicing of Lube Oil Coolers by dismantling,condition evaluation, transporting to workshop, thorough mechanical /ultrasonic mechanical cleaning the copper tube by steel brush, replacement of worn out parts like Synthetic rubber rings, Gaskets, O rings , nuts and bolts etc., assessment of leakages through pressure testing, reinstalling in original position & tetsing as per OEM standards. Note :- Rate quoted includes cost of new items for replacement.
65M & L for Servicing of Starting Air Compressor 12.5 HP by disconnecting electric motor & outlet piping, transporting the air compressor to work shop, dismantling air compressor, replacing worn our parts such as piston Ring, Oil Ring,Gas Ket Set, Bearings, Greasing Oiling & Reinstalling air compressor in original position including replacement of unserviceable soloniod coil, pressure switch etc , testing &comissioning all as specifiedand directed.Make ELGI, Model HP 12300 max working pressure 30 Bar, RPM 1100 of Air compressor.Note :- Rate quoted includes cost of new items for replacement
66M&L for servicing of the safety valve of air receiver capacity 0.50m3 , working pressure 30 kg/cm2, Design pressure 33kg/cm2 & test pressure 50 kg/cm2 all as specifed & directed.
67S & F in replacement of air drain valve max. Working pressure 35 kg/cm2, end can size 0.5 BSP, Max. Working temp. 75degeeC. For air receiverall as specifed & directed.
68M/L for servicing of DG control panel installed in CPP control room involving Calibration ofthe DE/NDE Sensors (01 set ie 02 nos,Ground protection Relay (01 no).ABB REM 543.110v AC.Aux,V:24vdc. 7CT,2PT Input (01 no.), Gen. ROTOR Earth fault relay ( 01 nos.), Gen. STATOR Earth fault relay (1 nos.), Triping Relay& Dead Bus Relay (2 nos) all as specifed & directed.
69M & L forServicing Automatic Voltage regulator AVR PANELS and replacement of defective parts all as specifed & directed. Note:- The above quoted rate includes replacing of defective AVR with new as existing capacity,replacing of control wiring, the calibration of Exciter panel and making sure the Voltage, RPM and frequency are as per the prescribed limits of OEM.
70M & L for Servicing ofLocal sensor Stand (LSS)PANEL .incl Calibration of the Pressure switch & 02 no. TemperatureSwitch ( HT < water ) 06 nos of Pr. Gauge. (HT & LT inlet and outletLube oil temp inlet and outlet pr and replacement of defective parts all as specifed & directed.
71M & L Servicing of Lighening Arrestor Protection Transformer (LAPT)PANEL incl Calibration ofDroop CT (01 no), Droop PT(01no), & Distribution Lightning arrestor CT(01no.) surge arrestor CT(01 no) core balance CT(01no) , & DROOPTransformers. (01no) and replacement of defective parts all as specifed & directed.
72M & L forServicing of Neutral Grounding Resistance (NGR)PANNEL incl Calibration of Protection CT (01 no).CBCT (1 nos) , Differential CT (03 nos) and replacement of defective parts all as specifed & directed.
73M&L for dismantalling the pump set from foundation and motor unit opening complete pump set , cleaning, replacing unserviseable parts such as gun metal bushes, rubber packing, ms nuts,bolts,rubber coupling , (spider) bearings, ai valve etc. With approved makes. Reassembling, reinstalling,testing for satisfactory running complete all as directed by EIC for the following pumps including transporting pumpsets to workshop for machininig work/ obtaining proper/suitable spares complete for:-
74Lub. Oil priming pump set 7.5 HP.
75HT water pump set 3 HP.
76LT water pump set 10 HP.
77M & L for rewinding of electric motors 3 phase 50Hz 415 volt comprisingof following activitiesfor motor of following capacity complete all as directed & specified & as per manufactures instructions Notes:- i) Disconnecting & removing the electric motor from installedposition & loading, unloading, including transporting. ii) Dismantling existing burnt winding from the motor, prepare for & including rewinding complete with super enamelled copper winding wire of existing guage including all material such as insulated paper, sleeves, tape, varnish etc. complete for class F insulation, keeping in hot air oven for drying, packing & reassembling complete. iii) Reinstalling in position & in alignment includingelectric connection, commissioning & testing in actual working condition to check designedRPMperformance complete. iv)Replacement ofBall bearings & bushesof existing sizewith exisisting make.
