| 1 | Dismantling & removing of the old damaged materials as per the requirement at sitewith all lead and liftincluding scaffolding, disposing the same materials at specified place including supplying of all labours, materials, T&P etc all complete as per the direction of Engineer-in-charge.(Excluding GST). |
| 2 | Brick work |
| 3 | R.C.C |
| 4 | cement plaster |
| 5 | Earth work in all kind of soil with initial lead and lift including roughdressing in layers not exceeding 0.3m in depth and the Earthtransported by transport vehicles as directed by the Engineer-in-charge.( Excluding GST) |
| 6 | Back Filling in foundation and plinth with excavated materials moorumincluding watering and ramming but excluding cost of GST as directedby the Engineer-in-charge |
| 7 | Filling in foundation and plinth with filling sand(saline) includingwatering and ramming but excluding cost of GST as directed by theEngineer-in-charge. ( 10% voids shall be deducted from the measured qty ) |
| 8 | P.C.C(1:3:6) of using 20 mm. & down C.B.G chips of approved quality infoundation & plinth including mixing hosting, laying to proper level &slope compacting, curing, watering charges etc. complete including cost & supply of all materials, labour, T&P, taxes, etc. complete butexcluding cost of GST as directed by Engineer-in-charge |
| 9 | Brick work in Fly Ash Bricks of size 25cmx 12cm x 8cm and having crushing strength not less than 75 Kg/Cm² to 99Kg/Cm² with C.M (1:6) including splay/cutting, racking out the joints curing, hoisting, staging at any height with cost and supply of all materials, labour,T&P, taxes, royalties, transportation charges, curing, testing charges etc. all complete but excluding GST as per direction of Engineer-in-charge |
| 10 | Cement concrete (1:1.5:3) using 12mm to 20mm size C.B.G. chips for all floors,foundation & plinth etc. of approved quality mixing, hoisting, laying, compacting, curing with cost and supply of all materials, labour, T&P, taxes, tollage, royalties, etc. all complete but excluding GST as directed by Engineer-in-charge. |
| 11 | Supply Tor/TMT steel manufactured by SAIL/TISCON/VIGAC Steel of Fe-500 confirming to IS-1786 including cutting, straightening, bending, binding & placing the grills in position for RCC works binding the grills with binding wire of 18 to 20 gauge including supply of steel, labour, materials, transportation charges, T&P, taxes, etc. all complete but excluding GST as per the direction of Engineer-in-charge. (NB: No payment shall be made for extra weight than theoretical co-efficient). |
| 12 | Providing rigid smooth leak proof centering & shuttering made of steel/ply, plank of approved quality for R.C.C. structures and deshuttering and removing the same after due period with supply of all materials, labour, T&P, taxes, royalties, tollage, etc. all leadand lif etc. all completebut excluding GST as directed by Engineer-in-charge |
| 13 | R.C.C. foundation and footing bases of columns mass concrete & precastslab etc |
| 14 | Beam, column, girder |
| 15 | Roof slab, landing, projection Chajja |
| 16 | 12 MM thick Cement plaster with cement mortar (1:6) proportion,over brick work including racking out the joints, finished smooth to theexposed surface, rounding the corners wherever found necessaryincluding cost & supply of all materials, labour, T&P, staging,scaffolding, watering, curing, taxes, tollage, royalties, etc. complete butexcluding cost of GST as per direction of Engineer-in-charge |
| 17 | 6 MM thick Cement plaster with cement mortar (1:4) proportion, overRCC work including racking out the joints, finished smooth to theexposed surface, rounding the corners whereverfoundnecessaryincluding cost & supply of all materials, labour, T&P, staging,scaffolding, watering, curing, taxes, tollage, royalties, etc. complete butexcluding cost of GST as per direction of Engineer-in-charge |
| 18 | Supplying fitting fixing of Vitrified floor tiles ( premimum Quality 600 x600 mm size)in floors, treads or steps and landing on 12mm thick bed of cement mortar 1:3(1cement: 3 sand) jointed with neat cement slury mixed with pigment to match the shades of the tiles including rubbing and cleaning complete including supply of all labour material taxes tollage etc all complete but excluding GST as per direction of Engineer in charge. |
| 19 | Distempering two coats of approved quality and shade to New work including one coat of primer supplying cleaning, brushing, the old paint, removing theflakes and finishing smooth the wall surface by applying plaster of parisor wall putty where required, sand papering including cost & supply ofall material labours, T&P scaffoldings, taxes etc. complete but excludingcost of GST as directed by the Engineer in charge |
| 20 | Exterior painting two coats to wall surface with acrylic based weathercoat paintincluding one coat of primer of approved quality &shade having resistance to Fungus,Fading, including scraping, cleaning, brushing, washing the old paint, asand when required, removing the flakes applyinguniformly two coatsincluding cost and supply of all materials, labour, T&P,taxes,transportation, staging, scaffolding, etc.completebut excluding cost ofGST as directed by the Engineer-in-charge. |
| 21 | providing fitting and fixing the fabricted MS /G.I structures after cutting,bending, making holes, jointing ,welding as per requirement andHoisting fabricated structurals, placing in position as per the drawingsor as directed with supply of labour and material,machinery, cost offuel, electrode, gas, consumables hire and running charges of all kind ofequipments etc all complete as per direction of Engineer-in-charge.( Excluding GST) |
| 22 | Transportation, supplying, fitting & fixing of Barbed wire2 Ply 4 pin of approved quality with supply of all labour and materials, T&P,etc. all complete as directed by the Engineer-in-charge. ( Excluding GST) |
| 23 | Painting two coats with approved quality & shade enamel paint onnew iron work over one coat of red oxide primer including scraping,cleaning, the old paint surface sand papering, filling the holes with waxputty etc. all complete including cost and supply of all materials, labour,T&P, all taxes, transportation charges, staging, scaffolding, etc. allomplete but excluding cost of GST as per direction of Engineer-incharge |
| 24 | Engagement of Tractor for shifting of over burden materials, debris from one place to otheretc. with fuel, engagement hire & running charges, cost of operator, etc. all complete as per direction of Engineer-in-charge only engagement perod will considered, no idle charges will be considered (Excluding GST). |
| 25 | Engagement of labour for cleaning &disposing the debrises,unwanted growth /creepers etc. wherever required for smooth disposal of accumulated rain water along with engagement of labour, T&P, etc. complete as per direction of Engineer in-charge.(Excluding GST) |
| 26 | Supplying ,fitting ,fixing of R.C.C(1:1.5:3) Benches in lawn and park area with supply of all labour ,T&P,taxes,etc.all complete as directed by Engineer -In-Charge.(Excluding GST) |