Tender For Construction Of Bridge Along Venkadesalapuram – Therkku Seliyanallur Roadacross Ulagamman Odai In Pirancheripanchayatin Manur Panchayat Union In Tirunelveli Districtunder Nabard Ridf Xxix., tirunelveli-Tamil Nadu

Rural Development And Panchayats Department has published Tender For Construction Of Bridge Along Venkadesalapuram – Therkku Seliyanallur Roadacross Ulagamman Odai In Pirancheripanchayatin Manur Panchayat Union In Tirunelveli Districtunder Nabard Ridf Xxix.. Submission Date for this Tender is 03-01-2024. Bridge Work Tenders in tirunelveli Tamil Nadu. Bidders can get complete Tender details and download the document.




Tender Notice

41087789
Corrigendum : Tender For Construction Of Bridge Along Venkadesalapuram – Therkku Seliyanallur Roadacross Ulagamman Odai In Pirancheripanchayatin Manur Panchayat Union In Tirunelveli Districtunder Nabard Ridf Xxix.
Open Tender
Indian
Tamil Nadu
tirunelveli
03-01-2024

Tender Details

Construction Of Bridge Along Venkadesalapuram – Therkku Seliyanallur Roadacross Ulagamman Odai In Pirancheripanchayatin Manur Panchayat Union In Tirunelveli Districtunder Nabard Ridf Xxix. ; 1 ) Construction Of Bridge Along Venkadesalapuram – Therkku Seliyanallur Roadacross Ulagamman Odai In Pirancheripanchayatin Manur Panchayat Union 2 Earthwork Excavation In All Classes Of Soilexcept Hard Rock Requiring Blasting And Depositing On Bank With All Leads And Lifts As Per Ss20b, Including Cost Of All Labour, Equipments And All Incidental Charges Such As Baling Our Water, Providing And Maintaining Necessary Cofferdams, Sheeting, Shoring Bracing And Their Subsequent Removal, Removal Of All Logs, Stumps, Grubs And Other Deleterious Matter And Obstructions, Trimming Bottom Of Excavation Backfilling, And Clearing The Site And Disposal Of All Surplus Materials Etc., Complete As Per Relevant Standard Specification For Dressing The Bed Up To Sill Level. 3 Earthwork Excavation In All Classes Of Soil Except Soft Rock Not Requiring Blasting And Hard Rock Requiring Blasting And Depositing On Bank With All Leads And Lifts As Per Ss20b, Including Cost Of All Labour, Equipments And All Incidental Charges Such As Baling Our Water, Providing And Maintaining Necessary Cofferdams, Sheeting, Shoring Bracing And Their Subsequent Removal, Removal Of All Logs, Stumps, Grubs And Other Deleterious Matter And Obstructions, Trimming Bottom Of Excavation Backfilling, And Clearing The Site And Disposal Of All Surplus Materials Etc., Complete As Per Relevant Standard Specification For Foundation Of Abutments, Piers And Wings. 4 Earthwork Excavation In Soft Disintegrated Rock Not Requiring Blastingexcept Medium Rock And Hard Rock Requiring Blasting And Depositing On Bank With All Leads And Lifts As Per Ss20b, Including Cost Of All Labour, Equipments And All Incidental Charges Such As Baling Our Water, Providing And Maintaining Necessary Cofferdams, Sheeting, Shoring Bracing And Their Subsequent Removal, Removal Of All Logs, Stumps, Grubs And Other Deleterious Matter And Obstructions, Trimming Bottom Of Excavation Backfilling, And Clearing The Site And Disposal Of All Surplus Materials Etc., Complete As Per Relevant Standard Specification For Foundation Of Abutments, Piers And Wings. 5 Vibrated Cement Concrete Of Grade M-10, Nominal Mix, 1:3:6, Using 40Mm Iss Hbg Metal Including Cost And Conveyance Of All Materials To Site Including Cement At Site Including Cost Of Formwork, Soft Water, Labour Charges For Mixing, Transporting, Laying And Curing Concrete, Working At Depths, Tools And Plants And Incidental Charges Such As Maintaining Of Protective Bunds, Cofferdams, Shoring, Strutting Etc; Complete As Per Relevant Standard Specification, Etc, Complete As Per Relevant Standard Specification For Rigid Apron. 