Tender For Repair And Maint Of 33 Kv Circuit Breaker Yard Maint Transformer Repair At 33/11 Kv Khyber Grid And Repair And Maintenance Of 33/11 Kv Ah R And R Grid And Repair/Maint Of 11 Kv Ht Cable From Khyber Grid To Manekshaw Centre Under Age Sldc U, delhi-Delhi

Military Engineer Services-MES has published Tender For Repair And Maint Of 33 Kv Circuit Breaker Yard Maint Transformer Repair At 33/11 Kv Khyber Grid And Repair And Maintenance Of 33/11 Kv Ah R And R Grid And Repair/Maint Of 11 Kv Ht Cable From Khyber Grid To Manekshaw Centre Under Age Sldc U. Submission Date for this Tender is 20-02-2024. Transformer Repair Tenders in delhi Delhi. Bidders can get complete Tender details and download the document.




Tender Notice

41215588
Corrigendum : Tender For Repair And Maint Of 33 Kv Circuit Breaker Yard Maint Transformer Repair At 33/11 Kv Khyber Grid And Repair And Maintenance Of 33/11 Kv Ah R And R Grid And Repair/Maint Of 11 Kv Ht Cable From Khyber Grid To Manekshaw Centre Under Age Sldc U
Open Tender
Indian
Delhi
delhi
20-02-2024

Tender Details

Repair And Maintenance Of 33 Kv Circuit Breaker Yard Maintenance Transformer Repair At 33 / 11 Kv Khyber Grid And Repair And Maintenance Of 33 / 11 Kv Ah R And R Grid And Repair / Maint Of 11 Kv Ht Cable From Khyber Grid To Manekshaw Centre Under Age Sldc Under Ge U E

Corrigendum Details

Sr No CorrigendumDate Corrignedum CorrigendumType NewSubmissionDate
1 08-Jan-2024 coor no 1 dt 8 jan Date 23-01-2024
2 18-Jan-2024 coor no 2 Date 30-01-2024
3 23-Jan-2024 coor No 3 Date 06-02-2024
4 03-Feb-2024 coorno4 dt 3 Feb 2024 Date 13-02-2024
5 06-Feb-2024 coorno5 Other 13-02-2024
6 13-Feb-2024 Bid Auto Extn Corrigendum Bid Auto Extn Corrigendum 20-02-2024

Key Value

Document Fees
INR 1000 /-
EMD
INR 162500.0 /-
Tender Value
INR 91.62 Lakhs /-

BOQ Items

Name of Work: Repair and maint of 33 KV circuit breaker yard maint , transformer repairat 33/11 KV Khyber grid & Repair & maintenance of 33/11 KV AH R&R Grid and Repair/Maint of 11 KV HT Cable from Khyber grid to Manekshaw Centre under AGE SLDC under GE (U) Electric Supply Delhi Cantt -10
Sl. No. Item Description
1Testing the cables with high voltage DC testing machine and locating the fault in the cables by fault locating machine to pin point exact position of fault, disconnecting faulty 33 KV HT cables of differentsizesfrom both ends, removal of Fault,Re-connections and testing of cables after removal of fault complete all as specified and directed. Note-: (a)33 KV HT cable & joints shall be measured and paid for separately under respective items of schedule. (b) Retrieved old serviceable cable coverwill be laid in trenches for cable protection. If extra PCC cover and sand required at site shall be measured and paid separately under respective items of BOQs. (c) Excavation and earth work will be measured and paid for separately under respective items of schedule.
2Supply andfix Cable jointing kit for 33 KV (Earthed) grade cable for straight through heat shrink type joint complete with jointing material and accessories suitable for 3 core XLPE armoured aluminium conductor cable of following size :-
3400 sqmm 3 core.
4300 sqmm 3 core.
5Supply andfixCable jointing kit for 33 KV (Earthed) grade cable for outdoor termination heat shrink type joint complete with jointing material and accessories suitable for 3 core XLPE armoured aluminium conductor cable offollowing size :-
6400 sqmm 3 core.
7300 sqmm 3 core.
8Material and labour for emergencymaintenance work of 33 KV overhead line during breakdown by deployingskilled labour and electriciansat faultysite havingGang of minimum 6 persons and transportation including hydraulic machine and other tools and plant required at site for fault rectification. Note:-Contractor or his rep shall come to the site of breakdown within one hour of notification of breakdown. In case the rep or contractor shall not come to the site of breakdown and not starts attending breakdown within 1.00 hour a penalty of Rs 1000 per fault per hour will be imposed over contractor and will be deduct from his dues.
9All as per Item No4 here-in -beforeabove but Gang of minimum 3 persons except hydraulic machine.
10Supplying and Fixing in replacement,PGclamps aluminium cast alloy suitable for existing ACSR conductorof typeZebra/Dog/Goat/Panther/Wolffor 33 KV yard /33 KV towers with GI nuts, bolts etccomplete all as specified and directed.
11S&F in replacement Isolators clamps aluminium cast alloyfor both terminals suitable for ACSR conductor of typeZebra/Dog/Goat/Panther/Wolf for 33 KV yard with GI nuts & bolts complete all as specified and directed
12Supplying and Fixing in replacement,T -connector/ clamps,aluminium cast alloy suitable for existing ACSR conductorof typeZebra/Dog/Goat/Panther/Wolf for 33 KV yardwith GI nuts & bolts complete all as specified and directed.
13S&F in replacement CT clamps aluminium cast alloyfor both terminals suitable for ACSR conductor of typeZebra/Dog/ Goat/Panther/Wolffor 33 KV yardwith GI nuts & bolts complete all as specified and directed
14S&F in replacement PT clamps aluminium cast alloyfor both terminals suitable for ACSR conductor of typeZebra/Dog/ Goat/Panther/Wolffor33 KV yardwith GI nuts & bolts complete all as specified and directed
15S&F in replacementdead endclamps aluminium cast alloyfor both terminals suitable for ACSR conductor of typeZebra/Dog/Goat/Panther/Wolfof 33 KV yard /33 KV towerswith GI nuts & bolts complete all as specified and directed
16S&F in replacement33 circuit breakerclamp aluminium cast alloyfor both terminals suitable for ACSR conductor of typeZebra/Dog/Goat/Panther/Wolffor 33 KV yardwith GI nuts & bolts complete all as specified and directed
17Supplying and Fixing in replacement, Post insulator with hardware fittings, 33 KV Grade,for isolatorcomplete all as specified and directed.
18Supplying and fixing in replacement, Disc insulators with hardware fittings, 33 KV Grade for 33 KV yardcomplete all as specified and directed.
19S&F in replacement of pin insulator with hardware fittings 33 KV gradecomplete all as specified and directed
20M&L for replacement ofaluminiumjumpermade ofACSR conductor of typeZebra/Dog/Goat/Panther/Wolf conductor of 33 KV towers/33 KV yard complete all as specified as directed .
21Material and labour forremoving of grass/vegetation bushesfrom inside of 33 KV towers and upto a distance of1.5 meter outside the tower complete all as specified as directed .
22M&L inreplacement ofdamage single/double /tripletension disc insulators and hardware fitting and fixing in position including tightening of bolts & nuts, complete after dismantlingand lowering of damage conductor/disc insulator by taking tension of conductor on a separate arrangement including opening & providing of jumpers of 33 KV tension towers complete all as specified and directed.
23M&L in replacementof damage single/ double /triple disc suspension disc insulator byre-arranging with good/new disc insulatorsafter taking the load of conductor on alternate arrangement including proper clamping etc. as per site requirement of 33 KV tower complete all as specified and directed.
24M&L for stretching/tightening of looseACSR conductor including fixing of conductor accessories such asclampetc as per site condition of Zebra/Dog/Goat/Panther/Wolf conductor of 33 KV lines complete all as specified and directed. Note : Length of indl conductor shall be measured.
25M & L for Jointing of ACSR conductor of any type with mid span joint through compression joint machine of 33 KV lines complete all as specified and directed.
26Trimming and cutting of tree branches(not more than 25mm girth) coming across 33 KV HT over head line clearing the line around 2m single/both sides and disposal of branchesfrom siteexceeding 50m and not exceeding 250m from site complete allas directed by Engr-in-Charge. Note : - (i)Length of span is approx 200 to 225 RM. (ii) Due care is to be given while trimming/cutting the tree branches that there should no damage to over head line conductor/pole. In case due to any negligence, damage is caused to be make good/renewal by the contractor from his own resources and nothing extra is admissible. (iii)All Safetytolabourer must be adhered by the contractor during trimming and cutting of tree branches.
27Supplying and fixing , Stretching, Securing, Connecting & testing of Aluminium Conductor Steel Reinforced (ACSR)of sizeZebra/Dog/Goat/Panther/Wolffor33 KV lines/33 KV yard complete including taking out old unserviceable conductor complete all as directed.
28Material & labour for repair /overhauling of OLTC ( On load tap changer ) of 33KV/11KV Power transformer of capacities 16/20 MVA at site by carrying outfollowing work of BBL make :- (a)Opening of top plate of OLTC. (b) Draining out of transformers oil from the OLTC. (c)Stopping of leakage of oil from main shaft of OLTC including replacement of oil seal and all gasket of OLTC. (d)Checking/servicing of moving and fixed contact of OLTC and resistance test of contact. (e)Flushing of OLTC assembly with hot new oil and removing of sludge. (f) Filling of new transformer oil in OLTC . (g)Tightening of all tapping leads and connections. (h)Refixing oftop plate of OLTC in original position after overhauling. (i)Electrical testing of manual/auto operation of OLTC. Note :- Transformer oil as required shall be measured and paid separately under respective item No 88 here-in-after as supply only.
29Material & labour for repair/overhauling of OLTC (On load tap changer )/diverter switch of 33KV/11KV Power transformer of capacities 12/16 MVA at site by carrying out following work of NGEF make :- (a)Opening of top plate of OLTC. (b) Draining out of transformers oil from the OLTC. (c)Stopping of leakage of oil from main shaft of OLTC including replacement of oil seal and all gasket of OLTC. (d)Checking /servicing of moving and fixed contact of OLTC and resistance test of contact. (e)Flushing of OLTC assembly with hot new oil and removing of sludge. (f) Filling of new transformer oil in OLTC . (g)Tightening of all tapping leads and connections. (h)Refixing of top plate of OLTC in original position after overhauling. (i)Electrical testing of manual/auto operation of OLTC. Note :-Transformer oil as required shall be measured and paid separately under respective item No 88 here-in-after as supply only.
