Tender For Pole Installation Work On 33 Kv Line Mandi Sameti Road (2) Increasing Capacity Of 33/11 Kv Substation Hussen Basti (Saharanpur) (2×5) To (10+5) Mva., saharanpur-Uttar Pradesh

Paschimanchal Vidyut Vitran Nigam Limited has published Tender For Pole Installation Work On 33 Kv Line Mandi Sameti Road (2) Increasing Capacity Of 33/11 Kv Substation Hussen Basti (Saharanpur) (2×5) To (10+5) Mva.. Submission Date for this Tender is 18-10-2023. Canal Construction Tenders in saharanpur Uttar Pradesh. Bidders can get complete Tender details and download the document.




Tender Notice

40178885
Tender For Pole Installation Work On 33 Kv Line Mandi Sameti Road (2) Increasing Capacity Of 33/11 Kv Substation Hussen Basti (Saharanpur) (2×5) To (10+5) Mva.
Open Tender
Indian
Uttar Pradesh
saharanpur
18-10-2023

Tender Details

Tender For Pole Installation Work On 33 Kv Line Mandi Sameti Road ( 2 ) Increasing Capacity Of 33 / 11 Kv Substation Hussen Basti ( Saharanpur ) ( 2×5 ) To ( 10+5 ) Mva.- 1 1. Supply Of Following Materialg.I. Angle ( 65×65×6 ) Mm 2 G.I. Channel ( 100×50 ) Mm 3 G.I Wire No. 6 Swg 4 G.I Wire No. 8 Swg 5 M.S. Earthing Rod 6 V Type Cross Arm 33 Kv 7 Cross Arm Holding Clamp For Pcc Pole 9 M + S.T. Pole 11 M Long & 13M Long 8 Guarding Clamp For S.T. Pole 11 M & 13M Long 9 F Bracket For 33 Kv 10 Danger Board With Clamp For Pcc Pole 9 M + S.T. Pole 11 M Long & 13M Long 11 Number Plate With Clamp For Pcc Pole 9 M + S.T. Pole 11 M Long & 13M Long 12 Aluminum Binding Wire 13 Barbed Wire 14 Read Oxide Paint 15 Aluminium Paint 16 M.S. Bolts Nuts & Washers 17 Earth Wire Clamp With Nut & Bolts 18 Eye Bolt 19 Concreting Of Support 20 Stone Pad ( 300×300×75 ) Mm 21 Turn Buckle 22 Guarding Angle 75×75×8 23 Gi Wire 16Swg For Binding 24 Supply Of Heat Shrinkable Out Door Jointing Kits Suitable For 11Kv, 3X300q.Mm Xlpe Cable ( Raychem / Densionor Pvvnl Approved Vender ) . 25 33 Kv Line Isolator 26 2. Safe Carriage Of With Loading & Unloading At Both Ends Respectively. ( Under Jurisdiction Of Pvvnl ) A ) Steel Tublar Pole Sp-72 13M ( Bottom Portiongalvanized ) 27 2. Safe Carriage Of With Loading & Unloading At Both Ends Respectively. ( Under Jurisdiction Of Pvvnl ) A ) Steel Tublar Pole Sp-72 13M ( Bottom Portiongalvanized ) 28 D ) 33 Kv Pin Isulators ( Polymer ) 29 E ) Acsr Dog Conductor 30 F ) 33 / 11 Kv, 10Mva Transformer 31 G ) 11Kv Xlpe Cable 3X300mm² 32 H ) 33Kv, 3×300Mm² Xlpe Cable 33 4. Dismantling Of Existing ( 5 Mva-1 Nos ) Transformer Keptat Suitable Place Outside Switchyarda ) Disconnecting Ht Cable Connection From 33Kv Side &11Kv Side Of 05Mva Power Transformer For Removing Power Transformer From Plinth After Proper Shutdown. Dismantling Of 11Kv Cable Support Structure, Copper Bus Bar Structure, M.S.Frame Etc. 34 B ) Disconnecting Copper Flexible / Earthing Strip From Power Transformer Neutral & Dismantling Neutral Earthing Systemto Facilitate Removal Of Power Transformer From Plinth. 35 C ) Disconnecting Earthing Strip From Body Of 05Mva Power Transformer 36 D ) Draining Of Transformer Oil From Conservator, Radiators Of Existing 05 Mva T / F, At 33 / 11 Kv S / S Hussen Basti ( Sre ) Into The Dry & Clean Drums And Stacking At The Safe Place In Substation Outside Of Switchyard. Empty Drums Shall Be Provided By Contractor. 37 E ) Removal Of Conservator, Radiators And Other Accessories From Existing 05 Mva Power Transformer. 38 F ) Safe Shifting Of 05 Mva Power Transformer Main Body And Other Accessories From The Substation Switchyard To Outside The Switchyard At Suitable Place Assigned By Concern J.E / S.D.O ( Distribution ) . 39 G ) Re-Assembling Of Conservator, Radiators And Other Accessories To Existing 05 Mva Power Transformer. 40 H ) Re-Filling The Transformer Oil ( Old & Used In Existing 5Mvat / F ) 41 5 Miscellaneous Electrical Works Of Increasing Capacity Of 33 / 11 Kv Substation Hussen Basti ( Saharanpur ) ( 2×5 ) To ( 10+5 ) Mva.Installation Of 33 / 11 Kv, 10 Mva Transformer :A ) Shifting Of Available 10 Mva 33 / 11 Kv, Transformer To Transformer Plinth In Switch Yard. 42 B ) Erection Of Shifted Transformer At Plinth By Fixing All Accessories Like Radiators, Conservator Tank, Filling The Transformer Oil To Desired Level And Ensuring That There Is No Leakage, Complete Job In All Respect. 43 6. Water Level Earthing By Boring And Lowering Of G.I. Pipe Size 40 Mm Dia & Thickness 2Mm Into The Ground At 20 Mtr Depth Or Upto The Water Level With The Lower End Of Solid Copper Cone Approx 225 Mm Long And 750 Gm In Weight Shall Be Provided And Screwed In Pipe As Well As Bringing Out A Continuous Copper Wire 6 Swg From The Cone Up To The Ground Surface Where It Will Be Bolted To The G.I. Earth Strip For Transformer Neutral Connection, The Earth Strip Will Be Welded To The G.I. Pipe And Neutral Earthing Support. 44 B ) Fabrication And Erection Of Neutral Earthing L Type Support Made Of M.S. Channel Size 100X50mm. Structure Shall Be 4 Mtr. Long With 1 Mtr. Arms And 0.75Mtr Bracing. Structure Shall Be Grouted In Ratio 1:3:6 In Block Size 300X300x1000mm Including Plinth And Painted With One Coat Of Ready Mixed Primer And Two Coat Of Enamel Aluminium Paint Work Includes Connecting Neutral Bushing Rod Of Power Transformer And M.S. Earthing Strip With The Help Of Flexible Copper Bond, M.S. Bolt And Washer With Stone Pad Of Size ( 300X300x75mm ) . 45 7.Ai ) Fabrication And Erection Of Cable Support Made Of Two Pieces Of M.S. Channel ( 100X50x6 ) Mm, 2.75 Meter Long, Joined To Each Other By Means Of 5 Nos. M.S. Angle ( 50X50x6 ) Mm Pieces Of Size 0.75Mtr Long Each By Welding At Equal Intervals And Grouting In A Block Of Size ( 300X1000x1000 ) Mm In C.C. 1:3:6 Complete With One Coat Of Ready Mixed Primer And Two Coats Of Al. Paint. Work Includes Providing Of Three Nos. M.S. Clamps Made Of ( 50X6 ) Mm M.S. Flat For Holding The Cable Including Nuts And Bolts With Stone Pad Of Size ( 300X300x75mm ) . 46 B ) Fixing 110Mm Dia 2Mm Thick 2M Long G.I.Pipe Over 11Kv, 3X300sq.Mm Xlpe Cable Before Mounting The 2No. Cable On Cable Support Structure. Work Includes Fixing Of Clamp, Sealing Of Top And Bottom End Of The G.I.Pipe. One End Of G.I.Pipe Is To Be Buried Under Earth About 500Mm. 47 Fabrication Of Copper Bus Bar Of Size ( 2500×50×6 ) Mm In L.V. Side Of 10 Mva 33 / 11 Kv, Power Transformer. Work Includes Connection Of Outside Bus Bar In L.V. Side Busing Rod Of Power Transformer And Other Side With Outdoor 11 Kv Cable Box As Well As Providing Empire Tape And H.T. Tape Etc. For Proper Insulation Work. 48 Preparation Of 11 Kv Power Cable Ends:Making Ofcable End Termination By Heat Shrinkable Out Door Jointing Kits Suitable For 11Kv, 3X300q.Mm Xlpe Cable. Providing, Fixing And Crimping Of Proper Size Good Quality Lugs Complete In All Respect. 49 Making Ofcable End Termination By Heat Shrinkable Indoor Jointing Kits Suitable For 11Kv, 3X300q.Mm Xlpe Cable.Providing, Fixing And Crimping Of Proper Size Good Quality Lugs Complete In All Respect. 