78Elect motor 0.5 to 1 HP
79Elect motor 3 HP
80Elect motor 4 HP
81Elect motor 5 HP
82Elect motor 7.5 HP
83Elect motor 10 HP
84M & L for Servicing of Plate Heat Exchangerby dismantling, assessment & condition evaluation, transporting to workshop, thoroughmechanical cleaning repairing , conducting DP test, replacement of worn out parts likeField Gaskets, Ring Gaskets,Pressure Guages, Spoolsgasketting, Pressure testing for leakages & reinstalling the PHEs in original position & testing & commissioning as per OEM standards.
85Labour only for carrying out servicing of DG sets( through authorised service rep/OEM) of capacity 2500 KW, 11 KV and Engine Make KOEL, Type 9PA 61-280 with rated BHP 3600 & all other connected equipments forming part of CPP including routine maintenance, replacement of engine oil, Engine oil leakage arresting,water pipe leakage arresting,fuel pipe leakkage arresting, leakkage arresting & binding with new asbestos rope on silencer/Exhaust pipesand replacement of defective / unserviceable spare partsas per site requirement including testing of DG sets after servicingso as to provide uninterrupted power supply as directed by EIC. Note :- The engine oil for filling/topup and other materials / spare parts will be measured and paid seperately under respective item here - in - below as mentioned.
86A) CYLINDERHEAD :
87a)  Visual inspection of the rocking gear.
88b)  Adjustment valve backlash on cold engine.
89c)  Inspection of the starting air valve flaps & rings.
90d) Strip opening of the cylinder Head
91e) Visual inspection of the Inlet and exhaust Valves
92f) Inspection of the Valve rocker assy
93g) Inspection of the rocking gear assy
94h) Inspection of the cylinder head assy
95j) caliberation of the tappet settings
96k) Timing gear caliberation/setting
97B) FUEL INJECTION :
98a) Check calibration Atomization & the tightness of the injector.
99b)  Replacement of injector nozzles if required
100c) Checking of the sliding of the injection pump racks.
101d) Replacement of the Anti splash screws.
102e) Inspection ofFuel injection pump
103C) CRANK CASE - BEARINGS - CRANK SHAFT :
104a) Carry out the crankcase inspection.
105b) Measurement of the crankshaft deflection
106c) Inspection of the bearing shells of two main bearings
107D) COUPLING - VIBRATION DAMPER :
108a) Check the resilient segment of the coupling and inspection of relilient material.
109E) FLUID SYSTEM:
110a)  Checking ofthe pneumatic starter
111b)  Inspection of the Air distributor disk.
112c)  Inspection of the Main starting valve.
113d)  Inspection & cleaning of the self cleaning fuel filter.
114e)  Inspection of the oil pump safety valve.
115f)  Inspection of the oil pressure control valve.
116g)  Inspection & cleaning of the self cleaning oil filter.
117h)  Inspection of centrifugal oil purifier
118j) Replacement of the filtering elements of self cleaning SOFRON
119k) Inspection of fuel feed pump
120l) Cleaning of lube oil MOTI filter
121F) GOVERNING - OVER SPEED - SAFETY – WIRING SYSTEM :
122a) Replacement of hydraulic governor or actuator oil.
123b)  Run the electronic overspeed test.
124c) Inspection & calibration of the electric actauator of electronic governor and calibration of same
125d) preperation of the governor connected with DG set of cap 2.5MW speed and frequency as required by the existing synchronising panels all as specified.
126Supply only followingspare parts foroverhauling of KOEL DG sets as mentioned in item Ser No 20.00 here-in-before.
127ROCKING GEARS
128Screw with expanded tappet cat part No. 79.033.28.0.00
129Special nut cat Part No. 79.033.35.0.00
130Fuel INJECTORS
131Helicoflex Sealing Joint Cat Part No. 27.067.16.0.00
132Copper Washer ( 20 x 27) Cat Part No. 50.508.20.000
133O RING D-8, 21A7, L120C7 Cat Part No 74.466.02.000
134Cap nut cat Part No. 79.041.03.0.00
135Ring D164 3.5D NSE6.531 60C7, Cat Part No.79.041.15.000
136Injector gasket Cat Part No. 79.041.18.0.00
137Bush Viton Cat Part No. 79.041. 19 .000
138O RING D135 3D NSE6. 531 60C7 Cat Part No 74.041.21.000
139Injector Nozzle Assembly 9x0.50x140cat part. 27.067.05.000
140Gasket cat part. 79.034.77.000
141FUEL FILTER
142Fuel Filters Element Cat Part No.79.352.06.0.00
143O Ring Filter cover (2.5 x 160, 21502) cat part No. 30.300.18.000
144O Ring Filter cover (3.5 x 112, 21502)cat part No. 30.300.28.000
145O Ring- Relief valve(2.5 x 13, 21502)cat part No. 30.300.34.000
146COUPLING
147O Ring DIA 17 x DIA 4x4 (20401) Cat Part No 70.657.33.0.00
148O Ring (20301)4x460 Material -Nitri Cat Part No 80.356.13.0.00
149STARTING AIR VALVE
150Copper Washer (30 x 38) Cat Part No 50.508.35.000.
