| 1 | Electrical Items : |
| 2 | Deep bore pipe earthing including (G.I. Pipe 40 mm. dia, B-Class, 60 feet, socket, cutter and 1x95 Sq. mm. XLPE Cable with Lug and Nut Bolt) with connection pipe to distribution T/F neutral or body.All material will be provided by Contractor. |
| 3 | Loading, Carriage and unloading of poles from store to work site or vice versa or from one site to another |
| 4 | Erection of Double pole structure by digging of pit by hydra |
| 5 | Erection ofSingle ST Poles including all fittings |
| 6 | Grouting of pole with cement brick ballast and coarse sand as per standard specification. |
| 7 | Making plinth of single pole of 400 mm dia, 600 mm height (200mm underground) with C.C. in ratio 1:4:8 of cements, stone ballast and coarse sand including cost of materials. |
| 8 | Painting of S.T. pole with one coat of red oxide and two coats of Aluminum Paintincluding cost of Ist Class enamel paint. |
| 9 | Earthing of supports by sagging of M.S. earthing rod 20mm and connecting with earth wire and related works as per standard specifications. |
| 10 | Taking outof 11 kV XLPE 3x120 Sq.mm cable from drum/complete drum of cableat site of work or store using JCB including carriage |
| 11 | Fabrication/modification of MS Item as per requirement of site |
| 12 | Fixing of MS Channel (100x50x6 )mm 2.4 / 2.8 mtr. Long/M.S. Angleand as per Required size |
| 13 | Fixing of danger board on erected poles |
| 14 | Making outdoor/indoor joints of 11/33 KV XLPE Cable where the cable is being laid. |
| 15 | Loading, Carriage and unloading of ACSR Dog Conductorfrom Store to Work Site or Vice-Versa. |
| 16 | Laying of ACSR Dog Conductor |
| 17 | Mounting of 11 kV Pin Insulator |
| 18 | Opening of H.T. Jumpers from the existing 3 Phase 3 Wire H.T. O.H. line for erection work. |
| 19 | Opening of LT Jumpers from the existing L.T. O.H. line for erection work. |
| 20 | Loading, carriage & unloading of distribution Transformers (upto 630 KVA) from store to site & vise-versa or from site to another site. |
| 21 | Erection of Distribution T/F on plinth/Double pole structure. |
| 22 | Dismantling of existing distribution T/F (Up to 630 KVA) |
| 23 | Connection of H.T. Jumper from fuse set to H.T. Bushing of the distribution transformer. |
| 24 | Fitting of L.T. D.B. by brackets & clamps on double pole structure & L.T. Cable Connection from T/F Cable to L.T.D.B. |
| 25 | Erection of LT Circuit 500 V/500 A |
| 26 | Connection of L.T. cable from L.T.D.B to L.T.O.H. |
| 27 | Jumpering of H.T.Lines from the existing HT O.H. line. |
| 28 | Jumpering of L.T. Lines from the existing LT O.H. line. |
| 29 | Erection of Drop out fuse set on Double Pole structure |
| 30 | Energizing and shifting of load on newly installed transformer from near over loaded transformer after construction of necessary LT OH Line. (If required) |
| 31 | Construction of T/F plinth, suitable for mounting of distribution transformer size of the plinth will be 1.2x1.2x1.2 meter solid with brick work. 75 mm thick C.C. in ratio 1:4:8 with cement, coarse sand and brick ballast laid on the base and 75 mm thick done on all the exposed sides to the plinth. |
| 32 | Fabrication, erection & grouting of T/F fencingof frame size 3x2.4 mtr. including cost of M.S. Angle size 40x40x5 and M.S. Flat size 35x5, fixing of welded steel wire fabric on steel frames by welding of 10 SWG wire fabric, including Painting fo two coats of paint on iron based surfaces with ready mixed paint to give bus green shade including cleaning of oil and dust. |
| 33 | Connecting of newly erected network with KESCO mains including testing, commissioning and energization of the same completely. |
| 34 | Carriage of all concerning stock materialfrom KESCo Store to site or vice-versa. |