6 Vibratedcement Concrete Of Grade M20 Design Mix Using 20Mm &12Mm Iss Size Hbg Graded Metal Including Cost And Conveyance Of All Materials To Site Including Cost Of Cementat Siteincluding Cost Of Formwork, Soft Water, Labour Charges For Mixing, Transporting, Layingand Curing Concrete , Working At Depths , Tools And Plants And Maintaining Of Protective Bunds, Cofferdams, Shoring, Strutting Etc., Complete As Per Relevant Standard Specifications, For Footings Of Abutment, Piers And Wings Below Sill Level. 7 Vibratedcement Concrete Of Grade M20 Design Mix Using 20Mm &12Mm Iss Size Hbg Graded Metal Including Cost And Conveyance Of All Materials To Site Including Cost Of Cementat Siteincluding Cost Of Formwork, Soft Water, Labour Charges For Mixing, Transporting, Layingand Curing Concrete , Working At Depths , Tools And Plants And Including All Other Incidental Charges Etc; Complete As Per Relevant Standard Specifications, For Substructure Of Abutments, Wings, And Piers Above Sill Level. 8 Vibratedreinforced Cement Concrete Of Grade M30 Design Mix Using 20Mm &12Mm Iss Size Hbg Graded Metal Including Cost And Conveyance Of All Materials To Site Including Cost Of Cementat Siteincluding Cost Of Formwork, Soft Water, Labour Charges For Mixing, Transporting, Layingand Curing Concrete , Working At Depths , Tools And Plants Including All Other Incidental Charges Etc; Complete As Per Relevant Standard Specifications, For Dirt Wall Cum Bed Block Over Abutments And Bed Block Over Piers. 9 Providing And Fixing Seepage Pipes Of 100Mm Dia. Pvc Pipes Of Required Lengths For Abutments And Wngs Including Cost And Conveyance Of All Materials To Work Site, Cost And Labour For 900Mm Dia. Semi-Spherical Back Fill Arrangements With 100Mm Size Broken Granite Chips At The Periphery And Labour Charges For Fixing, Etc., To Drain Of The Backfill In The Abutments And Wings. 10 Providing And Fixing Kraft Paper For Full Width Of Seating Of Deck Slab Andincluding Cost And Conveyanceto Work Site, Labour Charges For Fixing The Same In The Correct Position And All Other Incidental Charges Et., Complete. 11 Vibratedreinforced Cement Concrete Of Grade M35 Design Mix Usingiss Size Hbg Graded Metal Including Cost And Conveyance Of All Materials To Site Including Cost Of Cementat Siteincluding Cost Of Formwork, Soft Water, Labour Charges For Mixing, Transporting, Layingand Curing Concrete , Working At Depths , Tools And Plants Including All Other Incidental Charges Etc; Complete As Per Relevant Standard Specifications, For Deck Slab. 12 Providing Filter Media Behind The Abutments And Wings With Clean Iii Graded Material 53Mm To 5.6Mm To 600Mm Thick Andwell Compacted In Layerswith Smaller Sized Towards The Soil And Bigger Size Towards The Wall Including Cost And Conveyance To Work Site Includingall Labours And Other Incidental Charges Including Hire Charges For Tools And Plants Employed Etc., For Filter Media As Per MostS ( Roads Wing ) Specifications For Roads And Bridges Fourth Revision Cl. 309-3-2-13 And 305 -4-4 Etc., Complete. 13 Filling Behind Abutmants And Wings With Clean Gritty Gravel Including Cost And Conveyance Of Gravel To Worksite, Laying, Handling Charges And Filling In Layers, Tamping Under Optimum Moisture Content To Get The Maximum Density Including Watering, With All Leads For Water And All Other Incidental Charges Etc, Complete For Filling Behind The Abutment And Wings. 