| 1 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:3:6 (1 Cement : 3 coarse sand (zone-III) derived from natural sources : 6 graded stone aggregate 20 mm nominal size derived from natural sources) |
| 2 | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level : 1:2:4 (1 cement : 2 coarse sand (zone-III) derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources) |
| 3 | Providing and laying Centering and shuttering including strutting, propping etc. and removal of form work for : Retaining walls, return walls, walls (any thickness) including attached pilasters, buttresses, plinth and string courses fillets,kerbs and steps etc |
| 4 | Providing and laying Steel reinforcement for R.C.C. work including straightening, cutting,bending, placing in position and binding all complete above plinth level Thermo-Mechanically Treated bars of grade Fe-500D or more. |
| 5 | Providing and laying Brick Flat Soling 75mm thick with common burnt clay F.P.S. (non modular) bricks in foundation and plinth: |
| 6 | ROADWORK : Construction of Subgrade and Earthen Shoulders (Construction of subgrade and earthen shoulders with approved material obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of table (300-2) (a), ( Including cost of testing of materials at site and laboratory as directed by the deptt.) (b) from Govt land |
| 7 | By Mix in Place Method (Construction of granular sub-base by providing close graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with vibratory roller to achieve the desired density,complete as per cl. 401( Including cost of testing of materials at site and laboratory as directed by the deptt.) for grading- I Material |
| 8 | Dry Lean Cement Concrete Sub- base(Construction of dry lean cement concrete Sub base over a prepared sub-grade with coarse and fine aggregate conforming to IS: 383, the size of coarse aggregate not exceeding 25 mm, aggregate cement ratio not to exceed 15:1, aggregate gradation after blending to be as per table 600:1 , cement concrete not to be less than 150kg/cum, optimum moisture content to be determined during the trial length construction, concrete strength not to be less than 10Mpa at 7 days, mixed in a batching plant, transported to the site, laid with a paver with electronic sensor, compacting with 8-10 tonnes vibratory roller, finishing and curing.)(Including carriage of mixed materials up to10.0 Km initial lead from mixing plant.) |
| 9 | Cement Concrete Pavement (Construction of un-reinforced, dowel jointed, plain cement concrete pavement over a prepared sub base with 43 grade cement @400 kg per cum, coarse and fine aggregate conforming to IS 383, maximum size of coarse aggregate not exceeding 25 mm, mixed with Recron 3S fibre of Reliance Industries Ltd. or its equivalent @ 0.125 Kg. per bag of cement mixed in a batching and mixing plant as per approved mixed design, transported to the site, laid with a fixed form or slip form paver, spread , compacted and finished in a continuous operation includuing provision of contraction, expansion, construction and longitudinal joints, joint filler, seperation membrane, sealent primer, sealent joint , debonding strips dowel bar, tie rod, admixured as approved, curing compopund, finishing to lines and grades as per drawing. (Including carriage of mixed materials up to 10.0 Km initial lead from mixing plant.) as diected by the Department completeat all levels. |