50 Installation Of 33 Kv Isolators With Structure:Assembling And Installation Of Line Isolator On The Isolator Structure. Adjusting Of Operating Mechanism In Proper Alignment So As To Ensure Smooth Operation Of The Same. In Case Of Line Isolator Proper Operation Of Earth Links Shall Also Be Ensured. The Work Includes Fabrication For Proper Fixing If Required. 51 Erection Of Following Materiala- Erection Of Support After Excavation Of Foundation Pit In Mix Soil / Normal Soil / Soft & Hard Rock And Its Back Filling And Leveling Etc. The Size Of The Pit Will Be ( 900×600 ) Mm And Having Depth Of 1 / 6Th Of The Full Length Of The Support & Erection Of Support. The Work Includes Carriage And Handling Of Supports From Site Store To Pit Site. ( I ) 13 M Long Stp, Sp-72 Round Pole 52 B- Fixing Of All Clamps, Cross Bracing Sets 3.5 Mtr. From M.S. Angle 65×65×6Mm / 50×50×6Mm & Other Accessories On The Supports As Per Drawing. Work Includes Cutting Of Holes And Providing M.S. Bolts Of 16×40Mm Size In The Middle Of Cross Bracing With 1 No. Spring Washer. The Work Also Includes Carriage & Handling Of Accessories From Sectional Store To Pit Site As Well As Any Fabrication Work If Required. ( I ) Single Pole ( A ) 13 M Long Stp, Sp-72 Round Pole 53 Grouting Of Supports In Cc 1:4:8 ( Cement, Sand & 40 Mm Brick Ballast ) Grouting Will Be Done In The Block Of Size ( 450×450 ) Mm ×1 / 6Th Of Full Length Of The Support, Up To Ground Level, 300 Mm Plinth Above The Ground Level With C.C. 1:3:6 ( Cement, Course Sand And Stone Grit ) With Muffing As Per Drawing, Work Includes Back Filling And Proper Ramming. ( I ) 13 M Long Stp, Sp-72 Round Pole 54 Earthing Of Supports With Ms Earth Rod Of ( 20×2500 ) Mm Long Including Excavation Of Pit And Driving M.S. Rod 3.0 M Apart From Support And 0.5M Below The Ground Level And Connecting Below The Earth Electrodes With The Help Of G.I. Wire No. 8 Swg And Earthing Lugs. 55 Guarding Between Two Poles Like Single Poles, Double Poles, Four Poles, Etc. To Guard Lt, 33 Kv Line Telephone And River Crossing, Road Crossing Etc. With G.I. Wire No. 6 Swg And G.I. Wire No. 8 Swg, Including Cutting With Fabrication And Fixing Of Guarding Channel With Clamps Nut & Bolts Etc. As Per Drawing. 56 Laying, Spreading, Lifting And Final Sagging Of 3 Phases Of Acsr Dog Conductor In Accordance With Profile And Sag Chart Including Binding, Jumpering And Fixing Of P.G. Clamp As Per Requirement In 03 Nos. Conductor In Parallel. 57 Providing & Fixing Of Danger Board At Each Location As Per Specification Of The Drawing With Clamps Etc. 58 Painting Of Following Supports / Structures With 2 Coats Of Synthetic Enamel Paint After One Coat Of Ready Mix Primer Including Cost Of All Material, As Well As Rubbing / Cleaning Of Surface As Required For Proper Completion Of Work. Painting Will Be Done By Post Office Red Paint From Top To Cross Arm And Remaining By Aluminium Paint. ( A ) 13 Mtr, Sp-72 Poles Including All Channels / X-Arms / Clamps Etc ( I ) Single Supports 59 Wrapping Of Barbed Wire On 33 Kv Pcc Poles / Sp-55 St & Sp-72 St Poles As Anti-Climbing Device For A Length Of 0.9 Mtr., Wire Pitch / Gap 13Mm And Fixing Upper And Lower End Keeping Lower End At A Height Of 2.75 Mtr. From The Ground Complete With Supply And Fixing Of Lower End & Upper End Clamps Made Of M.S. Flat 40×5Mm Complete With Nuts & Bolts & All Other Required Material. 60 Numbering Of Each Supports By Preparing Background With Dark Yellow Paint In The Size Of 150Mm Dia And Writing Support Number 100Mm High With Black Paint. 61 Material Required Locl Store. ( Site To Store Saharanpur ) 62 Supply & Fixing Of Stone Pad ( 300×300×75 ) Mm 63 Power T / F Plinth Repair