14 Providing And Fixing Pvc Expansion Joint In Between Deck Slabs Over Abutment And Pier As Shown In The Drawing Including Cost And Conveyence Of Expansion Joints Including Shalimar Pad And Joint Sealent Etc, Complete. 15 Supply And Fabrication Of Fe-500 Steel Required For All Rcc Items Of Works Involved In The Schedule Cost Of Steel At Site Fabrication, Labour Charges For Cleaning The Rods Straightening, Cutting, Bending, Tying Grills, Including Overlapping To The Required Length Whenever Necessary And Placing The Reinforcement In Position As Specified In The Drawings, Including Cost Of Binding Wire, Provision Of Spacer Bars, Cover Blocks And All Other Incidental Charges Etc, Complete, Fe-500 Grade-1 Mt 16 Vibrated Cement Concrete M15 Grade, Nominal Mix 1:2:4, Using 20Mm Iss Hard Granite Broken Metal Including Cost And Conveyance Of All Materials To Site And Cement At Site Including Cost Of Formwork, Lead For Soft Water, Labour Charges For Mixing , Transporting, Laying, And Curing Concrete Working In Heights And Hire Charges For Tools And Plants, And All Other Incidental Charges Etc Complete As Per Relevant Specification For Base Course Below Approaches. 17 Vibrated Reinforced Cement Concrete M30 Design Mix Using 20Mm &12Mm Iss Graded Hard Granite Broken Metal Including Cost And Conveyance Of All Materials To Site Including Cement At Site Including Labour Charges For Mixing, Laying, Curing Concrete, Working At Heights, Hire Charges For Tools And Plants, Including All Other Incidental Chages Etc., Complete For Approach Slab. 18 Vibrated Cement Concrete M30 Design Mixusing 25, 12 & 6Mm Iss Size Hbg Graded Metal Including Cost And Conveyance Of All Materials To Worksite And Cement At Site Including All Labour Charges For Fixing Concrete, Laying, Vibrating, Hire Charges For Tools And Plants, Compacting, Curing With All Leads For Soft Water, Including All Other Incidental Charges, Formwork, Cost Of Premoulded Expansion Joints And Fixing The Same In Position Etc., Complete For Wearing Coat Over Deck Slab And Approach Slab. 19 Vibrated Reinforced Cement Concrete M-25, Grade, Design Mix Using 20Mm &12Mm Iss Size Hard Granite Broken Graded Metal Including Cost And Conveyance Of All Materials To Site Including Cement At Site But Excluding Cost And Fabrication Of Steel, Including Labour Charges For Mixing, Transporting, Laying, And Curing Concrete, Working At Heights, Hire Charges For Tools And Plants, Including All Other Incidental Charges, Etc, Complete For Rcc Hand Rails And Posts Over Deck Slab. 20 Vibrated Cement Concrete M20 Grade, Nominal Mix Using 20Mm &12Mm Iss Size Hard Granite Broken Metal Including Cost And Conveyance Of All Materials To Site And Cement At Site Including Labour Charges For Mixing, Transporting, Laying, And Curing Concrete, Working At Heights, Hire Charges For Tools And Plants, Including All Other Incidental Charges, Etc., Complete As Per Standard Specification For Pccparapets Over Wings. 21 Providing And Fixing Of Cast Iron Drainage Spouts 100Mm Dia As Per Most Drawing Sd / 205 With Grating Arrangements At Top As Shown In The Drawing Using 12Mm X 25Mm Flats For Grating Arrangements, And 100Mm Dia Drainage Spout Projecting Beyond The Bottom Of Deck Slab As Shown In The Drawing Including Cost And Conveyance Of Cast Iron Pipes And Flats And Fixing Them In Position Etc, Complete. 22 Dismantling 23 Dismantling Theexisting Pccin The Existing Bridge And Clearing Away From The Work Site And Carefully Stacking The Useful Materials For Reuse On The Road Side As Directed By The Departmental Officers Including All Labour And Incidental Charges Etc., Complete . Side Wall. 24 Dismantling Theexisting Pccin The Existing Bridge And Clearing Away From The Work Site And Carefully Stacking The Useful Materials For Reuse On The Road Side As Directed By The Departmental Officers Including All Labour And Incidental Charges Etc., Complete. Wearing Coat 25 Approach Road ( Sub Estimate ) 26 Excavationincludingremovalandsatisfactorydisposal Ofallmaterialsnecessaryfortheconstructionof Road Wayandsidedrainsin Accordancewithspecifications Andthelines, Gradesandcross Sectionsshownin Thedrawingsor As Indicatedby The Engineer Usingcarted Eathwithaleadof3kmforformationofapproach Road. 27 98% Compaction 28 100% Compaction 29 Providing And Laying Granular Sub Base As Per Table No 400-1 / 400-2 And Gradung Iii Of Morth Revison Iv With And Any Other Granular Material Or A Combination Those Of For 150 Mm Thick To Give A Cbr Of 20 On Prepared Sub Grade In Accordance With The Requirements Of The Specifications For Sand , Gravel & 6Mm Aggregate Mix 30 Provding And Laying Water Bound Macadam Grading - Ii Consisting Of Clean Crused Aggregates Mechanically Interlocked By Rolling And Bonding Together With Screening Binding Materials And Finised In Acordance With The Requirements Of The Specifications And T 31 Provding And Laying Water Bound Macadam Grading - Iii Consisting Of Clean Crused Aggregates Mechanically Interlocked By Rolling And Bonding Together With Screening Binding Materials And Finised In Acordance With The Requirements Of The Specifications And 32 Proivding And Laying Of Prime Coat Usingemulsion Bitumen At The Rate Of 7.00Kg / Sq.Mover The Wbm Surfacepreparatoryto Another Construction Over It. 33 Proivding And Laying Of Tack Coat Usingemulsion Bitumen At The Rate Of 2.50Kg / Sq.Mover The Wbm Surfacepreparatoryto Another Construction Over It. 34 Providing Laying And Compacting Open Graded Premix Carpet 20Mm Thick With A Liauid Seal Coat Which Is Shall Consist Of Open Graded Carpet Of 20Mm Thickness In A Single Course Composed Of Suitable Small Sized Aggregated Premixed With Bituminous Binder With Application Of Lquid Seal Coat For Sealing The Viods In A Bituminous Surface Conforming To The Specifications. 35 Providing And Laying Of Gravel For Berms Including Cost And Conveyance Of All Materials To Site And All Labour Charges For Spreading, Levelling And Watering Etc., Complete 36 Construction Of Retaining Wall 37 Earthworkexcavationinallclassesofsoilexcepthard Rockrequiringblastinganddepositingonbankwithall Leadsandliftsasperss20b, Includingcostofalllabour, Equipments Andall Incidentalcharges Such As Baling Out Water, Providing And Maintaining Necessary Cofffer Dams, Sheeting, Shoring, Bracingandtheirsubsequentremoval, Removalofalllogs, Stumps, Grubsandotherdeleterious Matterandobstructions, Trimmingbottomofexcavation, Backfilling, And Clearing The Site And Disposal Of All Surplus Materialsetc., Completeasperrelevantstandard Specifications Forfoundation Under Retaing Wall. 38 Filling Inside The Foundation With Clean Coarse Sand Including Cost And Conveyance Of Gravel To Worksite, Laying, Handlingchargesandfillinginlayers, Tamping Underoptimummoisturecontenttogetthemaximum Density Including Watering With All Leads For Water And All Other Incidental Charges Etc., Complete For Filling Inside The Foundation. 