Tender For Construction Of 300X200 Mm Dia. Size Of 180/165 M Deep Tube Well And Allied Works And Pump House Constrution In Awas Vikas Sector 4
Tender Value
38.18 Lakhs
Estimated cost
Bid Submission
19 Dec 2023
0 days left
EMD
76500
Bank guarantee accepted
Document Fee
4963
Non-refundable
Tender Type
Online
Tender Overview
Organization
Tender ID
Competition Type
NCB
Bidding Type
Tender
Location / State
nawabganj → Uttar Pradesh
EMD Exemption
Not Available
Quantity
Not Available
Website
Contact Person
Address
Project Description
Construction Of 300X200 Mm Dia. Size Of 180 / 165 M Deep Tube Well And Allied Works And Pump House Constrution In Awas Vikas Sector 4
BOQ
| Sl. No. | Item Description |
| 1 | Cartage of rig machine up to site |
| 2 | Cartage of rig machine\"s T&P from truck. |
| 3 | Loading and unloading of T&P |
| 4 | Cartage of tube well assembly by truck from store to site |
| 5 | Loading and unloading of tube well assembly |
| 6 | Toeing of 250 PSI air compressor by truck form store to site |
| 7 | Cartage of compressor T&P by truck from store to site |
| 8 | Loading and unloading of air compressor T&P |
| 9 | Toeing of O.P. unit by truck form store to site |
| 10 | Cartage of O.P. unit by truck from store to site |
| 11 | Loading and unloading of O.P. unit T&P |
| 12 | Cartage of pumping plant material by truk from store to site |
| 13 | Loading and unloading of pumping plant materials T&P |
| 14 | 300 mm dia 7.1 mm thick MSERW housing pipe |
| 15 | 300x200 mm dia M.S. reducer |
| 16 | 200 mm dia 7.1 mm thick MSERW plain pipe |
| 17 | 200 mm dia 7.1 mm thick MSERW slottedpipe |
| 18 | 200 mm dia bail plug |
| 19 | 300 mm dia M.S. clamp |
| 20 | 300 mm dia well cap |
| 21 | 300 mm dia M.S. ring |
| 22 | 200 mm dia M.S. ring |
| 23 | 300 mm dia tubewell assembly support |
| 24 | 200 mm dia centre guide |
| 25 | Painting of tubewell assembly with one coat of ready mixed, priming paint and two coat of approve superior quality read mixed paint of clear. synthetic including supply of all materials labour T&P etc required for proper completion of the work. |
| 26 | Supply of lal kuan quarry pea gravel 1.6 to 4.8 mm size duly screened washed and stacked , with carting loading unloading complete at site |
| 27 | Erection of D.C. rig machine T&P and camp equipages. |
| 28 | Dismantling of rig machine and its T&P |
| 29 | Drilling of 675mm diabore fromG.L. to 75 M Depth BGL |
| 30 | Drilling of 550mm dia bore 75 M to 80 M BGL |
| 31 | Drilling of 550 mm dia bore 80 m to 120 M BGL |
| 32 | Drilling of 550mm dia bore 120m to 160M BGL |
| 33 | Drilling of 550mm dia bore 160m to 180M BGL |
| 34 | Water arrangement charges for during the drilling |
| 35 | Logging of bore hole by electric logger |
| 36 | Barricadingof site for safety with necessaryT&P required labour etc complete. |
| 37 | 300mm diahousing pipe from GL to 67.41 m BGL |
| 38 | 200 mm diaplain/ slotted pipe from 67.41 to 80 m BGL |
| 39 | 200 mm diaplain/ slotted pipe from 80 to 120 m BGL |
| 40 | 200 mm diaplain/ slotted pipe from 120 to 152.69 m BGL |
| 41 | Erection of 250 Psi air compressor T&P& camp equipage |
| 42 | Development of T/W by 250 PSI Air compressor |
| 43 | Dismantling of air compressor and its T&P |
| 44 | Erection of 250 O.P. unitT&P& camp equipage |
| 45 | Development of T/W by 250 O.P. unit |
| 46 | Dismantling of O.P. unit and its T&P |
| 47 | Yield and verticality test of tubbwell along with chemical and bacteriological analysis of tubewell water. |
| 48 | Cleaning of site for soil and sand including filling of pit and disposal lead up to 10 km for way from site by tractor troly and labour including loading unloading after comelotion of drilling and development work. |
| 49 | Watch and wand during working perion by 2 chukidar day night |
| 50 | 25 HP clear water submersible pump complete with electric motor capable to operate on 415 ±volts3 phase 50 c/s a.c. supply of 700 LPM , 75 M head (1200 LPM 45 M head. 25 H.P. ) |
| 51 | 25 H.P. switch gear along with starter and control panel cable etc complete |
| 52 | 100 mm dia 5.4 mm thick MS column pipe with flanged, C.I.D.F. 90 degree band size 100 mm , C.I.D.F. Tee 100 mm dia, M.S. Distance pipe 100 mm dia , 1 m long 2 No., 1.5 m long 1 No. , MS reducer , sluice valve 100 mm dia 2 No., reflex valve 100 mm dia 1 No. pressure gauge, pipe wrenches 22/6, screw drive 12x250 mm , 8x250 mm , 5x250 mm , line tester, 1 No. chain pulling 4.5 m lift 1 No. installation of pumping plant commissioning trail and testing of pumping plant misc items such as protection ring cut out electric resistance rubberseet, painting of pumping plant, supply of installation of suitable of chlorinating plant (Dozer) |
| 53 | Construction of pump house |
| 54 | Estimate for internal electrification of pump house |
AI Tender Summary
Tender Timeline
Nov 29, 2023
11:30 IST
Tender Published
Tender notice published.
CompletedDec 19, 2023
17:00 IST
Bid Submission Deadline
Online submission via eProcurement portal.
CompletedDec 19, 2023
Bid Opening Date
Technical bids will be opened and evaluated.
CompletedTender Documents
Download All (ZIP) ↓
Disclaimer
We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender