Construction Of Ht, Lt Line, 11/0.4 Kv Sub Station And L.T. Extension Work To Giving New Connection In Ht/Lt Scheme As Per Uerc Regulation In 33/11 Kv S/S Lalpur Under Electricity Distribution Division, Kichha
Tender Overview
Project Description
Construction Of Ht, Lt Line, 11 / 0.4 Kv Sub Station And L.T. Extension Work To Giving New Connection In Ht / Lt Scheme As Per Uerc Regulation In 33 / 11 Kv S / S Lalpur Under Electricity Distribution Division, Kichha
BOQ
| Sl. No. | Item Description |
| 1 | Annexure-A (LABOUR CHARGES) |
| 2 | Earthing of support with M.S. Earth rod of 2.5 meter long by hammaring of M.S. Rod to proper depth and connecting the earth electrod with the help of G.I. wire as per construction manual. |
| 3 | Excavation of earth for stay pit of size 0.6x0.6x1.2 mtr in all types of soil including proper dressing of sides and ramming of bottom including getting out the excavated soil and disposal of surplus excavated soil as directed complete work |
| 4 | Fixing,tightening and nozzling of stay with pole and stay rod on required tension as per drawing/manual in LT line |
| 5 | Fixing,tightening and nozzling of stay with pole and stay rod on required tension as per drawing/manual in 11 KV Line |
| 6 | Grouting of Stay in size 0.6x0.6x0.3 in CC ratio 1:4:8 (1 cement :4 graded stone 20mm nominal size: 8 coarse sand ) block includ ing cost of Cement,sand andstone ballast back filling of soil and boulders in pit and ramming and proper alignment, leveling as per RESSPO Manual. |
| 7 | Excavation of earth for pole pit of size 0.9x0.6x1/6 of full length of pole for erection of pole in all types of soil including prop er dressing of sides and ramming of bottom including etting out the excavated soil and disposal of surplus excavated soil as directed complete work. |
| 8 | Erection of PCC single support pole in proper level and alignment along with fixing of all accessories like top channel,& clamps as per RESPO manual. |
| 9 | Erection of SP-23 single support pole in proper level and alignment along with fixing of all accessories like top channel,& clamps as per RESPO manual. |
| 10 | Erection of SP-33 single support pole in proper level and alignment along with fixing of all accessories like top channel,& clamps as per RESPO manual. |
| 11 | Erection of SP-55 single support pole in proper level and alignment along with fixing of all accessories like top channel,& clamps as per RESPO manual. |
| 12 | Erection of SP-72 single support pole in proper level and alignment along with fixing of all accessories like top channel,& clamps as per RESPO manual. |
| 13 | Erection of PCC double support pole in proper level and alignment along with fixing of all accessories like top channel, X bracings &clamps as per RESPO manual. |
| 14 | Erection of SP-23 double support pole in proper level and alignment along with fixing of all accessories like top channel, X bracings & clamps as per RESPO manual. |
| 15 | Erection of SP-33 double support pole in proper level and alignment along with fixing of all accessories like top channel, X bracings& clamps as per RESPO manual. |
| 16 | Erection of Sp-55 double support pole in proper level and alignment along with fixing of all accessories like top channel, X bracings & clamps as per RESPO manual. |
| 17 | Muffing of poles size 0.45x0.60 cm radius with 1:3:6(1 cement:3 coarse sand :graded stone 10 mm nominal size) block size 45 cm height from ground level including cost of cement,stone and sand etc. |
| 18 | Dismantling of Transformers from double pole /plinth including openingof all connections, circuts & earthing strip etc. (25 KVA) |
| 19 | Dismantling of Transformers from double pole /plinth including openingof all connections, circuts & earthing strip etc. (63 KVA) |