39 Vibratedcementconcreteofgradem15using20mm Size Hbgmetal Including Cost And Conveyance Ofall Materials To Site Including Cost Of Cement At Site Including Costofformwork, Softwater, Labourchargesfor Mixing, Transporting, Laying And Curing Concrete, Working At Depths, Toolsandplantsandmaintainingofprotective Bunds, Cofferdams, Shoring, Strutting Etc., Complete As Per Relevant Standard Specifications For Foundation Below. 40 Vibrated Cementconcretegradem20using20&10 Mm Iss Size Hbg Graded Metal Including Cost And Conveyance Of All Materials To Site And Cement At Site But Excludingcost Andfabrication Of Steel But Including Form Work And Centeringsoft Waterlabour Charges For Mixing, Transporting, Placing In Position, Vibrating And Compacting Finishing And Curing Concrete Working Atheights, Hire Charges For Tools And Plants, Including All Other Incidental Chargesetc., Completeasperstandardspecificationsfor Retaining Wall Foundation. 41 Vibratedcement Concrete Of Grade M 20 Using 20 Mm & 10 Mm Iss Size Hbg Metal Including Cost And Conveyance Ofallmaterialstositeincludingcostofcement Atsite Including Cost Of Formwork, Soft Water, Labour Charges For Mixing, Transporting, Layingand Curing Concrete , Working At Depths , Tools And Plants And Including All Other Incidental Charges Etc; Complete As Per Relevant Standard Specifications, Forsubstructureofretainingwall Above Sill Level - 42 Providingandfixingseepagepipesof100mmdia.Pvc Pipes Of Required Lengths For Retaining Wall Including Cost Andconveyanceofallmaterialstoworksiteandlabour Charges For Fixing, Complete 43 Gst Amount For Providing Service To Government Contract Works For The Above Construction Works. { Gst Amount Is The Total Gst Amount For Total Overall Quoted Amount Above This Row In Column Bb For All Works In This Package }

Corrigendum Details

Sr No CorrigendumDate Corrignedum CorrigendumType NewSubmissionDate
1 27-Dec-2023 Tender date corrigendum Date 03-01-2024

Key Value

Document Fees
Refer document
EMD
INR 167000.0 /-
Tender Value
Refer document

BOQ Items

Name of the Work: Construction of Bridge along Venkadesalapuram – Therkku Seliyanallur roadacross Ulagamman Odai in PirancheriPanchayatin Manur Panchayat union in Tirunelveli Districtunder NABARD RIDF XXIX
Sl. No. Item Description
11) Construction of Bridge along Venkadesalapuram – Therkku Seliyanallur roadacross Ulagamman Odai in PirancheriPanchayatin Manur Panchayat union
2Earthwork excavation in all classes of soilexcept hard rock requiring blasting and depositing on bank with all leads and lifts as per SS20B, including cost of all labour, equipments and all incidental charges such as baling our water, providing and maintaining necessary cofferdams, sheeting, shoring bracing and their subsequent removal, removal of all logs, stumps, grubs and other deleterious matter and obstructions, trimming bottom of excavation backfilling, and clearing the site and disposal of all surplus materials etc., complete as per relevant standard specification for DRESSING THE BED UP TO SILL LEVEL.
3Earthwork excavation in all classes of soil except Soft Rock not requiring blasting and hard rock requiring blasting and depositing on bank with all leads and lifts as per SS20B, including cost of all labour, equipments and all incidental charges such as baling our water, providing and maintaining necessary cofferdams, sheeting, shoring bracing and their subsequent removal, removal of all logs, stumps, grubs and other deleterious matter and obstructions, trimming bottom of excavation backfilling, and clearing the site and disposal of all surplus materials etc., complete as per relevant standard specification for FOUNDATION OF ABUTMENTS, PIERS AND WINGS.