151Conical Spring Washer (M 14) Cat Part No 50.527.10.000.
152Spring Cat Part No 79.040.03.0.00
153Washer Cat Part No 79.040.04.0.00
154Ring Cat Part No 79.040.06.0.00
155Snep Nut,(BINX NUT)HM10, Cat Part No 79.040.08.0.00
156O - Ring, MS29-513/126, 21A7, NSE 6.531, Cat Part No 79.040.10.0.00
157GOVERNOR DRIVE
158Key Cat Part No 50.402.08.025.
159Circlip External-30 MM Cat Part No 50.501.30.000.
160Circlip internal - 62 MM Cat Part No 50.502.62.000.
161Circlip internal- 80 MM Cat Part No 50.502.80.000.
162O Ring No AN58NSE 6.5, 21 A7 Cat Part No. 79.049.24.0.00
163Lub oil cooler and chrger cooler
164Set of Gasket and O Ring for Lub Oil Cooler Cat Part No 79.425.59.0.00
165EXHAUST MANIFOLD
166Gasket cat part No. 72.328.13.000
167Flexible joint cat part No. 79.078.07.000
168Exhaust gas temp sensor cat part No. 81.068.02.000
169Flexible joint cat part No. 27.052.21.000
170THERMOMETER / SWITCHES
171Thermometer 0- 100 to Suit M18X1.5 Cat Part No79.277.02.0.00
172Thermometer 0- 200 to Suit M18X1.5 Cat Part No79.277.03.0.00
173Supply Only lubricants.
174Lubrication oil system 68 for alternator bearings.
175ELGI Air lube oil for air compressors .
176lube oilSERVO Marine-10-40Grade.
177Material and Labour required for complete dismantling of existing burnt out 11 KV lightning arrestors and replacing the same with lightning arrestors suitable for 11 KV diesel generator.
178Supply & Fix in repairs heating element as existing on site of capacity 6 KW complete all as specified and directed by Engr-in-charge.
179M&L for caliberation of governor assembly of the DG set of cap 2.5 MW, 11 KVfor desired output inorder to maintain the voltage and frequency of the DG set witin the limit of +/-1% ofVoltage-11KV and frequency of 50HZ during all the time and dismantling of the governor assembly from the engine head and transporting the same to the OEM/authorized workshop and strip opening the governor assembly nad carrying out the requisite repair required to rectify the defects and assembling the governor assembly and refiiting the same with the DG set and testing the output of the DG set in the presence of the Engr-In-Chrage and rectifying the defects if any noticed complete all as specified and directed.
180Material & Labour required for servicing of air pressure control system mounted on 2.5 MW DG set by replacing old air reciever bottle of Cap 30 Kg/CM, drain valves , pressure control system complete including replacement of nuts and bolts assembly,cleaning of pipe line connected from DG set head to system be cleaned and made choke free complete as all as specifed and directed by Engineer-in-charge.
181M&L for preparation of old painted steel surfaces of 2.5 MW DG sets including alternator, support channels complete with the all connected equipments complete and painting with two coats of approved colour synthetic enamel paint complete all as directed. Note:-1. Painting should be done with existing colour codes and painting should apply with the help of spary gun using air compressor. 2. Quotated rate shall deemed to be included for preparation of old painted surface and applying zinc chrome primer over rusted portion all as directed.
182M&L for preparation of old painted steel surfaces of 62.5 KVA DG sets including alternator, support channels complete with the all connected equipments complete and painting with two coats of approved colour synthetic enamel paint complete all as directed.Note:-1. Painting should be done with existing colour codes and painting should apply with the help of spary gun using air compressor. 2. Quotated rate shall deemed to be included for preparation of old painted surface and applying zinc chrome primer over rusted portion all as directed.
183M&L for preparation of old painted surfaces of cooling tower inlet and outlet pipes any of size, support channels complete with the all connected accessories complete and painting with two coats of approved colour synthetic enamel paint complete all as directed. Note:-1. Painting should be done with existing colour codes and painting should apply with the help of spary gun using air compressor. 2. Quotated rate shall deemed to be included for preparation of old painted surface and applying zinc chrome primer over rusted portion all as directed.