Key Value

Document Fees
INR 3540 /-
EMD
INR 15500.0 /-
Tender Value
Refer document

BOQ Items

Name of Work:-Schedule of Work/Technical specification for Misc (1) Pole installation work on 33 KV line MANDI SAMETI ROAD (2) Increasing Capacity of 33/11 KV Substation Hussen Basti (Saharanpur) (2×5) to (10+5) MVA.
Sl. No. Item Description
11. Supply of following material G.I. Angle (65×65×6)mm
2G.I. Channel (100×50)mm
3G.I Wire No. 6 SWG
4G.I Wire No. 8 SWG
5M.S. Earthing Rod
6V Type Cross Arm 33 KV
7Cross Arm Holding clamp for PCC Pole 9 M + S.T. Pole 11 M long & 13M long
8Guarding Clamp for S.T. Pole 11 M & 13M long
9F Bracket for 33 KV
10Danger Board with clamp for PCC Pole 9 M + S.T. Pole 11 M long & 13M long
11Number Plate with clamp for PCC Pole 9 M + S.T. Pole 11 M long & 13M long
12Aluminum Binding wire
13Barbed wire
14Read Oxide Paint
15Aluminium paint
16M.S. Bolts Nuts & Washers
17Earth wire clamp with Nut & Bolts
18Eye bolt
19Concreting of support
20Stone pad (300×300×75)mm
21Turn Buckle
22Guarding Angle 75×75×8
23GI wire 16SWG for binding
24Supply of Heat shrinkable Out door jointing kits suitable for 11KV, 3x300q.mm XLPE cable (Raychem / Densionor PVVNL Approved vender).
2533 KV Line Isolator
262. Safe carriage of with loading & unloading at both ends respectively. (under jurisdiction of PVVNL) a) Steel Tublar Pole SP-72 13M (Bottom PortionGalvanized)
272. Safe carriage of with loading & unloading at both ends respectively. (under jurisdiction of PVVNL) a) Steel Tublar Pole SP-72 13M (Bottom PortionGalvanized)
28d) 33 KV Pin Isulators(Polymer)
29e) ACSR Dog Conductor
30f) 33/11 KV,10MVA Transformer
31g) 11KV XLPE cable 3x300mm²
32h) 33KV,3×300mm² XLPE Cable
334. Dismantling of Existing ( 5 MVA-1 Nos) Transformer Keptat suitable place outside switchyard a) Disconnecting HT cable connection from 33KV side &11KV side of 05MVA Power transformer for removing power transformer from plinth after proper shutdown. Dismantling of 11KV cable support structure, copper bus bar structure, M.S.Frame etc.
34b) Disconnecting copper flexible/Earthing strip from Power transformer neutral & Dismantling neutral earthing systemto facilitate removal of Power transformer from plinth.
35c) Disconnecting Earthing strip from body of 05MVA Power transformer
36d) Draining of transformer oil from conservator, radiators of existing 05 MVA T/F, at 33/11 KV S/S Hussen Basti (SRE)into the dry & clean drums and stacking at the safe place in Substation outside of switchyard. Empty drums shall be provided by contractor.
37e) Removal of conservator, radiators and other accessories from existing 05 MVA Power transformer.
38f) Safe Shifting of 05 MVA Power transformer main body and other accessories from the substation switchyard to outside the switchyard at suitable place assigned by concern J.E/S.D.O (Distribution).
39g) Re-assembling of conservator, radiators and other accessories to existing 05 MVA Power transformer.
40h) Re-filling the transformer oil (old & used in existing 5MVAT/F)
415 Miscellaneous Electrical works of Increasing Capacity of 33/11 KV Substation Hussen Basti (Saharanpur) (2×5) to (10+5) MVA. Installation of 33/11 KV, 10 MVA Transformer : a) Shifting of available 10 MVA 33/11 KV, Transformer to transformer plinth in Switch Yard.
42b) Erection of shifted Transformer at plinth by fixing all accessories like radiators, conservator tank, filling the transformer oil to desired level and ensuring that there is no leakage, complete job in all respect.
436. Water level earthing by Boring and lowering of G.I. pipe size 40 mm dia & thickness 2mm into the ground at 20 Mtr depth or upto the water level with the lower end of solid copper cone Approx 225 mm long and 750 gm in weight shall be provided and screwed in pipe as well as bringing out a continuous copper wire 6 SWG from the cone up to the ground surface where it will be bolted to the G.I. earth Strip for Transformer neutral connection, the earth strip will be welded to the G.I. pipe and neutral earthing support.
44b) Fabrication and erection of neutral earthing L Type support made of M.S. Channel size 100x50mm. Structure shall be 4 Mtr. long with 1 Mtr. Arms and 0.75Mtr bracing. Structure shall be grouted in ratio 1:3:6 in block size 300x300x1000mm including plinth and painted with one coat of Ready Mixed primer and Two coat of enamel Aluminium paint work includes connecting neutral bushing rod of power Transformer and M.S. Earthing strip with the help of flexible copper bond, M.S. Bolt and washer with stone Pad of size (300x300x75mm).
457.ai) Fabrication and erection of cable support made of two pieces of M.S. Channel (100x50x6)mm, 2.75 meter long, joined to each other by means of 5 Nos. M.S. Angle (50x50x6) mm pieces of size 0.75Mtr long each by welding at equal intervals and grouting in a block of size (300x1000x1000)mm in C.C. 1:3:6 complete with one coat of ready mixed primer and two coats of Al. paint. Work includes providing of three Nos. M.S. clamps made of (50x6)mm M.S. Flat for holding the cable including nuts and bolts with stone Pad of size (300x300x75mm).
46b) Fixing 110mm dia 2mm thick 2M long G.I.Pipe over 11KV, 3x300Sq.mm XLPE Cable before mounting the 2No. Cable on cable support structure. Work includes fixing of Clamp, sealing of top and bottom end of the G.I.Pipe. One end of G.I.Pipe is to be buried under earth about 500mm.
47Fabrication of copper bus bar of size (2500×50×6)mm in L.V. side of 10 MVA 33/11 KV, power transformer. Work includes connection of outside bus bar in L.V. side busing rod of Power Transformer and other side with outdoor 11 KV cable box as well as providing empire tape and H.T. tape etc. for proper insulation work.
48Preparation of 11 KV Power Cable ends: Making ofcable end termination by Heat shrinkable Out door jointing kits suitable for 11KV, 3x300q.mm XLPE cable. Providing, fixing and crimping of proper size good quality lugs complete in all respect.
49Making ofcable end termination by Heat shrinkable indoor jointing kits suitable for 11KV, 3x300q.mm XLPE cable.Providing, fixing and crimping of proper size good quality lugs complete in all respect.
50Installation of 33 KV Isolators with Structure: Assembling and installation of Line Isolator on the isolator structure. Adjusting of operating mechanism in proper alignment so as to ensure smooth operation of the same. In case of Line Isolator proper operation of earth links shall also be ensured. The work includes fabrication for proper fixing if required.
51Erection of Following material A- Erection of support after excavation of foundation pit in mix soil/normal soil/soft & hard rock and its back filling and leveling etc. The size of the pit will be (900×600)mm and having depth of 1/6th of the full length of the support & Erection of support. The work includes carriage and handling of supports from site store to pit site. (i) 13 M Long STP, SP-72 Round Pole
