Tender For Construction Of Drainage At Athi Thiravidar Mayanapathai Street In Avudaiyarpattu Panchayat.
Tender Overview
Project Description
Tender For Construction Of Drainage At Athi Thiravidar Mayanapathai Street In Avudaiyarpattu Panchayat.; Earth Wok Excavation For Foundation In Classes Of Soils Except Hard Rock Requiring Blasting With Initial Lead And Lift Etc., Including Leveling The Site Etc, Complete With Standard Specificationin Hard Stiff Clay Black Cotton Soil Hard Fred Earth 3 Cement Concrete 1:4:8 Using 40Mm Iss Size Hand Broken Granite Stone Jellyincluding Labour Charges For Mixing Concrete Watering And Laying The Concrete In Layers Not More The 15 Cm Thick Compacting Etc Complete Complying With Standard Specification Etc C 4 Supplying And Erecting Shuttering Including Complying With Standard Speficiation Including All Labour Charges Etc.Complete. 5 Cement Concrete : 1:2:4 With Broken Stone Jusing 20Mm Gauage Machine Broken Hbg Metal Including Cost And Conveyance And All Labour Charges Etc.Complete 6 Construction Of Culvert I @ Avudaiyarpattu Panchayat 7 Earth Work Excavation And Depositing On Bank With In Initial Lead Of 10 M And Initial Lift Of 2M In Hard Stiff Clay, Stiff Black Cotton Soil, Hard Red Earth, Earth Mixed With Small Sized Boulders And Hard Gravelly Soil As Per Ss 20B. 8 Cement Concrete 1:4:8 Mix Using 40Mm Iss Metal Including Cost And Conveyance Of All Materials To Site And All Labour Charges For Mixing, Laying And Curing Etc Complete. 9 Supplying And Erecting Centring For Sides And Suffits Including Supports And Structing Upto 3.29M Height For Plane Surface In All Cross Bracting Using Ms Sheets Of Size 90 X 60Cm And 10Kg Stiffened With Angle Of Size 25 X 25 X 3Mm For Boarding Laid Over Silver Oak Joists Os Size 10 X 6.5Mm At About 90Cm C / C And Supported By Casuring Props Of 10Cm 13Cm Dia At C / C Etc., Complete. 10 Below 11 Above 12 Cement Concrete 1:3:6 Mix Using 40Mm Iss Metal Including Cost And Conveyance Of All Materials To Site And All Labour Charges For Mixing, Laying And Curing Etc Complete. 13 Cement Concrete 1:2:4 Mix Using 20Mm Iss Metal Including Cost And Conveyance Of All Materials To Site And All Labour Charges For Mixing, Laying And Curing Etc Complete. 14 Supplying And Fabrication Of Steel Including Cost And Conveyance Of Steel To Site And All Labour Charges For Straightening, Cutting To Length, Bending To Shape And Tying In Position And Forming Grills For All R.C.C Works. 15 Reinforced Cement Concrete 1:1 1 / 2:3 Mix Using 20Mmiss Metal Including Cost And Conveyance Of All Materials To Site And All Labour Charges For Mixing, Laying, And Curing Etc Complete For 10 Cum 16 Construction Of Culvert Ii @ Avudaiyarpattu Panchayat 17 Earth Work Excavation And Depositing On Bank With In Initial Lead Of 10 M And Initial Lift Of 2M In Hard Stiff Clay, Stiff Black Cotton Soil, Hard Red Earth, Earth Mixed With Small Sized Boulders And Hard Gravelly Soil As Per Ss 20B. 18 Cement Concrete 1:4:8 Mix Using 40Mm Iss Metal Including Cost And Conveyance Of All Materials To Site And All Labour Charges For Mixing, Laying And Curing Etc Complete. 19 Supplying And Erecting Centring For Sides And Suffits Including Supports And Structing Upto 3.29M Height For Plane Surface In All Cross Bracting Using Ms Sheets Of Size 90 X 60Cm And 10Kg Stiffened With Angle Of Size 25 X 25 X 3Mm For Boarding Laid Over Silver Oak Joists Os Size 10 X 6.5Mm At About 90Cm C / C And Supported By Casuring Props Of 10Cm 13Cm Dia At C / C Etc., Complete. 20 Below 21 Above 22 Cement Concrete 1:3:6 Mix Using 40Mm Iss Metal Including Cost And Conveyance Of All Materials To Site And All Labour Charges For Mixing, Laying And Curing Etc Complete. 23 Cement Concrete 1:2:4 Mix Using 20Mm Iss Metal Including Cost And Conveyance Of All Materials To Site And All Labour Charges For Mixing, Laying And Curing Etc Complete. 24 Supplying And Fabrication Of Steel Including Cost And Conveyance Of Steel To Site And All Labour Charges For Straightening, Cutting To Length, Bending To Shape And Tying In Position And Forming Grills For All R.C.C Works. 