| 1 | Earth work in filling with cartage upto 5.0km distance from the site etc all complete required for propper completion of work |
| 2 | Earth work in excavation for foundation in soil mixed with mooram, kankar and singles etc all complete.Sl No 252 |
| 3 | P/L cement concrete 1:6:12 (1 cement 6 fine sand, 12 graded brick ballast 40mm normal size) including supply of all materials labour and T&P etc requred for proper completion of work. Sl No 273 |
| 4 | Class M-150 brick work in 1:4 with cement and c sand etc alll complete. |
| 5 | S/L of 80mm thick Rubber mould interlocking paver blocks etc all complete required for proper |
| 6 | P/L of cement concrete in 1:2:4 with cement C sand and 20mmstone grite etc all complete requred for proper completion of work. |
| 7 | Brick edging on both sides of roads of 1stclass brick 8cm (3\") wide and 12cm (4.50\") deep laid with mud mortar including labour and supply of bricks finished to requried template and in proper aligment and also including dressing and ramming the excavated earth including all labour T&P sundries requried for completion of work with materials. |
| 8 | Granular sub base with Graded Material (Table-400-1) BY MIX IN PLACE METHOD Construction of granular sub-base by surface by provinding close grader on prepared surface mixing by mix in place method with vibratory roller to achive the desired density complete as per clause 401 |
| 9 | Wet max Macadam (plant Mix Method) Provinding and laying spreading and compacting graded stone aggegte to wet mix macadam specification including premixing the materials with water of OMC Mechinical mix plant carrige of mixed material by tipper to site laying in unifrom layers with paver in sub base/base course on well preared surface and compacting with vibratory to achive the disired density. |
| 10 | Prime cost over WMM/WBM provinding and applying primer coat with SS-2 grade bitumen emulsion on prepared surface and sparying primer at the rate of 0.70kg/sqm using mechancal broom. |
| 11 | Tack coat on Bitumenous surface provinding and applying tack coat with bitumen pressure distributor at of 0.30kg per sqm on the prepared bituminous surface cleaned with mechanical broom. |
| 12 | Dence Graded Bituminus Macadam Grading provinding and lying dence graded bitumeus macadam with higher capacity HMP using crused aggegates of specified grading premixed with bituminous binder @4.5 per cent by weight of total mix and filler transporting the hot mix to work site lying with a hydrostatic paver finisher to the required garde level and alignet rolling with smooth wheeled vibatrory and tendam rollers to achive the desired compaction as per MORTH specification clause N0 505 complete in all respects. |
| 13 | Bituminus Concrete Grading2 P/L bituminus concrete with higher capacity hot mix plant using crused aggregate of specied grading premixed with bituminus binder @5.4 percent of mix to work site lying with hydrostaic paver finisher to the requred grade level and aligment rolling with smooth wheeledvibatrory and tendem rollers to achive the desired compaction as per MORTH specification clause N0 507 complete in all respects. |
| 14 | R.C.C work in 1:2:4with cement c sand and 20mm stone grit etc all complete |
| 15 | M.S iron work plain work as reinforcement including cutting bending and wastage etc all complete. Sl No 504 |
| 16 | Road Making with hot applied thermoplastic compound with Reflectrosing compound with Reflectrosing glass beds on Bituminous surface |
| 17 | Reflective Raised pavement markers (cat eye/Road stund ) Morth-804 (8.35) |
| 18 | S/F Sing board at site all complete |