184M&L for cleaning of diesel tank (Day Tank) of capacity 600 ltrs carefully by drining out fuel in the tank and disconnection from fuel system, descaling the diesel tank with water pressure and removing the complete sludge deposited, drying the tank, repair to any leakage, cleaning and testing of fuel line upto Fuel Pump inlet andpreparation of old painted surfaces of diesel tank (Day Tank) of capacity 600 ltrsincluding all inlet and outlet pipes any of size, support channels complete with the all connected accessories complete and painting with two coats of approved colour synthetic enamel paint complete all as directed. Note:-1. Painting should be done with existing colour codes and painting should apply with the help of spary gun using air compressor. 2. Quotated rate shall deemed to be included for preparation of old painted surface.
185M&L for cleaning of diesel tank (Drip Tank) of capacity 500 ltrs carefully by drining out fuel in the tank and disconnection from fuel system, descaling the diesel tank with water pressure and removing the complete sludge deposited, drying the tank, repair to any leakage, cleaning and testing of fuel line upto Fuel Pump inlet andpreparation of old painted surfaces of diesel tank (Drip Tank) of capacity 500 ltrs including all inlet and outlet pipes any of size, support channels complete with the all connected accessories complete and painting with two coats of approved colour synthetic enamel paint complete all as directed. Note:-1. Painting should be done with existing colour codes and painting should apply with the help of spary gun using air compressor. 2. Quotated rate shall deemed to be included for preparation of old painted surface.
186M&L for cleaning of Chemical mixing tank of capacity 600 ltrs - 01 No, Pre heating tank module 100 ltrs with heaters - 04 Nos and balance water tank 150 ltrs -04 Nos carefully by drining out chemical mixed water in the tank and disconnection from high temperature water circulation system system, descaling the all tank with water pressure and removing the complete sludge deposited, drying the tank, repair to any leakage, cleaning and testing of water line upto engine andpreparation of old painted surfaces of Chemical mixing tank of capacity 600 ltrs - 01 No, Pre heating tank module 100 ltrs with heaters - 04 Nos and balance water tank 150 ltrs -04 Nos including all inlet and outlet pipes any of size, support channels complete with the all connected accessories complete and painting with two coats of approved colour synthetic enamel paint complete all as directed. Note:-1. Painting should be done with existing colour codes and painting should apply with the help of spary gun using air compressor. 2. Quotated rate shall deemed to be included for preparation of old painted surface.
187M&L for preparation of old painted surfaces of air circulation System of 2.5 MW DG Set comprising of Diesel engine driven compressor-01 No, Electric driven compressor-01 No and air reciever bottle of Cap 30 kg/CM -04 Nos including all inlet and outlet pipes any of size, support channels complete with the all connected accessories complete and painting with two coats of approved colour synthetic enamel paint complete all as directed. Note:-1. Painting should be done with existing colour codes and painting should apply with the help of spary gun using air compressor. 2. Quotated rate shall deemed to be included for preparation of old painted surface and applying zinc chrome primer over rusted portion all as directed.
188M&L for adding Chemical KEM Water treatment 107 M for water softening purpose into the Chemical mixing tankall as directed.
189M&L for earthingcomplete in repairs with galvanized steel earth plate electrode600x600x6mm thick buried in ground vertical to a depth not less than 2.25 mtrs deep below ground level with top edge of plate not less than 1.5 mtr below normal ground level connected to galvanized GI strip of size 32 X 6 mm and 40 mm dia bore 7.5 mtr long light grade GI protection pipe for earth strip and GI watering pipe 40 mm dia medium grade from the top edge of earth plate fixed with deep cut onone end of pipe and fix from earth plate up to one feet above ground level of other end and plugged watering pipe at top with MS cap and grouted in PCC 1:2:4 of size 30 X 30 X 30 CM etc and 15 CM alternate layer of charcoal and salt around all sides of earth plate all as shown in electric plate no 3 of SSR part I of 2009. Note :- All joints either strip to strip of strip to earth plate are fixed with welded joints.
190Supplying and fixing in repairs 32mm X 6mm ,GI earth strip all as specified and directed
Disclaimer :
We takes all possible care for accurate & authentic tender information, however Users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender.
Tell us about your Product / Services,
We will Find Tenders for you

Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy

For Tender Information Services Visit : TenderDetail