30Material and labour for servicing /testing of line circuit breaker, control panelincluding outdoor CT, PT and relays in control panelof outdoor SF 6 Gas Circuit Breaker of capacity 1250/800 Amps and rating 36 KV complete as per details mentioned as under:- (a) Details of servicing of breaker :- (i) Checking of Closing/Tripping coil assembly (ii) Adjustment of mechanism if required. (iii) Clean the circuit breaker to remove dust and dirt. (iv) Apply a small amount of oil to rotary sections, sliding surfaces, pins, coupling section, etc.use grease for the operating shaft and bearings, and machine oil for other parts. (v) Check for rust and wear. (vi) Checking of spring charge mechanism (vii) Visual check for rust and deformation. (viii) Check for loosened bolts and nuts, broken spring washers and snap pins etc. (ix) Check for loosened connections, rust, damaged lead wires. (x) Checking of control circuit & tighten the connections if any. (xi) Check close & trip coil. (xii) Replacement of Dashpot/shock absorbers . (xiii) Replacement ofcarbon brush of spring charging motor (xiv) Cleaning of porcelain bushing (xv) Checking of limit switch
31(b) The following test shall be carried out:- (i) Primary Injection Test of outdoor CT / PT (ii) Closing & Opening Timing Test for all three poles. (iii) IR Test with megger in open and closed condition. (iv) Contact resistance test for all three poles (v) Closing coil resistance (vi) Tripping coil resistance. (c) Testing of following relays of control panelwith Secondary Injection Kit ,checking andprogramming of relay:- (i) Over current and earth fault relay (ii) Line differential relay (d) Testing of following Aux relay:- (i) DC Supply supervision relay. (ii) Trip Circuit supervision relay (ii) SF 6 gas pressure low. (iii) PT Fuse failure relay (iv) Master trip relay (v) Under voltage relay (vi) Over voltage relay
32Material and labour for servicing/testing of transformer circuit breaker, control panel including outdoor CT, PT and relays in control panel of outdoor SF 6 Gas Circuit Breaker of capacity 1250/800 Amps and rating 36 KV complete as per details mentioned as under:- (a) All as mentioned in item ser No 26(a) here-in-before (b) All as mentioned in item ser No 26(b) here-in-before
33(c) Testing of following relays of control panelwith Secondary Injection Kit ,checking andprogramming of relay:- (i) Over current and earth fault Relay (ii) Transformer differential relay (d) Testing of following Aux relay (i) DC supply supervision relay. (ii) CB SF 6 gas pressure low. (iii) Master trip relay (iv) Main Buchholz trip (v) Buchholz OLTC Trip (vi) SPR & PRV trip. (vii) Winding temp high trip (viii) Oil temp high trip. (ix) Main Buchholz alarm (x) Winding temp High alarm (xi) Low Oil level alarm (xii) Oil temp high alarm
34Material and labour for servicing /testing ofline breaker/control panelincluding outdoor CT, PT and relays in control panel of outdoor VCB of capacity 1250 Amps and rating 36 KV complete as per details mentioned as under:- (a) Details of servicing of breaker :- (i) Checking of Closing/Tripping coil assembly (ii) Adjustment of mechanism if required. (iii) Clean the circuit breaker to remove dust and dirt. The envelope of the vacuum interrupter and insulating materials shall be wiped with a clean cloth. (iv) Checking the contact for wear. Replace if the contact piece has worn out. (v) Apply a small amount of oil to rotary sections, sliding surfaces, pins, coupling section, etc.use grease for the operating shaft and bearings, and machine oil for other parts. (vi) Check for rust and wear. (vii) Checking of spring charge mechanism (viii) Visual check for rust and deformation. (ix) Check for loosened bolts and nuts, broken spring washers and snap pins etc. (x) Check for loosened connections, rust, damaged lead wires. (xi) Checking of control circuit & tighten the connections if any. (xii) Check close & trip coil. (xiii) Replacement of Dashpot/shock absorbers . (xiv) Replacement ofcarbon brush of spring charging motor (xv)Cleaning ofporcelain bushing (xvi)Checking of limit switch
35(b) The following test shall be carried out:- (i) Primary Injection Test of outdoor CT / PT (ii) Closing & Opening Timing Test for all three poles. (iii) IR Test with megger in open and closed condition. (iv) Contact resistance test for all three poles (v) Testing VCB bottle (vi) Closing coil resistance (vii) Tripping coil resistance. (c) Testing of following relays of control panel with Secondary Injection Kit ,checking andprogramming of relay:- (i) Over current and earth fault relay (d) Testing of following Aux relay (i) DCsupervision relay. (ii) Master trip relay. (iii) Voltage selection relay
36Material and labour for servicing /testing oftransformerbreaker/control panel including outdoor CT, PT and relays in control panel of outdoor MOCB of capacity 1250 Amps and rating 33 KV complete as per details mentioned as under:- (a) Details of servicing of breaker :- (i) Checking of oil level in each pole (ii) Checking of visible oil leaks (iii) Cleaning of porcelain bushings (iv) Checking of oil leakage from oil dash pot in operating mechanism (v) Checking of contact burning (vi) Cleaning and lubricating (vii) Checking/tightening of all electrical terminals and earth terminals and earth connections. (viii) Checking of auxiliary switch (ix) Checking of limit switches and friction clutch. (x) Checking of closing/tripping coils (xi) Checking of spring charging mechanism (xii) Adjustment of mechanism if required. (xiii) Check for rust and wear. (xiv) Visual check for rust and deformation. (xv) Check for loosened bolts and nuts, broken spring washers and snap pins etc.
37(xvi) Check for loosened connections, rust, damaged lead wires. (xvii) Checking of control circuit & tighten the connections if any. (xviii) Replacement of Dashpot/shock absorbers . (xix) Replacement of carbon brush of spring charging motor (b) All as mentioned in item ser No 26(b) here-in-before (c) All as mentioned in item ser No 26(c) here-in-before (d) All as mentioned in item ser No 26(d) here-in-before
38Material and labour for epoxy coatingon CT, PT, insulators in 11 KV VCB panels complete all as directed by Engr-in-charge
39Material and labour for servicing /testing ofbreaker/control panelincludingCT, PT and relays in control panelof VCB of capacity 2000 /800/630 Amps and rating 11 KVcomplete as details mentioned as under:- (a) Details of servicing of breaker :- (i) Adjustment of mechanism if required. (ii) Clean the circuit breaker to remove dust and dirt. The envelope of the vacuum interrupter and insulating materials shall be wiped with a clean cloth. (iii) Apply a small amount of oil to rotary sections, sliding surfaces, pins, coupling section, etc.use grease for the operating shaft and bearings, and machine oil for other parts. (iv) Check for rust and wear. (v) Check Spring Tension and pitting of the Cluster Contacts. (vi) Visual check for rust and deformation. (vii) Check for loosened bolts and nuts, broken spring washers and snap pins etc. (viii) Check for loosened connections, rust, damaged lead wires. (ix) Check whether the contacts are damaged by arcing.
40(x) Checking of control circuit & tighten the connections if any. (xi) Check close & trip coil. (xii) Checking of Jaw Contacts Conditions and repair/adjust. (xiii) Replace the jaw contacts,If required. (xiv) Improvement of resistance of epoxy insulator and epoxy body by applying post heated varnish. (xv) Replacement of Dashpot/shock absorbers . (xvi) Replacement ofcarbon brush of spring charging motor (b) The following test shall be carried out:- (i) Primary Injection Test of CT / PT (ii) Closing & Opening Timing Test for all three poles. (iii) IR Test with megger in open and closed condition. (iv) Contact resistance test for all three poles (v) Closing coil resistance (vi) Tripping coil resistance. (c) Testing of following relays of control panelwith Secondary Injection Kit ,checking andprogramming of relay:- (i) Over current and earth fault relay (d) Testing of following Aux relay (i) DC Supply supervision relay. (ii) Master trip relay
41S&F in replacement of closing coilassembly 50 volts DC of existingmake for SF 6 breaker of capacity 1250 amps of rating 36 KV complete all as specified and directed
42S&F in replacement of tripping coilassembly 50 volts DC of existingmake for SF 6 breaker of capacity 1250 amps of rating 36 KV complete all as specified and directed
43S&F in replacement of closing coilassembly 50 volts DC of existingmake for VCB of capacity 1250 amps of rating 36 KV complete all as specified and directed
44S&F in replacement of tripping coilassembly 50 volts DC of existingmake for VCB of capacity 1250 amps of rating 36 KVcomplete all as specified and directed.
45Material & labour for repair /servicing of marshalling box panel of 33KV/11KV Power transformer of capacities20 MVAincludingfollowing :- (a) Testing& repair to control wiring. (b) Testing ofOTI, WTI gauge/ meter matching with OTI, WTI indicator in RTCC panel. (c) Testing of fuse/ MCB (d) Replacement of gaskets& locks including preparation of old painted surfaces of steel by brushing/cleaning stain, greasy spots with thinner, applying two coats of spray painting (synthetic enamel paint) on all sides of etccomplete all as specified and directed.
46Material & labour for repair/servicing of marshalling box panel of 33KV/11KV Power transformer of capacities 16 MVAincluding following :- (a) Testing & repair to control wiring. (b) Testing of OTI, WTI gauge/meter matching with OTI, WTI indicator in RTCC panel. (c) Testing of fuse/MCB (d) Replacement of gaskets & locks including preparation of old painted surfaces of steel by brushing/cleaning stain, greasy spots with thinner, applying two coats of spray painting (synthetic enamel paint) on all sides of etc complete all as specified and directed.
47Material and labour for Preparation of old painted surfaces of steel by brushing/cleaning stain, greasy spots with thinner, applying two coats of spray painting (synthetic enamel paint) on all sides of 33 KV outdoorbrakerswith spraying machine including writing description of equipment in block English letter 50 mm high with white /black synthetic enamel paint complete all asdirected by Engr -in-Charge.
48Material and labour for Preparation of old painted surfaces of steel by brushing/cleaning stain, greasy spots with thinner, applying two coats of spray painting (synthetic enamel paint) on all sides ofTerminal Kiosk (TK) at 33 KV Yard with spraying machine including writing description of equipment in block English letter 25 mm high with white /black synthetic enamel paint complete all asdirected by Engr -in-Charge.
49Material and labour for preparation of old painted surfaces of 33 KV Switch yard including all outer steel structures/ frame/gate of bus bay at Grid, having dimensions 54 m x 11.5m x 9.5m and steel housing ofcapacitor bank having dimension 6m x 4.4m x 4m (incluiding top closed) by brushing/cleaning stains, greasy spots with thinner, applying two coats of spray painting (synthetic enamel paint) with spraying machine in the yard including writing description of equipments in block English letters 100 mm high with white/blacksynthetic enamel paint complete all asspecified and directed.
50Disconnecting power supply, preparation of old painted surfaces of steel by brushing/cleaning stain, greasy spots with thinner, applying two coats of spray painting (synthetic enamel paint) on all sidesof 33 KV16/20 MVA transformer and its accessories with spraying machine in the yard including writing description of equipment in block English letter 50 mm high with white/Black synthetic enamel paint and re-connection after painting complete all as specified and directed.