| 20 | Dismantling of Transformers from double pole /plinth including openingof all connections, circuts & earthing strip etc. (100 KVA) |
| 21 | Installation of 33/11 KV Metering cubical in the Metering room with groutingand making all connection. |
| 22 | Loading, unloading & carriage of LT PRMC from Store to pit site & Installation on the double pole with the help of Nut Bolt & Clamp and making to pass LT cable from T/F to PRMC. |
| 23 | Laying and erection of L.T. PVC Cable including crimping of lugs of size 1x70,120, 150 Sq.mm. (Including all cost of material) |
| 24 | Digging of trench of size 0.60x0.15 x 1.5 mtr. and laying of underground11 KV XLPE cable with makingof brick housing and fillingof sand including filling of earth with ramming. & repairing of road includingcost of cement sand and stone blast |
| 25 | Installation / mounting of new 100 KVA Tranformer on pole structure and fixing of channel / angle etc. and making all connections ofHt and LT side and its complete commissioning. |
| 26 | Installation / mounting of new 63 KVA Tranformer on pole structure and fixing of channel / angle etc. and making all connections of Ht and LT side and its complete commissioning. |
| 27 | Installation / mounting of new 25 KVA Tranformer on pole structure and fixing of channel / angle etc. and making all connections of Ht and LT side and its complete commissioning. |
| 28 | Mounting & Fixing of Fuse sets on double pole structures including making of connections complete work |
| 29 | Fixing of triangular type bracket on 11 KV line |
| 30 | Laying, Spreading, Stringing and sagging of 11 KV / 33 KV line in 3 phase (3 Phase 3 wire) of ACSR Weasel as phase wire with G.I. earth wire complete including fixing of all accessories in 3 Nos. conductor in parallel with binding and jumpering as per profile and profile and sagging chart. |
| 31 | Laying, Spreading, Stringing and sagging of 11 KV / 33 KV line in 3 phase (3 Phase 3 wire) of ACSR Rabbit as phase wire with G.I. earth wire complete including fixing of all accessories in 3 Nos. conductor in parallel with binding and jumpering as per profile and profile and sagging chart. |
| 32 | Laying, Spreading, Stringing and sagging of 11 KV / 33 KV line in 3 phase (3 Phase 3 wire) of ACSR Dog as phase wire with G.I. earthwire complete including fixing of all accessories in 3 Nos. conductor in parallel with binding and jumpering as per profile and pro file and sagging chart. |
| 33 | Laying, Spreading, Stringing and sagging of L.T. Lines of ACSR Weasel as phase wire(3 phase 4 wire) with G.I. earth wire complete wi th binding and jumpering as per RESSPO Specn |
| 34 | Laying, Spreading, Stringing and sagging of L.T. Lines of ACSR Weasel as phase wire(2 phase 3 wire) with G.I. earth wire complete wi th binding and jumpering as per RESSPO Specn |
| 35 | Laying, Spreading, Stringing and sagging of L.T. Lines of ACSR Weasel as phase wire(1 phase 2 wire) with G.I. earth wire complete wi th binding and jumpering as per RESSPO Specn |
| 36 | Route cleareance by cutting of tree branches / proning, loping and chopping of trees for L.T., 11 & 33 KV line. |
| 37 | T-off Connection Complete 11 KV line |
| 38 | Laying,Sagging & binding of AB cable of size 120 sqmm.(Only for cable,additional provisions to be made for matching accessories inst allation,case of any network modification i.e additionalpole etc. and for actual connection,disonnection as per site condition. |
| 39 | Making of section pole for existing LT/HT/33KV line complete in all respect. |
| 40 | Jointing and fixing of cable jointing kit indoor/outdoor 11 KV XLPEheat shrinkable cable boxes |
| 41 | Cartage of PCC Poles from store centre to construction site with loading, unloading at both points and proper stacking.(Distance 21- 50 Km) |
| 42 | Cartage of ST pole SP-21/23 Poles from store centre to construction site with loading, unloading at both points and proper stacking. (Distance 21-50 Km) |
| 43 | Cartage of ST pole SP-33 Poles from store centre to construction site with loading, unloading at both points and proper stacking.(Di stance 21-50 Km) |
| 44 | Cartage of ST pole SP-55 Poles from store centre to construction site with loading, unloading at both points and proper stacking.(Di stance 21-50 Km) |
| 45 | Cartage of ST pole SP-72 Poles from store centre to construction site with loading, unloading at both points and proper stacking.(Di stance 21-50 Km) |
| 46 | Cartage of other material (other than poles) by vehicle from Store Center to nearest construction site Store including loading and unloading at both ends(distance 21-50 Km) |
| 47 | Cartage of the 16/25 KVA transformer from store center to construction site with loading and unloading at both points.(Distance 21-50 Km) |
| 48 | Cartage of the 63 KVA transformer from store center to construction site with loading and unloading at both points.(Distance 21-50 K m) |
| 49 | Cartage of the 100 KVA transformer from store center to construction site with loading and unloading at both points.(Distance 21-50 Km) |
| 50 | Cartage of the 33 KV VCB,feeder panels(O/D),T/F Control panel from store center to construction site with loading and unloading at both points.(Distance 21-50 Km) |
| 51 | Headload cartage of PCC Pole from road to site(distance 0-1 Km) |
| 52 | Headload cartage of SP-21/23 Pole from road to site(distance 1-3 Km) |
| 53 | Headload cartage of SP-33 Pole from road to site(distance 0-1 Km) |
| 54 | Headload cartage of SP-55 Pole from road to site(distance 0-1 Km) |
| 55 | Headload cartage of SP-72 Pole from road to site(distance 0-1 Km) |
| 56 | Head load cartage of small material(distance 0-1 Km) |
| 57 | Head load cartage of small material(distance 1-3 Km) |
| 58 | Headload cartage of 25 KVA transformer from road to site(distance 0-1 Km) |
| 59 | Headload cartage of 63 KVA transformer from road to site(distance 0-1 Km) |
| 60 | Headload cartage of 100 KVA transformer from road to site(distance 0-1 Km) |
| 61 | FABRICATION OF STEEL FOR STRUCTURE |
| 62 | DIGGING OF PIT FOR MAKING TRENCH 0.6X0.15X1.5 MTR FT DEPTH,INCLUDING BRICK AND SAND WORKINCLUDING BACK FILLING AS PER RESPO |
| 63 | LAYING STRINGING AND SAGGING OF LT AB CABLE 3X70+1X50 SQMM |
| 64 | Digging of Pit through Hammer at CC, DAMAR Road |
| 65 | Transportation Charges of 25 KVA including packing, forwarding, loading, unloading, stacking and transit insurance. |
| 66 | Transportation Charges of 63 KVA including packing, forwarding, loading, unloading, stacking and transit insurance. |
| 67 | Transportation Charges of 100 KVA including packing, forwarding, loading, unloading, stacking and transit insurance. |
| 68 | Annexure-B (SUPPLY ITEMS) |
| 69 | Supply of F CLAMP |
| 70 | Supply of X ARM CLAMP FOR PCC POLE WITH N/B |
| 71 | Supply of X ARM CLAMP FOR ST POLE SP-55 WITH N/B |
| 72 | Supply of LT CLAMP FOR PCC POLE WITH N&B |
| 73 | Supply of LT CLAMP WITH N&B ST POLE SP-55 |
| 74 | Supply of STAY CLAMP FOR ST POLE WITHNUT BOLT |
| 75 | Supply of DOUBLE POLE CLAMPS WITH N/B FOR PCC POLE |
| 76 | Supply of DOUBLE POLE CLAMPS WITH N/B FOR SP-55 |
| 77 | Supply of STAY CLAMP WITH N&B PCC POLE 8.5 MTR |
| 78 | Supply of STAY INSULATOR 75x90 MM |
| 79 | Supply of SHACKLE INSULATOR 75X90 MM WITH NUT BOLT |
| 80 | Supply of Piercing connector for 120-95 SQ.MM |
| 81 | Supply of Piercing connector for 95-35 SQ.MM |
| 82 | Supply of LT DISTRUBITON BOX 3 PHASE |
| 83 | Supply of CRIMPING TYPE Al. LUGS (25-100) SQ.MM |
| 84 | Supply of MS Flat 40x6 MM |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
CompletedBid Opening Date
Technical bids will be opened and evaluated.
CompletedTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender