| 1 | SUPPLY OF MATERIAL PORTION |
| 2 | ST Pole SP-21 Galvanized |
| 3 | ST Pole SP-10 Galvanized |
| 4 | Stay Set 16X1800 MM |
| 5 | Stay Wire 7/10 SWG |
| 6 | EARTHING ROD MS 20X2500MM |
| 7 | GI WIRE 5MM/6 SWG |
| 8 | Stay Clamp For ST Pole SP- 21/10 Of Size 50x6 sqmm duly red oxide painted with sitable size with fitted Nut andBolts and washer as per specification of UPCL |
| 9 | MS Half Clamp For LT DB For ST Pole SP- 21/10 Of Size 35x5 sqmm duly red oxide painted with suitable size with fitted Nut andBolts and washer as per specification of UPCL |
| 10 | 3 Phase LT Distribution Box With inbuilt panel lock, Al Bus Bar RYB 25x6mm,Al Busbar N 40x6mm |
| 11 | 1 Phase LT Distribution Box With inbuilt panel lock, Al Bus Bar RYB 25x6mm,Al Busbar N 40x6mm |
| 12 | Insulated piercing connector size 70-70/35-35 sqmm for line to line tapping |
| 13 | Insulated piercing connector size 70/35 sqmm to 25 sqmm for energising disribution box |
| 14 | Dead End Clamp With I Hook & MS Clamp made of MS Flat for ST Pole SP-21/10 of Size 50x6 sqmm duly red oxide painted with suitable size with fitted Nut and Bolts and washer for Dead End Assembly as per UPCL specification |
| 15 | Suspension Clamp WithI Hook & MS Clampmade of MS Flat for ST Pole SP-21/10 of Size 50x6 sqmm duly red oxide painted with suitable size with fitted Nut and Bolts and washer for Suspension Clamp as per UPCL specification |
| 16 | LT Wire Neutral Connector PG Clamp 50/25-25sqmm single bolt as per UPCL specificationfor energising distribution box |
| 17 | LT Wire Neutral Connector PG Clamp 50-50/25-25sqmm single bolt as per UPCL specification for line to line tapping |
| 18 | Head shink type end caps suitable for LT ABC |
| 19 | Lug size O type 35 Sqr Mm |
| 20 | 1x35 sq mm XLPE insulated Al. Cable for energising the distribution boxes |
| 21 | LT AB Cable 3x70+1x50 Sqr mm |
| 22 | LT AB Cable 3x35+1x25 Sqr mm |
| 23 | LT AB Cable 1x35+1x25 Sqr mm |
| 24 | LABOUR PORTION |
| 25 | ERECTION OF EARTHING ROD |
| 26 | EXCAVATION OF PIT FOR STAY SET |
| 27 | ERECTION OF LT STAY SET |
| 28 | GROUTING OF STAY SET |
| 29 | EXCAVATION OF PIT FOR POLE |
| 30 | ERECTION OF SINGLE SP-10 POLE |
| 31 | ERECTION OF SINGLE SP-21 POLE |
| 32 | GROUTING OF POLE |
| 33 | MUFFING OF POLE |
| 34 | DISMANTLING OF LT LINE 1 P 2 W(WEASEL) |
| 35 | DISMANTLING OF LT LINE 2 P 3 W(WEASEL) |
| 36 | DISMANTLING OF LT LINE 3 P 4 W(WEASEL) |
| 37 | PAINTING OF SP-10 POLE |
| 38 | PAINTING OF SP-21/23 POLE |
| 39 | HEADLOAD CARTAGESP-10 POLE(1-3 KM) |
| 40 | HEADLOAD CARTAGE SP-21/23 POLE(1-3 KM) |
| 41 | HEADLOAD CARTAGE OF MATERIAL(1-3 KM) |
| 42 | DISCONNECTION & RECONNECTIONOF Consumer |
| 43 | LAYING OF LT AB CABLE 3X70+1X50 SQMM |
| 44 | LAYING OF LT AB CABLE 3X35+1X25 SQMM |
| 45 | Straightening of Tilted STP Poles |
| 46 | BACK CARTAGE OF PETTY MATERIAL,150-200KM |
| 47 | Installation of LT Distribution Box |
| 48 | BACK HEAD LOAD CART. OF PETTY MAT. 1-3KM |
| 49 | LAYING OF1x35sqmm XLPE INSULATED CABLE |
| 50 | RENOZZELING OF EXISTING STAY SET |
| 51 | LAYING OFLT AB Cable 1x35+1x25sqmm |
| 52 | LOOPING AND CHOPPING OF TREE BRANCHES |
| 53 | Installation of LT Distribution Box complete work |