51All as per item No 41 here-in -beforebut capacity of powertransformer 16 MVA.
52Material & labour for cleaning of the bay/yard (82.5 RM x 26.5 RM) manually without damaging any equipments, cable or parts of the 33 KV Grid bays, removing of dusts/grass/herbs etc all as directed by Engr -in-charge.
53Material and labour for spreading of stone aggregate of nominal size not more than 40mm from the bay/yard manually without damaging any equipments, cable or parts of the 33 KV Grid bays, spreading & levelling of finished gravel uniformly in layers n. exc. 15 cm thick watered and rammed to true surface all as specified and directed
54M & L for cutting and removing grass, vegetation bushes etc from inside boundary wall and outside boundary wall of 33/11 KV Sub Stn, around 33 KV towersand removing all rubbish to a distance not exceeding 50 m as directed.
55M&L for Servicing & repairstoAir-break switch (isolator) off load, rotating type, 33 KV, 800 Amps to 1250 Amps capacity, with proper alignment of isolator rotatingblades, with fixed contact jaws, arcing horns, applying petroleum jelly to moving mechanism, cleaning and lubricatingto isolator gear box assembly,tightening all nuts, bolts and clamps of jumpers etc, repairing to isolator gear box assembly and making in proper serviceable condition for smooth functioning, testing and commissioningon load complete all as specified and directed.
56Supplying and fixing in repairs, male/moving contact/ rotating blade of HDE copper silver platedofAir Brake, off load isolator switch, rotating type, 33 KV, 1250/800 Amps capacitywith all fixing nuts, bolts etc complete all as specified and directed.
57Supplying and fixing in repairs, FixedContacts,madeof HDE copper,silver plated, of Air Brake, off load isolator switch, rotating type,33 KV, 1250/800 Amps capacitywith all fixing nuts, bolts etc. complete all as specified and directed.
58Supplying and fixing in replacement of terminal pad for Air Brake, off load isolator switch, rotating type, 33 KV, 1250/800 Amps capacity.
59Supplying and fixing in replacement of arching horn for Air Brake, off load isolator switch, rotating type, 33 KV, 1250/800 Amps capacity.
60Supply , installation, testing and commissioning in replacement of 33 KV air bake off load line isolator switch rotating type manually gear drive mechanism operated highest system voltage 36 KV rated current 1250 Amps triple polewith earthing device each pole consist of insulating pedestals 03 Nos on galvanized steel base as per BSS /IS incuding rotating blade of HDE copper and fixed contacts of same material , springloaded arcing horns of adequate sectionto brake magnetizing current of transformeras directed with adequate 50mm diaGI operating pipe for operation from ground level and operating handle complete with both off and on positions complete all as specified and directed.
61All as per item No 51 above but bus isolator without earthing device
62Supplying ,fixing , testing of master trip relay , 50/24 Volt DC in control panel including wiring and taking down old UNSV relay complete all as specified and directed.
63Supplying ,fixing , testing of Trip circuit supervision relay, 50/24 Volt DC in control panelincluding wiring and taking down old UNSV relay complete all as specified and directed.
64Supplying ,fixing , testing ofDC supervision relay, 50/24 Volt DC in control panel including wiring and taking down old UNSV relay complete all as specified and directed.
65Supplying ,fixing , testing ofSF 6 gas pressure supervisionrelay, 50/24 Volt DC in control panelincluding wiring and taking down old UNSV relay complete all as specified and directed.
66Supplying and fixing in replacementPT fusefor 11 KV/110 V PT complete as directed at site.
67Supply installation, testing and commissioning in replacement Potential Transformer (PT) oil cooled out door single phase ( Earthed type) of voltage ratio 33 KV/110 V class3P - 0.5-3, burden 50 VAinsulation level of 70/170 KV as specified below:- (a) Normal System Voltage-33 KV (b) Highest System Voltage-36 KV (c) Rated Primary voltage- 33 KV/v3 (d) Rated secondary voltage- 110 V/v3 (e) Nos of Lt winding 2 (f) Metering Core Accuracy class - 0.5 (g) Metering Core Rated Burden- 50 VA (h) Nos of Phase- Single (Earthed Type) (j) Protection core accuracy class - 3P (k) Protection core rated Burden - 50 VA (l) Rated Voltage Factor - 1.2 continuous & 1.5 for 30 Sec (m) Insulation Level- 36/70 KV.170 KVP (n) Temp rise at rated continuous thermal current over ambient at site -45 0C (o) Porcelain Bushing type - Hollow Cylinder (p) 1.2/50 micro second impulse withstand test vol -170 KV (Peak) (q) Creepage distance of HV bushing - 900 mm (min) (r) Primary & Secondary winding material - Copper
68Supply, installation, testing and commissioning in replacement 33 KV current transformer oil cooled out door single phase, oil immersed and self cooled type of ratio 800-400/1-1-1-1 suitable for metering and protection equipment installed on control panels terminal block as specified below :- (a) Normal System Voltage-33 KV (b) Highest System Voltage-36 KV (c) Rated Primary current- 800-400 Amp (d) Rated secondary current- 1 Amp (e) Nos of Core - 4 (f) Core01: Accuracy class 5P10, 10VA, ALF =10 (g) Core02: Accuracy Class 1.0, 10VA, ISF = 5 (h) Core 03Protection core accuracy class -PS,Protection knee point voltage- 300 Volt at lower ratio (j)Core 04-Spare (k) Continuous thermal current rating 120 % of rated primary current (l)Temp rise at rated contineous thermal current over ambient at site - Less than or equal to 45 degree C (m) Insulation Level- 36/70 KV.170 KVP (n) 1.2/50Micro second impulse withstand test voltage- 170 KV (peak) (o) Short time thermal current rating for one second - 25 KA/1 Second (p) Dynamic Current Rating - 62.5 KA ( peak) (q) Porcelain Bushing type - Hollow Cylinder (r) Creepage distance of HV bushing - 900 mm (min) (s) Primary & Secondary winding material - Copper
69M&L in replacement Earthing complete with galvanized steel earth plate electrode of size 60cmx60cmx6 mm thick, buried directly in ground (earth pit not less than 2.25 m below normal ground level) with top edge of earth plate not less than 1.5mbelow normal ground level, connected to galvanized strip 32mmby means of bolts, nuts, check nuts and washers of galvanised iron or steel as shown in electricalplate No 3 of SSR Part I, connected to earth test point and the equipment on the other nuts and washers of galvanised iron side complete all as specified, including testing and commissioning complete all as directed. Note :- (a) The unit rates quoted against this item shall be deemed to include the cost of excavation and earth work in soft/loose soil, common salt & charcoal dust in alternate layers, PCC 1:3:6 type C2as in pit, precast RCC 1:2:4 type B-1 with necessary reinforcement 6mm dia both waysas in cover & frame for pit, funnel, watering pipe 20 mm bore GI pipe light grade, protection pipe 40 mm bore GI pipe medium grade etc. (b)The quoted rates shall also deemed to include the cost of earth test point and earth strip/GIlead wire and protection pipe upto 7.5 meter beyond the earth plates electrode.
70S&F steel structure with ISMB/Channel/Angle iron/flat, clamps and back plates fabricated from structural steel sections including nuts, bolts, washers,welding, bending cold or hot,drilling holes for bolts, in any shape or size as indicated or directed and inclusive of one primer coat, one under coat and one finishing coat of synthetic enamel paint at 33 KV yard for fixing of isolator/CT/PT and for fixing of GO/DO etc complete as directed by Engr-In-Charge.
71Supply and laying PVC insulated PVC sheathed cable galvanized steel strip or wire armoured electric control cables (Heavy duty) with stranded Copper conductor of size 2.5 sq mm 10 core 1100 Volts grade complete all as specified and directed.
72All as per item No. 62 above but 2.5 sqmm 6 core copper conductor.
73M&L for Bore earthing 150 mm dia buried by vertical boring machine, depth 50 mtr below ground level using earth electrode 50mm dia GI pipe medium grade duly drilled hole of 12mm dia, 115mm C/C on both side of the pipe including lowering in bore well upto the depth of 49 mtr and one mtr above the ground level. The pipe electrode should be filled around commercial salt charcoal dust, copper sulphate and magnesium phosphate of 30 cm layer each upto the full length of pipe. The borewell should have 12 mtr of length 150mm dia MS pipe for protection of borewell. Welding of GI Strip 50mmx6mm on earth electrode GI Pipe 50mm dia upto 10mtr below ground level and 15 mtr from the bore well to test point gun metal and PCC foundation surrounding the borewell 60cmx60cmx30cm all as directed by Engr-in-charge. GI strip more than 25mtr will be measured and paid separately. Note :- Cost of gun metal test point deemed to be included in the quoted rate.
74Taking out of heavy duty cooling fan ,3 phase, 50 Hzof size 600mm form power transformer 33/11 KV of capacity12/16 MVA,servicing of the fan by opening including cleaning, greasing , replacement of defective spares parts such asbearing/ bushing, capacitor, canopy, clamp, blade, etc with new one and painting of fan body with synthetic enamel paint and re-assembling in same position after repairs and testing complete all as directed by Engr-in-Charge. Note :- (a) The cost of spare parts deemed to be included in quoted rates . (b)Rewinding of the fan will be measured and paid separately under respective item of schedule here-in-after.
75All as per item No 65here-in before but of size 450mm from power transformer 33/11 KV of capacity 16/20 MVA
76M&L for Rewinding ofheavy duty cooling fan, 3 phase, 50 Hzof size 600mmof power transformer 33/11 KV capacitywith super enamelled copper wire as per existing gauge including heating, varnishing, etc complete as required and directed.
77All as per item No 67here-in before but of size 450mm
78Supplying, installation, commissioning and testing in replacement of 11 KV Current Transformer (CT`s), indoor type, epoxy cast bar Primary typehaving ratio 1200/600/5-5-5 Amps, core -1, Class 10 P20, 15 VA for protection, Core 2 Class 0.5, 15 VA for metering, core -3 for differential protection, Short circuit time rating 18.4 kA for 3 Sec including associated wiring including taking down old unserviceable CTs complete all as specified and directed.
79Supplying, installation, commissioning and testing in replacement of 11 KV Current Transformer (CT`s), indoor type, epoxy cast bar Primary typehaving ratio800/400/5-5-5 Amps , core -1, Class 10 P20 , 15 VA for protection , Core 2 Class 0.5 , 15 VA for metering including associated wiring including taking down old unserviceable CTs complete all as specified and directed.
80Supplying, installation, commissioning and testingof 11 KV Current Transformer (CT`s), indoor type, resin cast epoxy type,of 13.1 KA/Sec having ratio 300/150/5-5 Amps having Core1: Class 5P10, 10VA for protection , Core2: Class 0.5, 10VAfor metering andassociated wiringincluding taking down old unserviceable CTs complete all as specified and directed.
81Supplying, installation, commissioning and testingof 11 KV Current Transformer (CT`s), indoor type, resin cast epoxy type,of 13.1 KA/Sec having ratio 250/125/5-5 Amps having Core1: Class 5P10, 10VA for protection , Core2: Class 0.5, 10VAfor metering andassociated wiringincluding taking down old unserviceable CTs complete all as specified and directed.
82S&F in replacement of vacuum interrupter suitable for1250 amps, 11 KV HT VCB complete all as specified and directed
83Supplying, laying, jointing testing and connecting in replacement , XLPE insulated, screened, PVC bedded, galvanised steel strip or wire armoured,electric power cable (heavy duty) with multistranded aluminium conductors, 33 KV (E)grade, of size400 Sq mm, 3 core, laid in trenches complete all as specified & directed.
84All as per srl item No 74 here-in- before but size of cable 300 Sqmm , 3 core
85Supplying, laying, jointing testing and connecting in replacementXLPE insulated, screened, PVCbedded, galvanised steel strip or wire armoured,electric power cable (heavy duty) with multistranded aluminium conductors, 11 KV grade, IS 7098marked, suitable for HT 11 KV(E) systemlaid in trenchesfixed to pole, including jointing & testing of size 240 Sqmm 3 core complete all as specified and directed. Location : Khyber Grid to Manekshaw Centre Note for Item No 74,75 & 76 :-Excavation, earth work ,cable protection , sand fillings , cable joint shall be measured and paid separately under respective Item No 77 to 84.
86Excavation in trenches not exc. 1.5 m wide and not exc 1.5 mtr deep in soft/loose soil for laying / taking up/ taking down of cables and getting out and levelling of bottom surface to required level all as specified and directed by Engineer- in- Charge.
87Returning filling in,. Including spreading, levelling,. Watering and well ramming soil in layers not exceeding 25 cm thick all as specified and directed.
88Removing excavated material (ie soil) from site to a distance n. exc 50 mtrs away and depositing where directed at a level n. exc. 1.5 mtr above the starting point all as specified and directed by Engineer-in-Charge.
89Material and labour for river washed and screened, dry sand for filling in trenches below and around underground cables for cushioning of cables etc, complete all as specified. Note :- Measurement shall be taken after punning down.
90Supplying & laying reinforced precast concrete cable cover, class EHV, type 1 with peak, size 450mm x 230mm x 50mm in trenches for protecting under ground cable as per IS (for 33 KV Cable) complete all as specified and directed.
91All as per srl item No 81 here-in-before but using old reinforced precast concrete cable cove obtained under srl item No 77 here in before.
92Supplying and laying un-reinforced precast concrete cable cover, class HV, type 1, flat size 300mmx 180mm x 40mm.
93All as per srl item No 83here-in-before but using old un-reinforced precast concrete cable cover obtained under srl item No 77 here in before.
94Material & labour for repair /servicing of RTCC panel of OLTC control panel of 33KV/11KV Power transformers of capacities 16/20MVA including repair /replacement to control wiring, repair to operation of OLTC from RTCCand checkingof followingand testing complete all as specified and directed :- (a) Digital Winding temp meter. (b) Digital oil temp meter. (c) Digital remote tap position indicator. (d)Indicator lamps. (e)Space Heater. (f) Fan auto working switch. (g)Analog to digital convertor and other spares required for displaying winding and oil temp.
95All as per item ser No 85here-in-before but 33KV/11KV Power transformers of capacities 12/16MVA
96M&L for ON load Centrifuging and dehydration includingfiltration and cleaning of transformer oil by dehydration machine of 11/0.433 KV transformer installed at various site on plinth/4/6 pole structure of any capacityand topping up deficient transformer oil including testing of samples before and after dehydration and filtration complete all as specified and directed. Note :-Deficient quantity of Transformer oil required for top up shall be measured and paid separately under item No13here-in -after as supply only.
97Supply only transformer oil of approved quality as per IS having dielectric strength of 45-60 KV in 2.5mm gap for filling in transformer or for topping up as required and directed.
98S&F in replacement silica gel with breather assembly, suitable for power transformer 33KV/11KV of 16/20 MVA capacity complete all as specified and directed
99Supply and filling in replacement silica gel in breather oftransformer complete all as directed
100Supply andfix Cable jointing kit for 11 KV (Earthed) grade cable for straight through heat shrink type joint complete with jointing material and accessories suitable for 3 core XLPE armoured aluminium conductor cable ofsize 185 Sqmm.
101Supply andfix Cable jointing kit for 11 KV (Earthed) grade cable for indoor termination heat shrink type joint complete with jointing material and accessories suitable for 3 core XLPE armoured aluminium conductor cable of size 185Sqmm .
