Urban Local Bodies has published Construction Of Rcc Box Culvert And Side Drain At South-East Corner Of Sedho Pukur In Ward No-21 Under Bolpur Municipality.. Submission Date for this Tender is 01-11-2023. Culvert Tenders in bolpur West Bengal. Bidders can get complete Tender details and download the document.
Sl. No. | Item Description |
1 | Dismantling R.C. floor, roof, beams etc. including cutting rods and removing rubbish as directed within a lead of 75 m. including stacking of steel bars.(a) In ground floor including roof. |
2 | Dismantling all types of masonry excepting cement concrete plain or reinforced, stacking serviceable materials at site and removing rubbish as directed within a lead of 75 m. (a) In ground floor including roof. |
3 | Dismantling all types of plain cement concrete works, stacking serviceale materials at site and removing rubbish as directed within lead of 75 m. In ground floor including roof. (a) Upto 150 mm thick. |
4 | Earth work in excavation of foundation trenches or drains, in all sorts of soil (including mixed soil but excluding laterite or sandstone) including removing, spreading or stacking the spoils within a lead of 75 m. as directed. The item includes necessary trimming the sides of trenches,levelling, dressing and ramming the bottom,bailing out water as required complete.(a) Depth of excavation not exceeding 1,500 mm. |
5 | (A) Filling in foundation or plinth by silver sand in layers not exceeding 150 mm as directed and consolidating the same by thorough saturation with water, ramming complete including the cost of supply of sand. (payment to be made onmeasurement of finished quantity).(B) Do - by fine sand |
6 | Supplying and laying Polyhtene Sheet (150 gm/Sq.m) over damp prrof course or below flooring or roof terracing or in foundation or in foundation trenches. |
7 | Hire and labour charges for shuttering with centering and necessary staging upto 4 m using approved stout props and thick hard wood planks of approved thickness with required bracing for concrete slabs, beams and columns, lintels curved or straight including fitting, fixing and striking out after completion of works (upto roof of ground floor).(f) 25 mm to 30 mm shuttering without staging in foundation |
8 | (a) 25 mm to 30 mm thick wooden shuttering as per decision & direction of Engineer-in-chrge. |
9 | Ordinary Cement concrete (mix 1:1.5:3) with graded stone chips (20 mm nominal size) excluding shuttering and reinforcement if any, in ground floor as per relevant IS codes.(i) Pakur Variety |
10 | Water Bound Macadam Sub Base : Water Bound Macadam Sub Base by consolidating Jhama metal / Laterite chelly or stone metal /shingles of specific size in hard crust to requisite thickness (measured after compaction) in layers including screening of metals etc. as necessary, hand packing, sweeping, watering and rolling in stages with power roller to proper line, grade and camber, lighting, guarding & barricading and making necessary earthen bundh of one metre width on each side where necessary to protect edges and preparing the bed by necessary cutting or filling and rolling all complete including the cost of all materials and hire and labour charges of all men and machineries and compacting to the required density, as per Clause 404 of Specifications for Road & Bridge Works of MoRT&H (5th Revision). (i) For Construction of Sub Base by consolidating Jhama metal (63 mm to 45 mm) with moorum screening : |
11 | Ordinary Cement Concrete (mix 1:2:4) with graded stone chips (20mm nominal size) excluding shuttering and reinforcement, if any, in ground floor as per relevent IS codes. (a) Pakur Variety |
12 | Reinforcement for reinforced concrete work in all sorts of structures including distribution bars, stirrups, binders etc initial straightening and removal of loose rust (if necessary), cutting to requisite length, hooking and bending to correct shape, placing in proper position and binding with 16 gauge black annealed wire at every intersection, complete as per drawing and direction. (a) For works in foundation, basement and upto roof of ground floor/upto 4 m. (i) Tor steel/Mild Steel(ii) JSW/SPL/SHYAM/SRMB/...... |
13 | Removal of rubbish,earth etc. from the working site and disposal of the same beyond the compound, in conformity with the Municipal / Corporation Rules for such disposal, loading into truck and cleaning the site in all respect as per direction of Engineer in charge |
14 | Construction of Steel structure openable covered frame over existing drain for smooth cleaning of sludge at time to time, work executed as per decision of E-i-C.Details specified in Annexure-A. |
15 | ADD 18 % GST |
16 | ADD 1% CESS |