25 Reinforced Cement Concrete 1:1 1 / 2:3 Mix Using 20Mmiss Metal Including Cost And Conveyance Of All Materials To Site And All Labour Charges For Mixing, Laying, And Curing Etc Complete For 10 Cum 26 Construction Of Culvert Iii @ Avudaiyarpattu Panchayat 27 Earth Work Excavation And Depositing On Bank With In Initial Lead Of 10 M And Initial Lift Of 2M In Hard Stiff Clay, Stiff Black Cotton Soil, Hard Red Earth, Earth Mixed With Small Sized Boulders And Hard Gravelly Soil As Per Ss 20B. 28 Cement Concrete 1:4:8 Mix Using 40Mm Iss Metal Including Cost And Conveyance Of All Materials To Site And All Labour Charges For Mixing, Laying And Curing Etc Complete. 29 Supplying And Erecting Centring For Sides And Suffits Including Supports And Structing Upto 3.29M Height For Plane Surface In All Cross Bracting Using Ms Sheets Of Size 90 X 60Cm And 10Kg Stiffened With Angle Of Size 25 X 25 X 3Mm For Boarding Laid Over Silver Oak Joists Os Size 10 X 6.5Mm At About 90Cm C / C And Supported By Casuring Props Of 10Cm 13Cm Dia At C / C Etc., Complete. 30 Below 31 Above 32 Cement Concrete 1:3:6 Mix Using 40Mm Iss Metal Including Cost And Conveyance Of All Materials To Site And All Labour Charges For Mixing, Laying And Curing Etc Complete. 33 Cement Concrete 1:2:4 Mix Using 20Mm Iss Metal Including Cost And Conveyance Of All Materials To Site And All Labour Charges For Mixing, Laying And Curing Etc Complete. 34 Supplying And Fabrication Of Steel Including Cost And Conveyance Of Steel To Site And All Labour Charges For Straightening, Cutting To Length, Bending To Shape And Tying In Position And Forming Grills For All R.C.C Works. 35 Reinforced Cement Concrete 1:1 1 / 2:3 Mix Using 20Mmiss Metal Including Cost And Conveyance Of All Materials To Site And All Labour Charges For Mixing, Laying, And Curing Etc Complete For 10 Cum 36 Construction Of Culvert Iv @ Avudaiyarpattu Panchayat 37 Earth Work Excavation And Depositing On Bank With In Initial Lead Of 10 M And Initial Lift Of 2M In Hard Stiff Clay, Stiff Black Cotton Soil, Hard Red Earth, Earth Mixed With Small Sized Boulders And Hard Gravelly Soil As Per Ss 20B. 38 Cement Concrete 1:4:8 Mix Using 40Mm Iss Metal Including Cost And Conveyance Of All Materials To Site And All Labour Charges For Mixing, Laying And Curing Etc Complete. 39 Supplying And Erecting Centring For Sides And Suffits Including Supports And Structing Upto 3.29M Height For Plane Surface In All Cross Bracting Using Ms Sheets Of Size 90 X 60Cm And 10Kg Stiffened With Angle Of Size 25 X 25 X 3Mm For Boarding Laid Over Silver Oak Joists Os Size 10 X 6.5Mm At About 90Cm C / C And Supported By Casuring Props Of 10Cm 13Cm Dia At C / C Etc., Complete. 40 Below 41 Above 42 Cement Concrete 1:3:6 Mix Using 40Mm Iss Metal Including Cost And Conveyance Of All Materials To Site And All Labour Charges For Mixing, Laying And Curing Etc Complete. 43 Cement Concrete 1:2:4 Mix Using 20Mm Iss Metal Including Cost And Conveyance Of All Materials To Site And All Labour Charges For Mixing, Laying And Curing Etc Complete. 44 Supplying And Fabrication Of Steel Including Cost And Conveyance Of Steel To Site And All Labour Charges For Straightening, Cutting To Length, Bending To Shape And Tying In Position And Forming Grills For All R.C.C Works. 45 Reinforced Cement Concrete 1:1 1 / 2:3 Mix Using 20Mmiss Metal Including Cost And Conveyance Of All Materials To Site And All Labour Charges For Mixing, Laying, And Curing Etc Complete For 10 Cum 46 Construction Of Culvert V @ Avudaiyarpattu Panchayat 47 Earth Work Excavation And Depositing On Bank With In Initial Lead Of 10 M And Initial Lift Of 2M In Hard Stiff Clay, Stiff Black Cotton Soil, Hard Red Earth, Earth Mixed With Small Sized Boulders And Hard Gravelly Soil As Per Ss 20B. 48 Cement Concrete 1:4:8 Mix Using 40Mm Iss Metal Including Cost And Conveyance Of All Materials To Site And All Labour Charges For Mixing, Laying And Curing Etc Complete. 49 Supplying And Erecting Centring For Sides And Suffits Including Supports And Structing Upto 3.29M Height For Plane Surface In All Cross Bracting Using Ms Sheets Of Size 90 X 60Cm And 10Kg Stiffened With Angle Of Size 25 X 25 X 3Mm For Boarding Laid Over Silver Oak Joists Os Size 10 X 6.5Mm At About 90Cm C / C And Supported By Casuring Props Of 10Cm 13Cm Dia At C / C Etc., Complete. 50 Below 51 Above 52 Cement Concrete 1:3:6 Mix Using 40Mm Iss Metal Including Cost And Conveyance Of All Materials To Site And All Labour Charges For Mixing, Laying And Curing Etc Complete. 53 Cement Concrete 1:2:4 Mix Using 20Mm Iss Metal Including Cost And Conveyance Of All Materials To Site And All Labour Charges For Mixing, Laying And Curing Etc Complete. 54 Supplying And Fabrication Of Steel Including Cost And Conveyance Of Steel To Site And All Labour Charges For Straightening, Cutting To Length, Bending To Shape And Tying In Position And Forming Grills For All R.C.C Works. 55 Reinforced Cement Concrete 1:1 1 / 2:3 Mix Using 20Mmiss Metal Including Cost And Conveyance Of All Materials To Site And All Labour Charges For Mixing, Laying, And Curing Etc Complete For 10 Cum 56 Providingname Board 57 Photo Graphic Charges 58 Gst Amount For Providing Service To Government Contract Works For The Above Construction Works. { Gst Amount Is The Total Gst Amount For Total Overall Quoted Amount Above This Row In Column Bb For All Works In This Package }
BOQ
| Sl. No. | Item Description |
| 1 | Construction of drainageat Athi Thiravidar Mayanapathai streetin AvudaiyarpattuPanchayat |
| 2 | Earth wok excavation for foundation in classes of soils except hard rock requiring blasting with initial lead and lift etc., including leveling the site etc,complete with standard specificationin hard stiff clay black cotton soil hard fred earth |
| 3 | Cement Concrete 1:4:8 Using 40mm ISS size Hand Broken granite stone jellyincluding labour charges for mixing concrete watering and laying the concrete in layers not more the 15 cm thick compacting etc complete complying with standard specification etc c |
| 4 | Supplying and erecting shuttering including complying with standard speficiation including all labour charges etc.complete. |
| 5 | Cement Concrete : 1:2:4 with broken stone jusing 20mm gauage machine broken HBG metal including cost and conveyance and all labour charges etc.complete |
| 6 | CONSTRUCTION OF CULVERT I @ AVUDAIYARPATTU Panchayat |
| 7 | Earth work excavation and depositing on bank with in initial lead of 10 m and initial lift of 2m in hard stiff clay, stiff black cotton soil, hard red earth,earth mixed with small sized boulders and hard gravelly soil as per SS 20B. |
| 8 | Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete. |
| 9 | Supplying and erecting centring for sides and suffits including supports and structing upto 3.29m height for plane surface in all cross bracting using MS sheets of size 90 x 60cm and 10kg stiffened with angle of size 25 x 25 x 3mm for boarding laid over silver oak joists os size 10 x 6.5mm at about 90cm C/C and supported by casuring props of 10cm 13cm dia at C/C etc., complete. |
| 10 | Below |
| 11 | Above |
| 12 | Cement concrete 1:3:6 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete. |
| 13 | Cement concrete 1:2:4 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete. |
| 14 | Supplying and fabrication of steel including cost and conveyance of steel to site and all labour charges for straightening, cutting to length, bending to shape and tying in position and forming grills for all R.C.C works. |
| 15 | Reinforced cement concrete 1:1 1/2:3 mix using 20mmISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying, and curing etc complete for 10 cum |
| 16 | CONSTRUCTION OF CULVERT II @ AVUDAIYARPATTU Panchayat |
| 17 | Earth work excavation and depositing on bank with in initial lead of 10 m and initial lift of 2m in hard stiff clay, stiff black cotton soil, hard red earth,earth mixed with small sized boulders and hard gravelly soil as per SS 20B. |
| 18 | Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete. |
| 19 | Supplying and erecting centring for sides and suffits including supports and structing upto 3.29m height for plane surface in all cross bracting using MS sheets of size 90 x 60cm and 10kg stiffened with angle of size 25 x 25 x 3mm for boarding laid over silver oak joists os size 10 x 6.5mm at about 90cm C/C and supported by casuring props of 10cm 13cm dia at C/C etc., complete. |
| 20 | Below |
| 21 | Above |
| 22 | Cement concrete 1:3:6 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete. |
| 23 | Cement concrete 1:2:4 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete. |
| 24 | Supplying and fabrication of steel including cost and conveyance of steel to site and all labour charges for straightening, cutting to length, bending to shape and tying in position and forming grills for all R.C.C works. |
| 25 | Reinforced cement concrete 1:1 1/2:3 mix using 20mmISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying, and curing etc complete for 10 cum |
| 26 | CONSTRUCTION OF CULVERT III @ AVUDAIYARPATTU Panchayat |