102Boring of holes under road, pavement, hard standing by trenchless technology using ultra sounding technique and necessary machine including HDPE pipe of200 mm dia suitable for 0.6 mpa working pressure
103Material and labour for servicing /testing of33 KV GIS (Gas Insulated System breaker Panel )includingCT, PT and relays in control panelof 33 KV VCB of capacity 1250 Amps rating 36 KVcomplete as details mentioned as under:- ( Incomer -02, C&R Panel -01, O/G Panel -02 ) (a) Details of servicing of breaker :- (i) Adjustment of mechanism if required. (ii) Clean the circuit breaker to remove dust and dirt. The envelope of the vacuum interrupter and insulating materials shall be wiped with a clean cloth. (iii) Apply a small amount of oil to rotary sections, sliding surfaces, pins, coupling section, etc.use grease for the operating shaft and bearings, and machine oil for other parts. (iv) Check for rust and wear. (v) Check Spring Tension and pitting of the Cluster Contacts. (vi) Visual check for rust and deformation. (vii) Check for loosened bolts and nuts, broken spring washers and snap pins etc. (viii) Check for loosened connections, rust, damaged lead wires. (ix) Check whether the contacts are damaged by arcing. (x) Checking of control circuit & tighten the connections if any. (xi) Check close & trip coil. (xii) Checking of Jaw Contacts Conditions and repair/adjust. (xiii) Replace the jaw contacts,If required. (xiv) Improvement of resistance of epoxy insulator and epoxy body by applying post heated varnish. (xv) Replacement of Dashpot/shock absorbers . (xvi) Replacement ofcarbon brush of spring charging motor
104(b) The following test shall be carried out:- (i) Primary Injection Test of CT / PT (ii) Closing & Opening Timing Test for all three poles. (iii) IR Test with megger in open and closed condition. (iv) Contact resistance test for all three poles (v) Closing coil resistance (vi) Tripping coil resistance. (c) Testing of following relays of control panelwith Secondary Injection Kit ,checking andprogramming of relay:- (i) Over current and earth fault relay (d) Testing of following Aux relay (i) DC Supply supervision relay. (ii) Master trip relay
105Material & labour for repair /overhauling of OLTC ( On load tap changer ) of 33KV/11KV Power transformerof capacities8/10 MVAat siteby carried outfollowing work of BBL make :- (a)Opening of top plate of OLTC. (b) Draining out of transformers oil from the OLTC. (c)Stopping of leakage of oil from main shaft of OLTC including replacement of oil seal and all gasket of OLTC. (d)Checking /servicing of moving and fixed contact of OLTC and resistance test of contact. (e)Flushing of OLTC assembly with hot new oil and removing of sludge. (f) Filling of new transformer oil in OLTC . (g)Tightening of all tapping leads and connections. (h)Refixing oftop plate of OLTC in original position after overhauling. (i)Electrical testing of manual/auto operation of OLTC. Note :- Transformer oil as requiredshall be measured and paid separately under item No 88here-in -before as supply only.
106Material & labour for repair /servicing of marshalling box panel of 33KV/11KV Power transformer of capacities8/10 MVAincludingfollowing :- (a) Testing& repair to control wiring. (b) Testing ofOTI, WTI gauge/ meter matching with OTI, WTI indicator in RTCC panel. (c) Testing of fuse/ MCB (d) Replacement of gaskets& locks including preparation of old painted surfaces of steel by brushing/cleaning stain, greasy spots with thinner, applying two coats of spray painting (synthetic enamel paint) on all sides of etccomplete all as specified and directed.
107Disconnecting power supply, Preparation of old painted surfaces of steel by brushing/cleaning stain, greasy spots with thinner, applying two coats of spray painting (synthetic enamel paint) on all sidesof 33 KV8/10MVA transformer and its accessories with spraying machine in the yard including writing description of equipment in block English letter 50 mm high with white/Black synthetic enamel paint and re-connection after painting complete all as specified and directed.
108Taking out of heavy duty colling fan ,3 phase, 50 Hzof size 450 mm form power transformer 33/11 KV of capacity8/10 MVA,servicing of the fan by opening including cleaning, greasing , replacement of defective spares parts such asbearing/ bushing, capacitor, canopy, clamp, blade, etc with new one and painting of fan body with synthetic enamel paint and re-assembling in same position after repairs and testing complete all as directed by Engr-in-Charge. Note :- (a) The cost of spare parts deemed to be included in quoted rates . (b)Rewinding of the fan will be measured and paid separately under respective item of schedule here-in-after.
109M&L for Rewinding ofheavy duty colling fan, 3 phase, 50 Hzof size 450 mm of8/10 MVApower transformer 33/11 KV capacitywith super enamelled copper wire as per existing gauge including heating, varnishing, etc complete as required and directed.
110Supply and fixing in replacement of ACB 4 Pole 800 Amps,50 KA415 Volt, Horizontal , Manual draw out type motorized, front operated with microprocessor based LCD protection release and adjustable over current and earth fault protection complete all as specified and directed.
111Supply and fixing in replacement of ACB 4 Pole , 1250 Amps,50 KA415 Volt, Horizontal draw out type motorized, front operated with microprocessor based LCD protection release and adjustable over current and earth fault protection
112Supply and fixing for fabrication ofBus bar duct(Length 28 Mtr)size 300 mm x 500 mm complete with Aluminium busbar of rating 1250 Amps , size 100 mm x 12.5 mm, complete withnut and bolts withassy complete all as specified and directed.
113Supply and fixing of AluminiumBus bar100 mm x 12.5 mm of rating 1250 Amps for existing03 Nos ACB Panelsincluding including nut, bolts with assembly complete all as specified and directed.
114(xi) All existing earthing of the lifts shall be maintained and made fully functional by the contractor to the entire satisfaction of the Engr-in-Charge.
Disclaimer :
We takes all possible care for accurate & authentic tender information, however Users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender.
Tell us about your Product / Services,
We will Find Tenders for you

Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy

For Tender Information Services Visit : TenderDetail