52B- Fixing of all clamps, Cross Bracing Sets 3.5 Mtr. from M.S. Angle 65×65×6mm/50×50×6mm & other accessories on the supports as per drawing. Work includes cutting of holes and providing M.S. Bolts of 16×40mm size in the middle of cross bracing with 1 no. spring washer. The work also includes carriage & handling of accessories from sectional store to pit site as well as any fabrication work if required. (i) Single Pole (a) 13 M Long STP, SP-72 Round Pole
53Grouting of supports in CC 1:4:8 (Cement, sand & 40 mm brick ballast) Grouting will be done in the block of size (450×450)mm ×1/6th of full length of the support, up to ground level, 300 mm plinth above the ground level with C.C. 1:3:6 (Cement, Course sand and Stone grit) with muffing as per drawing, work includes back filling and proper ramming. (i) 13 M Long STP, SP-72 Round Pole
54Earthing of supports with MS earth Rod of (20×2500)mm long including excavation of pit and driving M.S. Rod 3.0 M apart from support and 0.5m below the ground level and connecting below the earth electrodes with the help of G.I. wire no. 8 SWG and earthing lugs.
55Guarding between two poles like single poles, double poles, four poles, etc. to guard LT, 33 KV Line telephone and river crossing, road crossing etc. with G.I. wire no. 6 SWG and G.I. wire no. 8 SWG, including cutting with fabrication and fixing of guarding channel with clamps nut & bolts etc. as per drawing.
56Laying, spreading, lifting and final sagging of 3 phases of ACSR Dog conductor in accordance with profile and sag chart including binding, Jumpering and fixing of P.G. Clamp as per requirement in 03 Nos. conductor in parallel.
57Providing & fixing of danger board at each location as per specification of the drawing with clamps etc.
58Painting of following supports/structures with 2 coats of synthetic enamel paint after one coat of ready mix primer including cost of all material, as well as rubbing/cleaning of surface as required for proper completion of work. Painting will be done by post office red paint from top to cross arm and remaining by Aluminium paint. (a) 13 Mtr, SP-72 Poles including all channels/X-Arms/Clamps etc (i) Single supports
59Wrapping of barbed wire on 33 KV PCC Poles/SP-55 ST & SP-72 ST Poles as anti-climbing device for a length of 0.9 Mtr., wire pitch/gap 13mm and fixing upper and lower end keeping lower end at a height of 2.75 Mtr. from the ground complete with supply and fixing of lower end & upper end clamps made of M.S. Flat 40×5mm complete with nuts & bolts & all other required material.
60Numbering of each supports by preparing background with dark yellow paint in the size of 150mm dia and writing support number 100mm high with black paint.
61Material required Locl store.(Site to Store Saharanpur)
62Supply & Fixing of Stone Pad (300×300×75)mm
63Power T/F Plinth Repair
Disclaimer :
We takes all possible care for accurate & authentic tender information, however Users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender.
Tell us about your Product / Services,
We will Find Tenders for you

Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy

For Tender Information Services Visit : TenderDetail