| 27 | Earth work excavation and depositing on bank with in initial lead of 10 m and initial lift of 2m in hard stiff clay, stiff black cotton soil, hard red earth,earth mixed with small sized boulders and hard gravelly soil as per SS 20B. |
| 28 | Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete. |
| 29 | Supplying and erecting centring for sides and suffits including supports and structing upto 3.29m height for plane surface in all cross bracting using MS sheets of size 90 x 60cm and 10kg stiffened with angle of size 25 x 25 x 3mm for boarding laid over silver oak joists os size 10 x 6.5mm at about 90cm C/C and supported by casuring props of 10cm 13cm dia at C/C etc., complete. |
| 30 | Below |
| 31 | Above |
| 32 | Cement concrete 1:3:6 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete. |
| 33 | Cement concrete 1:2:4 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete. |
| 34 | Supplying and fabrication of steel including cost and conveyance of steel to site and all labour charges for straightening, cutting to length, bending to shape and tying in position and forming grills for all R.C.C works. |
| 35 | Reinforced cement concrete 1:1 1/2:3 mix using 20mmISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying, and curing etc complete for 10 cum |
| 36 | CONSTRUCTION OF CULVERT IV @ AVUDAIYARPATTU Panchayat |
| 37 | Earth work excavation and depositing on bank with in initial lead of 10 m and initial lift of 2m in hard stiff clay, stiff black cotton soil, hard red earth,earth mixed with small sized boulders and hard gravelly soil as per SS 20B. |
| 38 | Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete. |
| 39 | Supplying and erecting centring for sides and suffits including supports and structing upto 3.29m height for plane surface in all cross bracting using MS sheets of size 90 x 60cm and 10kg stiffened with angle of size 25 x 25 x 3mm for boarding laid over silver oak joists os size 10 x 6.5mm at about 90cm C/C and supported by casuring props of 10cm 13cm dia at C/C etc., complete. |
| 40 | Below |
| 41 | Above |
| 42 | Cement concrete 1:3:6 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete. |
| 43 | Cement concrete 1:2:4 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete. |
| 44 | Supplying and fabrication of steel including cost and conveyance of steel to site and all labour charges for straightening, cutting to length, bending to shape and tying in position and forming grills for all R.C.C works. |
| 45 | Reinforced cement concrete 1:1 1/2:3 mix using 20mmISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying, and curing etc complete for 10 cum |
| 46 | CONSTRUCTION OF CULVERT V @ AVUDAIYARPATTU Panchayat |
| 47 | Earth work excavation and depositing on bank with in initial lead of 10 m and initial lift of 2m in hard stiff clay, stiff black cotton soil, hard red earth,earth mixed with small sized boulders and hard gravelly soil as per SS 20B. |
| 48 | Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete. |
| 49 | Supplying and erecting centring for sides and suffits including supports and structing upto 3.29m height for plane surface in all cross bracting using MS sheets of size 90 x 60cm and 10kg stiffened with angle of size 25 x 25 x 3mm for boarding laid over silver oak joists os size 10 x 6.5mm at about 90cm C/C and supported by casuring props of 10cm 13cm dia at C/C etc., complete. |
| 50 | Below |
| 51 | Above |
| 52 | Cement concrete 1:3:6 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete. |
| 53 | Cement concrete 1:2:4 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete. |
| 54 | Supplying and fabrication of steel including cost and conveyance of steel to site and all labour charges for straightening, cutting to length, bending to shape and tying in position and forming grills for all R.C.C works. |
| 55 | Reinforced cement concrete 1:1 1/2:3 mix using 20mmISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying, and curing etc complete for 10 cum |
| 56 | ProvidingName Board |
| 57 | Photo Graphic Charges |
| 58 | GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column \"BB\" for all works in this package} |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
CompletedBid Opening Date
Technical bids will be opened and evaluated.
CompletedTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender