Tender For Consultancy Services For Project Management Including Preparation Of Detailed Project Report Of Selected Stretches Corridors Of Road Networks In The State Of Maharashtra For Upgradation To Two Lanes With Paved Shoulders Four Lane Configur, malegaon-Maharashtra

Ministry Of Road Transport And Highways has published Tender For Consultancy Services For Project Management Including Preparation Of Detailed Project Report Of Selected Stretches Corridors Of Road Networks In The State Of Maharashtra For Upgradation To Two Lanes With Paved Shoulders Four Lane Configur. Submission Date for this Tender is 05-01-2024. Consultancy Service Tenders in malegaon Maharashtra. Bidders can get complete Tender details and download the document.




Tender Notice

41045389
Corrigendum : Tender For Consultancy Services For Project Management Including Preparation Of Detailed Project Report Of Selected Stretches Corridors Of Road Networks In The State Of Maharashtra For Upgradation To Two Lanes With Paved Shoulders Four Lane Configur
Open Tender
Indian
Maharashtra
malegaon
05-01-2024

Tender Details

Consultancy Services For Project Management Including Preparation Of Detailed Project Report Of Selected Stretches / Corridors Of Road Networks In The State Of Maharashtra For Upgradation To Two Lanes With Paved Shoulders / Four Lane Configuration Of Malegaon Manmad Road Nh-160H Km 95+500 To 128+350 ( Length = 32.850 Km ) ; 1 Key Personnel 2 Team Leader Cum Senior Highway Engineer 3 Senior Bridge Engineer 4 Highway Cum Pavement Engineer 5 Material-Cum-Geotechnical Engineer- Geologist 6 Senior Survey Engineer 7 Traffic And Safety Expert 8 Environmental Specialist 9 Quantity Surveyor / Documentation Expert 10 Land Acquisition Expert 11 Utility Expert 12 B: Sub Professional Staff ( To Be Assessed By Consultant As Per Requirement Of Assignment And One Sub-Professional Be A Fresh Graduate ) 13 To Be Filled By Consultant 14 To Be Filled By Consultant 15 To Be Filled By Consultant 16 To Be Filled By Consultant 17 To Be Filled By Consultant 18 To Be Filled By Consultant 19 To Be Filled By Consultant 20 Support Staff 21 Office Manager 22 Typist 23 Office Boy 24 Night Watchman 25 The Vehicles Provided By The Consultants Shall Include The Cost For Rental, Drivers, Operation, Maintenance, Repairs, Insurance, Etc.A. For Use Of Consultants 26 Duty Travel To Site ( Fixed Costs ) 27 Office Rent ( Fixed Costs ) The Rent Cost Includes Maintenance, Cleaning, Repairs, Etc. 28 Vi. Office Supplies, Utilities And Communication ( Fixed Costs ) 29 Office Supplies Drafting 30 Supplies Computer 31 Running Costs 32 Domestic And International Communication 33 Office Furniture And Equipment ( Rental ) 34 Office Furniture And Equipment 35 Viii.Reports And Document Printing 36 Monthly Report ( Per Month ) 37 Inception Report & Qap 38 Environment And Social Impactscreening Report 39 Draft Feasibility Report 40 Final Feasibility Report 41 Strip Plan With L.A. Reports 42 Draft La And Clearances I Report 43 Final La And Clearances I Report 44 Draft Environmental Assessment Report & Rap 45 Final Environmental Assessment Report & Rap 46 Draft Detailed Design Report & Drawings Etc. 47 Draft Emp 48 Draft Bidding Documents 49 Final Detailed Project Report With Bill Of Quantities, Cost Estimates, Updated Drawings , Etc 50 Final Emp 51 Final Bidding Documents 52 Draft 3 ( A ) , 3 ( A ) And 3 ( D ) Notification For Land Acquisition ( 3 Copies Each ) 53 La & Clearances Ii Report 54 Ix Survey And Investigation 55 Topographic Survey Including Hire Charges For Equipment And Supply Of Survey Teams Comprising Of Project Survey Field Staff Etc. Inclusive Of Cost Of Materials , Labourer. 56 Detailed Topographic Surveys Using Air Borne Tomography And Air Borne Lidar Technology 57 B. Investigation ( Fixed Cost ) 58 Road And Bridge Inventory 59 Fwd Test And Pavement Evaluation 60 Roughness Survey 61 Axle Load Survey 62 Material Survey And Investigation 63 Sub-Grade Investigation 64 Traffic Survey 65 Socio-Economic & Census Survey / Studies 66 Land Acquisition Studies 67 Any Other Investigations / Surveys 68 C. Net Work Survey And Gpr 69 Net Work Survey Of The Existing Highways As A Responsitory For Civil Work As Per Direction From Authority 70 Gpr Survey For Detection Of Under Ground Utilities 71 Cost Of Supply And Fixing Boundary Pillars 72 Procuring And Fixing Boundary Pillars And Its Installation, Complete In All Respect As Per Irc:25, 1967:Wherever The Proposed Alignment Follows The Existing Alignment, The Boundary Pillars Shall Be Fixed At An Interval Of 200M On Either Side Of Proposed Right Of Way. Wherever There Is A Proposal Of Realignment Of The Existing Highway And / Or Construction Of New Bypasses, Consultant Shall Fix Boundary Pillars Along The Proposed Alignment On The Extreme Boundary On Either Side Of The Project Highway At 50 M Interval. ( Lumpsum ) 73 Land Acquisition Team Including Support Staff And Logistics / Transportation 74 Ex-Land Revenue Inspector / Officer Or Equivalent 75 Ex-Kanoogo / Girdwar Or Equivalent 76 Ex-Patwari Or Equivalent 77 Typist 78 Peon 79 Logistic For Land Acquisition Team 80 Computer Including Necessary Peripherals 81 Printers 82 Vehicles ( Bolero Or Equivalent ) With Monthly Running Limit Of 4000 Km 83 Estimate Of Costfor Expatriate Consultants ( Inr ) Remuneration Of Exptriate Staff Including Per Diem Allowances 84 Staff 1 85 Staff 2 86 Staff 3 87 Staff 4 88 Staff 5 89 Staff 6 90 International Airfares ( Fixed Cost ) Mobilization Anddemobilization 91 Position 1 92 Position 2 93 Position 3 94 Position 4 95 Inland Travel In Home Country ( Fixed Costs ) 96 Airlines 97 Other Miscellaneous Expenses ( Like Da, Internal Travel Expenses Other Incidentals ) 98 Income Tax ( Expariate ) ( As Per Prevaling Norms ) 99 Other Taxes / Duties ( If Any ) Specify Clearly 100 Goods & Service Tax ( As Per Prevaling Norms ) 101 Sub Soil Investigation ( Boring ) 102 A ) Boring In All Type O Soils ( Other Than Hard Rock ) 103 B ) Boring In Hard Rock

Corrigendum Details

Sr No CorrigendumDate Corrignedum CorrigendumType NewSubmissionDate
1 24-Dec-2023 Corrigendum no.1 Date 05-01-2024
2 30-Dec-2023 CSD Other 05-01-2024

Key Value

Document Fees
INR 5900 /-
EMD
INR 100000.0 /-
Tender Value
Refer document

BOQ Items

NAME OF WORK : Consultancy Services for Project Management including preparation of Detailed Project Report of Selected stretches/corridors of Road Networks in the State of Maharashtra for Upgradation to Two lanes with paved shoulders/Four lane configuration of Malegaon Manmad Road NH-160H Km 95+500 to 128+350 (Length = 32.850 km)
Sl. No. Item Description
1Key Personnel
2Team Leader cum Senior Highway Engineer
3Senior Bridge Engineer
4Highway cum Pavement Engineer
5Material-cum-Geotechnical Engineer- Geologist
6Senior Survey Engineer
7Traffic and Safety Expert
8Environmental Specialist
9Quantity Surveyor/ Documentation Expert
10Land Acquisition Expert
11Utility Expert
12B: Sub Professional Staff (To be assessed by Consultant as per requirement of assignment and one sub-professional be a fresh graduate)
13To be filled by Consultant
14To be filled by Consultant
15To be filled by Consultant
16To be filled by Consultant
17To be filled by Consultant
18To be filled by Consultant
19To be filled by Consultant
20Support Staff
21Office Manager
22Typist
23Office Boy
24Night Watchman
25The vehicles provided by the Consultants shall include the cost for rental, drivers, operation, maintenance, repairs, insurance, etc. A. For use of consultants
26Duty Travel to Site (Fixed Costs)
27Office Rent (Fixed Costs) The rent cost includes maintenance, Cleaning, repairs, etc.
28VI. Office Supplies, Utilities and Communication ( Fixed Costs )
29Office Supplies Drafting
30Supplies computer
31Running Costs
32Domestic and International Communication
33Office Furniture and Equipment ( Rental )
34Office Furniture and Equipment
35VIII.Reports and Document Printing
36Monthly Report (per month)
37Inception Report & QAP
38Environment and Social Impact Screening Report
39Draft Feasibility Report
40Final Feasibility Report
41Strip Plan with L.A. Reports
42Draft LA and Clearances I Report
43Final LA and Clearances I Report
44Draft Environmental Assessment report & RAP
45Final Environmental Assessment report & RAP
46Draft Detailed Design Report & Drawings etc.
47Draft EMP
48Draft Bidding Documents
49Final Detailed Project Report with Bill of Quantities, Cost Estimates, Updated Drawings ,etc
50Final EMP
51Final Bidding Documents
52Draft 3(a) ,3(A) and 3(D) notification for land acquisition ( 3 copies each)
53LA & Clearances II Report
54IX Survey and Investigation
55Topographic Survey including hire charges for equipment and supply of survey Teams comprising of project survey field staff etc. inclusive of cost of materials , labourer.
56Detailed topographic surveys using Air Borne Tomography and Air Borne LiDAR Technology
57B. Investigation (Fixed cost)
58Road and Bridge Inventory
59FWD Test and Pavement Evaluation
60Roughness Survey
61Axle Load Survey
62Material Survey and Investigation
63Sub-grade Investigation
64Traffic Survey
65Socio-economic & Census Survey/ Studies
66Land Acquisition Studies
67Any other investigations/surveys
68C. NET WORK SURVEY AND GPR
69Net work Survey of the existing Highways as a responsitory for civil work as per direction from Authority
70GPR Survey for detection of under ground utilities
71Cost of supply and fixing boundary pillars
72Procuring and fixing boundary pillars and its installation, complete in all respect as per IRC:25,1967:Wherever the proposed alignment follows the existing alignment, the boundary pillars shall be fixed at an interval of 200m on either side of proposed Right of Way. Wherever there is a proposal of realignment of the existing Highway and/or construction of New Bypasses, Consultant shall fix boundary pillars along the proposed alignment on the extreme boundary on either side of the project Highway at 50 m interval. (lumpsum )
73Land acquisition Team including support staff and logistics/transportation
74Ex-Land revenue inspector/officer or equivalent
75EX-kanoogo/Girdwar or equivalent
76Ex-Patwari or equivalent
77typist
78peon
79Logistic for Land Acquisition Team
80computer including necessary peripherals
81printers
82Vehicles(Bolero or equivalent )with monthly running limit of 4000 km
83Estimate of Costfor Expatriate Consultants (INR) Remuneration of Exptriate staff including per diem allowances
84Staff 1
85Staff 2
86Staff 3
87Staff 4
88Staff 5
89Staff 6
90International Airfares (Fixed Cost) Mobilization andDemobilization
91Position 1
92Position 2
93Position 3
94Position 4
95Inland Travel in Home Country (Fixed Costs)
96Airlines
97Other Miscellaneous expenses (like DA, internal travel expenses other incidentals)
98Income Tax (Expariate)( as per prevaling Norms)
99Other Taxes / Duties (if any) Specify clearly
100Goods & Service Tax ( as per prevaling Norms)
101Sub Soil Investigation ( Boring)
102a) Boring in all type o soils ( Other than hard rock)
103b) Boring in Hard Rock
Disclaimer :
We takes all possible care for accurate & authentic tender information, however Users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender.
Tell us about your Product / Services,
We will Find Tenders for you

Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy

For Tender Information Services Visit : TenderDetail