4Earthwork excavation in Soft Disintegrated rock not requiring blastingexcept medium rock and hard rock requiring blasting and depositing on bank with all leads and lifts as per SS20B, including cost of all labour, equipments and all incidental charges such as baling our water, providing and maintaining necessary cofferdams, sheeting, shoring bracing and their subsequent removal, removal of all logs, stumps, grubs and other deleterious matter and obstructions, trimming bottom of excavation backfilling, and clearing the site and disposal of all surplus materials etc., complete as per relevant standard specification for FOUNDATION OF ABUTMENTS, PIERS AND WINGS.
5Vibrated Cement Concrete of Grade M-10, Nominal Mix, 1:3:6,using 40mm ISS HBG metal including cost and conveyance of all materials to site including cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete, working at depths, Tools and Plants and incidental charges such as maintaining of protective bunds, cofferdams, shoring, strutting etc; complete as per relevant standard specification, etc, complete as per relevant standard specification for RIGID APRON.
6VibratedCement Concrete of grade M20 Design Mix using 20mm &12mm ISS size HBG graded metal including cost and conveyance of all materials to site including cost of cementat siteincluding cost of formwork, soft water, labour charges for mixing, transporting, layingand curing concrete , working at depths , tools and plants and maintaining of protective bunds, cofferdams, shoring, strutting etc., complete as per relevant standard specifications, for FOOTINGS OF ABUTMENT, PIERS AND WINGS BELOW SILL LEVEL.
7VibratedCement Concrete of grade M20 Design Mix using 20mm &12mm ISS size HBG graded metal including cost and conveyance of all materials to site including cost of cementat siteincluding cost of formwork, soft water, labour charges for mixing, transporting, layingand curing concrete , working at depths , tools and plants and including all other incidental charges etc; complete as per relevant standard specifications, for SUBSTRUCTURE OF ABUTMENTS, WINGS, AND PIERS ABOVE SILL LEVEL.
8VibratedReinforced Cement Concrete of grade M30 design mix using 20mm &12mm ISS size HBG graded metal including cost and conveyance of all materials to site including cost of cementat siteincluding cost of formwork, soft water, labour charges for mixing, transporting, layingand curing concrete , working at depths , tools and plants including all other incidental charges etc; complete as per relevant standard specifications, for DIRT WALL CUM BED BLOCK OVER ABUTMENTS AND BED BLOCK OVER PIERS.
9Providing and fixing seepage pipes of 100mm dia. PVC pipes of required lengths for abutments and wngs including cost and conveyance of all materials to work site, cost and labour for 900mm dia. semi-spherical back fill arrangements with 100mm size broken granite chips at the periphery and labour charges for fixing, etc.,to drain of the backfill IN THE ABUTMENTS AND WINGS.
10Providing and fixing KRAFT PAPER for full width of seating of deck slab andincluding cost and conveyanceto work site, labour charges for fixing the same in the correct position and all other incidental charges et., complete.
11VibratedReinforced Cement Concrete of grade M35 Design Mix usingISS size HBG graded metal including cost and conveyance of all materials to site including cost of cementat siteincluding cost of formwork, soft water, labour charges for mixing, transporting, layingand curing concrete , working at depths , tools and plants including all other incidental charges etc; complete as per relevant standard specifications, for DECK SLAB.
12Providing filter media behind the abutments and wings with clean III graded material 53mm to 5.6mm to 600mm thick andwell compacted in layerswith smaller sized towards the soil and bigger size towards the wall including cost and conveyance to work site includingall labours and other incidental charges including hire charges for tools and plants employed etc., for filter media as per MOST"s (Roads Wing) specifications for Roads and Bridges " Fourth Revision Cl. 309-3-2-13 and 305 -4-4 etc., complete.
13Filling behind Abutmants and wings with clean gritty gravel including cost and conveyance of gravel to worksite,laying,handling charges and filling in layers,tamping under optimum moisture content to get the maximum density including watering,with all leads for water and all other incidental charges etc,complete for filling behind the abutment and wings.
14Providing and fixing PVC EXPANSION JOINT in between deck slabs over abutment and pier as shown in the drawing including cost and conveyence of expansion joints including shalimar pad and joint sealent etc, complete.
15Supply and fabrication of Fe-500 steel required for all RCC items of works involved in the schedule cost of steel at site fabrication,labour charges for cleaning the rods straightening, cutting, bending, tying grills, including overlapping to the required length whenever necessary and placing the reinforcement in position as specified in the drawings,including cost of binding wire, provision of spacer bars, cover blocks and all other incidental charges etc,complete, Fe-500 grade-1 MT
16Vibrated Cement Concrete M15 grade, Nominal Mix 1:2:4, using 20mm ISS hard granite broken metal including cost and conveyance of all materials to site and cement at site including cost of formwork, lead for soft water, labour charges for mixing , transporting, laying, and curing concrete working in heights and hire charges for tools and plants, and all other incidental charges etc complete as per relevant specification for BASE COURSE BELOW APPROACHES.
17Vibrated reinforced cement concrete M30 design mix using 20mm &12mm ISS graded hard granite broken metal including cost and conveyance of all materials to site including cement at site including labour charges for mixing, laying, curing concrete, working at heights,hire charges for tools and plants, including all other incidental chages etc., complete for Approach Slab.
18Vibrated cement Concrete M30 design mixusing 25, 12 & 6mm ISS size HBG graded metal including cost and conveyance of all materials to worksite and cement at site including all labour charges for fixing concrete, laying, vibrating, hire charges for tools and plants, compacting, curing with all leads for soft water, including all other incidental charges,formwork,cost of premoulded expansion joints and fixing the same in position etc., complete for wearing coat over deck slab and approach slab.
19Vibrated Reinforced Cement Concrete M-25, Grade, Design Mix using 20mm &12mm ISS size hard granite broken graded metal including cost and conveyance of all materials to site including cement at site but excluding cost and fabrication of steel, including labour charges for mixing, transporting, laying, and curing concrete,working at heights,hire charges for tools and plants,including all other incidental charges,etc, complete for RCC HAND RAILS AND POSTS OVER DECK SLAB.
20Vibrated Cement Concrete M20 grade, Nominal Mix using 20mm &12mm ISS size hard granite broken metal including cost and conveyance of all materials to site and cement at site including labour charges for mixing, transporting, laying, and curing concrete, working at heights, hire charges for tools and plants, including all other incidental charges,etc.,complete as per standard specification for PCCPARAPETS OVER WINGS.
21Providing and fixing of cast iron drainage spouts 100mm dia as per MOST drawing SD/205 with grating arrangements at top as shown in the drawing using 12mm x 25mm flats for grating arrangements, and 100mm dia drainage spout projecting beyond the bottom of deck slab as shown in the drawing including cost and conveyance of cast iron pipes and flats and fixing them in position etc,complete.
22Dismantling
23Dismantling theexisting PCCin the existing bridge and clearing away from the work site and carefully stacking the useful materials for reuse on the road side as directed by the departmental officers including all labour and incidental charges etc., complete . Side wall.
24Dismantling theexisting PCCin the existing bridge and clearing away from the work site and carefully stacking the useful materials for reuse on the road side as directed by the departmental officers including all labour and incidental charges etc., complete. Wearing coat
25Approach road (Sub Estimate)
26Excavationincludingremovalandsatisfactorydisposal ofallmaterialsnecessaryfortheconstructionof road wayandsidedrainsin accordancewithspecifications andthelines,gradesandcross sectionsshownin thedrawingsor as indicatedby the Engineer usingCarted Eathwithaleadof3kmforformationofApproach Road.
2798% COMPACTION
28100% COMPACTION
29Providing and laying Granular Sub base as per table no 400-1/400-2 and gradung III of MORTH Revison IV with and any other Granular material or a combination those of for 150 mm thick to give a CBR of 20 on prepared sub grade in accordance with the requirements of the Specifications For Sand ,Gravel & 6mm Aggregate mix
30Provding and Laying Water bound macadam Grading - II consisting of clean crused aggregates mechanically interlocked by rolling and bonding together with Screening binding materials and finised in acordance with the requirements of the specifications and t
31Provding and Laying Water bound macadam Grading - III consisting of clean crused aggregates mechanically interlocked by rolling and bonding together with Screening binding materials and finised in acordance with the requirements of the specifications and
32Proivding and laying of prime coat usingEmulsion Bitumen at the rate of 7.00kg/sq.mover the WBM surfacepreparatoryto another construction over it.
33Proivding and laying of Tack coat usingEmulsion Bitumen at the rate of 2.50kg/sq.mover the WBM surfacepreparatoryto another construction over it.
34Providing laying and compacting Open graded premix carpet 20mm thick with a liauid seal coat which is shall consist of open graded carpet of 20mm thickness in a single course composed of suitable small sized aggregated premixed with bituminous binder with application of lquid seal coat for sealing the viods in a bituminous surface conforming to the specifications.
35Providing and laying of Gravel for berms including cost and conveyance of all materials to site and all labour charges for spreading, levelling and watering etc., complete
36Construction of  Retaining Wall
37Earthworkexcavationinallclassesofsoilexcepthard rockrequiringblastinganddepositingonbankwithall leadsandliftsasperSS20B,includingcostofalllabour, equipments andall incidentalcharges such as baling out water, providing and maintaining necessary cofffer dams, sheeting,shoring,bracingandtheirsubsequentremoval, removalofalllogs,stumps,grubsandotherdeleterious matterandobstructions,trimmingbottomofexcavation, backfilling, and clearing the site and disposal of all surplus materialsetc.,completeasperrelevantstandard specifications forFOUNDATION UNDER RETAING WALL.
38Filling inside the Foundation with clean coarse sand including cost and conveyance of gravel to worksite, laying,handlingchargesandfillinginlayers,tamping underoptimummoisturecontenttogetthemaximum density including watering with all leads for water and all other incidental charges etc., complete for filling inside the Foundation.
39VibratedCementConcreteofGradeM15using20mm size HBGmetal including cost and conveyance ofall materials to site including cost of cement at site including costofformwork,softwater,labourchargesfor mixing, transporting, laying and curing concrete, working at depths,toolsandplantsandmaintainingofprotective bunds, cofferdams, shoring, strutting etc., complete as per relevant standard specifications for FOUNDATION BELOW.
40Vibrated CementConcreteGradeM20using20&10 mm ISS size HBG graded metal including cost and conveyance of all materials to site and cement at site but excludingcost andfabrication of steel but including form work and centeringsoft waterlabour charges for mixing, transporting, placing in position, vibrating and compacting finishing and curing concrete working atheights, hire charges for tools and plants, including all other incidental chargesetc.,completeasperstandardspecificationsfor RETAINING WALL FOUNDATION.
41VibratedCement Concrete of Grade M 20 using 20 mm & 10 mm ISS size HBG metal including cost and conveyance ofallmaterialstositeincludingcostofcement atsite including cost of formwork, soft water, labour charges for mixing, transporting, layingand curing concrete , working at depths , tools and plants and including all other incidental charges etc; complete as per relevant standard specifications,forSUBSTRUCTUREOFRETAININGWALL ABOVE SILL LEVEL -
42Providingandfixingseepagepipesof100mmdia.PVC pipes of required lengths for Retaining Wall including cost andconveyanceofallmaterialstoworksiteandlabour charges for fixing, complete
43GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
Disclaimer :
We takes all possible care for accurate & authentic tender information, however Users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender.
Tell us about your Product / Services,
We will Find Tenders for you

Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy

For Tender Information Services Visit : TenderDetail