| 1 | Providing and making UPVC/MDPE pipe consumer service connection on Distribution main by drilling hole with suitable means , including all labour UPVC /MDPE Pipe of required length with or without Road crossing asdescribed below, including cost of specials like Saddle/Clamp Saddle of suitable material, and diameter suitable for Distribution main, 15mm /20mm/25mm respective Dia Heavy duty Brass/Polyprophylyne(Twin Jacketed ) Ferrule , Male and Female thread adapter Elbow, Bends,couplers ,Tees, Clamps of suitable material and sundry materials as per requirment, including providing and fixing medium duty 15.mm brass bib tap, GI casing pipe of suitable diameter of32mm/ 40mm/ 50mm respectively of required length for Road crossing, including requird labour for excavation in all types of strata up to the depth of 0.75m or as per site requirement,all types of plumbing fittings, refilling , Closing the water supply in that area, dewatering, hydraulic testing and restarting the water supply,transportation of material etc. complete as directed by EngineerinA) Household Connection without water meter (Comression Saddle+ISI Mark Ferrul) for HDPE & PVC pipe dsr 21-2278/17 with road crossing |
| 2 | without road crossing |
| 3 | Excavation for foundation / pipe trenches in earth, soils of all types, sand, gravel and soft murum, including removing the excavated material upto a distance of 50 metres and lifts as below, stacking and spreading as directed, normal dewatering, preparing the bed for foundation and excluding backfilling, etc. complete. |
| 4 | Excavation for foundation / pipe trenches in hard murum including removing the excavated material upto a distance of 50 M and lifts as below,stacking and spreading as directed by Engineer-in-charge, normal dewatering, preparing the bed for foundation and excluding backfilling, etc. complete |
| 5 | Excavation for foundation / pipe trenches in soft rock and old cement and lime masonry foundation asphalt road including removing the excavated material upto a distance of 50 M beyond the area and lifts as below, stacking as directed by Engineer-incharge, normal dewatering, preparing the bed for foundation and excluding backfilling, etc. complete. |
| 6 | Filling in plinth and floors murum bedding in trenches with approved murum from excavated materials from foundation in 15to 20 cm layers including watering and compaction, etc. complete. |
| 7 | Providing and supplying in standard lengths ISI mark rigid unplasticised PVC pipes suitable for potable water with solvent cement joints including cost of couplers, as per IS specification no. 4985 / 1988 excluding GST levied by GOI and GOM in all respect, including transportation, freight charges, inspectioncharges, loading, unloading, conveyance to the departmental stores and stacking the same in closed shed duly protected from sun rays and rains including cost of jointing material i.e. solvent cement, etc. complete (selffit type to be jointed with cement solvent) 63 mm dia 4 kg/cm2 |
| 8 | 75 mm dia 4kg/cm2 |
| 9 | 90 mm dia 4kg/cm2 |
| 10 | Lowering, laying and jointing with P.V.C. pipes and specials of following class and diameter including cost of conveyance from stores to site of works including cost of all labour, material, except cement solvent, rubber ring, as per IS code, etc. complete (with cement solvent joint / ring fit joint) 63 mm di |
| 11 | 75 mm dia 4kg/cm2 |
| 12 | 90 mm dia 4kg/cm2 |
| 13 | Refilling the trenches with available excavated stuff with soft material first over pipeline and then hard material in 15 cm layers with all leads and lifts including consolidation, surcharging, etc. complete. |
| 14 | Providing and laying in situ Cement Concrete M-15 of trap/ granite / quartzite /gneiss metal for foundation and bedding including bailing out water, form work,compaction, curing, etc. complete. (Cement 5.90 bags / cum) 60/1 b) In PCC M-150 |
| 15 | GST 18 % |